Obligations that cannot be secured by planning condition
Conditions prevent things well and require things badly. Payments, affordable housing, off-site works and long-term maintenance all have to be secured by obligation rather than condition.
A planning condition cannot require anybody to pay money. That single rule decides most of the condition or planning obligation question, because the moment a scheme needs a financial contribution, an in-perpetuity commitment or anything done on land outside the application site, the authority has to put it in a section 106 agreement instead.
The six tests for conditions in Planning Practice Guidance are familiar: necessary, relevant to planning, relevant to the development permitted, enforceable, precise, and reasonable in all other respects. Enforceability is where most failed conditions come apart, and it is worth understanding why before you agree to one.
Why a condition cannot require a payment
Breach of condition is enforced through a breach of condition notice under section 187A of the Town and Country Planning Act 1990, or through an enforcement notice requiring steps to remedy the breach. Neither mechanism can recover a sum of money. There is no judgment debt, no charge on the land, nothing to sue on.
So a condition saying "the developer shall pay £40,000 towards off-site highway works prior to first occupation" is unenforceable, and an unenforceable condition fails the fourth test. Inspectors delete these on appeal with little discussion.
The workaround authorities sometimes reach for is a negative condition: no occupation until the contribution has been paid. That is enforceable in form, because you can enforce against occupation. Whether it is reasonable is another matter, and a condition whose only purpose is to compel a payment the authority could not require directly tends to fail the reasonableness test. Expect argument rather than a clean answer.
Positive obligations and the enforcement gap
Conditions work well at preventing things and badly at requiring them over time. You can condition that no development takes place until a drainage scheme is approved. You cannot usefully condition that a management company maintains the attenuation basin for 30 years.
The gap is the same one: enforcement against a continuing positive duty needs somebody identifiable to enforce against, and a planning unit that has been sold into 40 freehold titles no longer has one. Section 106 solves this because an obligation under section 106 is a covenant that runs with the land and binds successors in title, and the authority can enforce it by injunction or by entering the land and recovering its costs.
The practical list of matters that have to go into an agreement rather than a condition is short and stable.
- Financial contributions of any kind, including index-linked ones
- Affordable housing tenure, mix, transfer terms and nomination rights
- Works or land outside the application site, including off-site highway and open space works
- Long-term management and maintenance commitments
- Monitoring and review mechanisms, including viability review clauses
- Restrictions on occupation tied to a register or allocation policy
Affordable housing is the clearest case. The tenure split, the transfer price, the provider's requirements and the fallback if no provider comes forward all need contractual drafting, which is why an affordable housing cascade mechanism lives in the agreement and not in a condition.
Land outside the application site
A condition can only regulate the development permitted. Where the necessary works sit on third party land, the authority has two routes.
The first is a Grampian condition: a negative condition preventing commencement or occupation until specified off-site works have been carried out. This is lawful and widely used, and the test applied on appeal is whether there is a reasonable prospect of the works being delivered within the lifetime of the permission. If the land is in the ownership of an unwilling third party and no agreement is in sight, the condition fails that test and the application is likely to be refused instead.
The second is a section 106 agreement signed by the landowner of the off-site land as well as the applicant. That is the cleaner answer where the off-site owner is cooperative, and it is the only answer where the obligation is positive and continuing.
Highway works are the recurring complication, because they usually need a section 278 agreement with the highway authority as well. The planning obligation secures the commitment to enter into the section 278, and the section 278 governs the works themselves. Where the boundary between the two sits is set out in section 278 agreements and where a section 106 starts.
Choosing between the two
Where both routes are available, a condition is the default. Planning Practice Guidance is explicit that planning obligations should only be used where it is not possible to address unacceptable impacts through a condition, and the Community Infrastructure Levy Regulations 2010 add the statutory tests that an obligation must be necessary to make the development acceptable, directly related to it, and fairly and reasonably related in scale and kind.
