Section 278 agreements and where a section 106 starts

Updated 6 min readBy PlanScope Editorial Team

Works in the public highway go through a section 278 agreement, obligations on your land through a section 106, and adopted streets through a section 38. Here is the join.

The section 278 or section 106 question has a clean answer at the boundary and a messy one in the middle. Works in the existing public highway are delivered under a section 278 agreement with the highway authority under the Highways Act 1980. Obligations that restrict or require something on your land, or that secure a payment towards something off it, sit in a section 106 planning obligation with the local planning authority. New streets that will be adopted go through a section 38 agreement.

Three agreements, three different teams, and on a two-tier authority two different councils. Which is where most of the confusion comes from.

What a section 278 agreement covers

Section 278 lets a highway authority enter into an agreement with a developer for works to be carried out in the public highway at the developer's expense. The authority remains responsible for the highway. The developer funds, and usually constructs under licence, the alterations the development makes necessary.

Typical content: a new or widened access, a right-turn lane, a signalised junction or signal modification, a pedestrian crossing, footway widening and resurfacing, kerb realignment, drainage alterations within the highway, traffic signs and markings, and street lighting.

The process has its own gates. Technical approval of the design, a safety audit, an agreement with a fee for checking and supervision, a bond or surety, and in some cases a commuted sum towards future maintenance of anything that is not a standard highway item.

On the strategic road network the counterparty changes. National Highways controls those routes, and the national policy on development affecting the strategic network sets the approach it takes, so an access onto a trunk road is a different conversation from one onto a borough road.

What a section 106 obligation can secure

A planning obligation can restrict the use of land, require operations or activities, require land to be used in a specified way, or require a payment. It binds the land, so it passes to successors in title.

Crucially, it must meet the statutory tests for a planning obligation: necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind. Those tests, in the levy regulations, are why a highway contribution has to be justified against an identified scheme rather than requested as a round number.

Where an obligation relates to highways, it generally does one of three things:

  • Secures a financial contribution towards works the authority will deliver itself.
  • Requires the developer to enter into a section 278 agreement and complete the works by a defined trigger.
  • Secures a travel plan, monitoring, and sometimes travel vouchers or car club provision.

That second one is the join between the two regimes. The obligation is the planning hook, the section 278 agreement is the delivery mechanism, and they have to be drafted to match.

Works in the highway and works on site

Item Normal route
New access from the public highway Section 278
Internal estate roads to be adopted Section 38
Internal roads to stay private Planning condition and the layout drawings
Dropped kerb for a single dwelling Section 184 vehicle crossing application
Off-site junction improvement delivered by the council Section 106 contribution
Footway link across third party land Section 106, plus land acquisition
Stopping up a highway to allow development Order under the planning Act
Travel plan and monitoring Section 106

The boundary that trips people up is the site access itself, because it starts on your land and ends in the highway. The part within the highway boundary is section 278 work. The part on your land is built under the planning permission. Get the highway boundary confirmed in writing before the design is fixed, because it is rarely where the fence is.

Section 38 adoption of new streets

Where new streets are to become publicly maintainable, a section 38 agreement is the route. The authority approves the design to its own standards, the developer builds it, a maintenance period runs, and the street is then adopted.

Expect: design standards that may differ from the layout the planning permission approved, a bond covering the cost of completion if the developer fails, inspection fees, a defined maintenance period before adoption, and a commuted sum for non-standard items such as unusual surfacing or specialist street furniture.

The common conflict is between a planning-led layout, with narrow streets, shared surfaces and tight radii intended to slow traffic, and adoption standards written for maintenance and refuse access. Resolve it before the permission is issued, not after, because a street that cannot be adopted leaves the management company and the purchasers with the cost.

Bonds, inspection fees and commuted sums

These are real numbers in an appraisal and they are usually missed at feasibility stage.

Bonds are typically calculated as a percentage of the assessed works cost and are released in stages. Inspection and checking fees are charged by the authority on a published basis, so ask for their current fee schedule rather than estimating. Commuted sums apply where the authority will inherit something more expensive to maintain than a standard adopted street.

Add the design and safety audit costs to that. A full audit regime on a significant junction involves several stages, each with its own fee and each capable of sending the design back.