A condition is faster, costs nothing in legal fees, and can be varied under section 73 with an appeal right if the authority refuses. An obligation needs solicitors on both sides, the authority's legal costs paid by the applicant, and a deed of variation to change later. On a scheme of 15 units, the difference between a conditioned drainage scheme and a drainage obligation with a management company can be six weeks and several thousand pounds.
| Matter | Condition | Obligation |
|---|---|---|
| Approval of details before works start | Yes | Not needed |
| Restriction on hours, use or occupation | Yes | Not needed |
| Payment of a contribution | No | Yes |
| Affordable housing delivery and tenure | No | Yes |
| Off-site works on third party land | Grampian only | Yes, with that owner as a party |
| Long-term maintenance | No | Yes |
| Viability review after a trigger date | No | Yes |
Unilateral undertakings and their limits
A unilateral undertaking is an obligation given by the applicant and landowner without the authority as a signatory. It is the standard tool at appeal, where you cannot force an authority to engage in drafting before the inspector decides.
The limit is that an undertaking can only contain obligations the giver can perform. It cannot bind the authority to do anything, so it cannot include council obligations such as a duty to spend a contribution on a specified project within a period, or to repay it if unspent. That matters: a contribution paid under a unilateral undertaking with no repayment clause is gone.
Undertakings are also harder to negotiate after the event, because the authority never agreed the wording. If an inspector finds an undertaking defective, the usual outcome is that the obligation carries no weight and the appeal falls with it.
Where this goes wrong in practice
Three failures recur.
Authorities ask for a condition requiring a payment, usually a monitoring fee, and nobody challenges it. The condition sits on the permission unenforceable, and at discharge stage somebody notices.
Agreements include matters that should have been conditions, which inflates legal costs and makes later variation harder than it needed to be. Drainage details, materials and landscaping belong on the permission.
And obligations get drafted against triggers that do not work on the ground, which is a drafting problem rather than a legal one. If the trigger is first occupation of the tenth dwelling on a site built out in two phases of 20, somebody has to be counting. The practical fixes are set out in section 106 phasing triggers and what they key to.
When you are sorting one from the other, read the authority's draft heads of terms against the six tests and the three regulation 122 tests before you accept anything. A planning statement that sets out which matters you accept as conditions and which you accept as obligations, with reasons, saves a round of correspondence later.
This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. See PlanScope pricing if you want to know what a draft supporting statement costs.
Frequently asked questions
Why can a planning condition not require a financial contribution?
Because there is no way to enforce it. Breach of condition is pursued through a breach of condition notice under section 187A of the Town and Country Planning Act 1990 or an enforcement notice requiring remedial steps, and neither can recover money. A condition requiring payment therefore fails the enforceability test in Planning Practice Guidance and inspectors routinely delete it on appeal.
What is a Grampian condition?
A negative condition that prevents development starting or being occupied until specified works have been carried out, usually on land outside the application site. It is lawful, and the test on appeal is whether there is a reasonable prospect of the works being delivered within the life of the permission. Where the land belongs to an unwilling third party, that test is not met.
Should drainage details be a condition or a section 106 obligation?
Approval of the drainage scheme before works start is a condition, because it prevents something until details are agreed. Long-term maintenance of the drainage infrastructure is an obligation, because it is a continuing positive duty that has to bind successors in title. Many schemes need both, and splitting them correctly keeps legal costs down.
What are the limits of a unilateral undertaking?
It can only contain obligations the giver can perform, so it cannot bind the council to anything. That means no duty on the authority to spend a contribution on a named project, and no repayment clause if the money is not spent. Undertakings are the standard tool at appeal because the authority cannot be compelled to negotiate drafting beforehand.
Is a condition quicker and less costly than a section 106 obligation?
Usually, yes. A condition costs nothing in legal fees and can be varied under section 73 with an appeal right if the authority refuses. An obligation needs solicitors on both sides, the authority's legal costs paid by the applicant, and a deed of variation to change later. Planning Practice Guidance also prefers conditions where they would work.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.