Sequencing the agreements against conditions

The order that works:

  1. Agree the access and off-site works in principle at pre-application stage with the highway authority, not just the planning officer.
  2. Settle the heads of terms for the obligation before the committee report is written.
  3. Complete the section 106 agreement before the decision notice issues.
  4. Start the section 278 technical approval process immediately after permission, because it runs on its own timetable.
  5. Complete the section 38 agreement before the first street is built, not after.
  6. Check the triggers: a condition requiring the access to be completed before first occupation depends on a section 278 timetable nobody has yet agreed.

Trip generation and the evidence behind the works come from the Transport Assessment or, on a smaller scheme, the Transport Statement. Where a travel plan is secured by obligation, the Travel Plan itself becomes a contractual document with monitoring attached, which is a different thing from an aspirational submission document.

Who negotiates each one

Planning obligations are negotiated with the local planning authority's planning and legal teams, with the highway authority consulted. Section 278 and section 38 agreements are negotiated with the highway authority's agreements team, which on a county or unitary authority may sit in a different directorate and keep a different timetable.

In a two-tier area the district is the planning authority and the county is the highway authority, so a developer runs two negotiations with two sets of lawyers. Budget for both. The most common programme failure on a small major is a permission granted in March and an access that cannot be built until the following spring because nobody started the technical approval, and where levy money is involved, the relationship with how the neighbourhood share is spent is a separate question again.

PlanScope can draft the transport and planning documents that support these negotiations, structured to policy, with trip figures and junction details flagged as to be confirmed until your transport consultant supplies them. Transport work is a report type where councils usually expect a suitably qualified author, so professional review is strongly advised.

This is general guidance, not legal advice. Fee schedules, bond rates and adoption standards are set locally and change, so check the current published position with the highway authority and take legal advice before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is the difference between a section 278 and a section 106?

A section 278 agreement under the Highways Act 1980 lets the highway authority allow works in the existing public highway at the developer's expense. A section 106 planning obligation binds the land and can restrict use, require works or secure a payment. A section 106 often requires the developer to enter a section 278 agreement, which is where the two meet.

When is a section 38 agreement needed?

Where new streets within a development are to become publicly maintainable. The authority approves the design to its own adoption standards, the developer builds it, a maintenance period runs and the street is then adopted. Internal roads that will stay private are controlled through the planning permission and layout drawings instead.

What tests must a planning obligation meet?

It must be necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind. Those statutory tests are why a highway contribution has to be justified against an identified scheme rather than requested as a round sum.

Who do I negotiate highway works with?

The highway authority's agreements team, which is separate from planning. In a two-tier area the district is the planning authority while the county is the highway authority, so there are two negotiations with two sets of lawyers. On the strategic road network the counterparty is National Highways instead.

What extra costs come with a section 278 or section 38?

Technical approval and checking fees, safety audit fees across several stages, inspection and supervision charges, a bond or surety calculated on the assessed works cost, and commuted sums where the authority will inherit non-standard items to maintain. Ask for the authority's current published fee schedule rather than estimating.

Sources and further reading

section 278section 106highwaysadoptionplanning obligationsaccess

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Viability, Obligations and Commercial

View all →
Viability, Obligations and Commercial7 min read

Agent of change obligations for a music or sports venue

Building homes beside an established venue means funding the mitigation. The split between conditions and obligations, noise deeds and their limits, and the drafting.

Read article →
Viability, Obligations and Commercial7 min read

Build cost indices and the date of the cost plan

Cost indices and tender price indices measure different things. How the base date, the index and the valuation date interact, and how to state the basis so it holds up.

Read article →
Viability, Obligations and Commercial6 min read

Professional fees and contingency in a development appraisal

Fees and contingency look like small lines in an appraisal and move the residual land value a long way. Both are tested, and both are defended with scope documents rather than convention.

Read article →
Viability, Obligations and Commercial7 min read

Transport contributions and the trip based calculation

Highway authorities build sustainable transport contributions from trip rates and mode share. Understanding how the figure is assembled is the only way to test whether it meets the statutory tests.

Read article →
Viability, Obligations and Commercial6 min read

Affordable housing on a site with a demolition credit

Twelve houses replacing four is twelve gross and eight net. Whether the threshold and percentage are read gross or net can be the whole margin, and the levy applies a separate floorspace test with its own timing trap.

Read article →
Viability, Obligations and Commercial6 min read

Nutrient neutrality mitigation cost in a viability appraisal

In an affected catchment, nutrient mitigation is a condition of consent rather than an enhancement. Price it per dwelling with a dated quotation, and model the securing obligation and the programme delay alongside it.

Read article →