Build cost indices and the date of the cost plan
Cost indices and tender price indices measure different things. How the base date, the index and the valuation date interact, and how to state the basis so it holds up.
The build cost index and the viability date you choose can move a residual land value by more than any argument about affordable housing percentages. A cost plan carries a base date, the date at which its rates were current. Bring that figure forward to a valuation date using the wrong index, or forward to the mid point of the build while holding sales values static, and you have manufactured a deficit the authority's consultant will find in an afternoon.
So state the base date on the first page of the cost plan, state the index, and state what you did with it. Most disputes about cost inputs are really disputes about one of those three things being left implicit.
Why the base date decides the argument
A cost plan priced in the second quarter of two years ago is not evidence of today's cost. It is evidence of that quarter's cost, which has to be adjusted. The adjustment is where the money is.
Three dates are in play and they are routinely confused:
- The base date of the cost plan, when the rates were current.
- The valuation date of the appraisal, normally the date the assessment is submitted or the date agreed with the authority.
- The mid point of the construction period, which some appraisals use as the point to which costs are inflated.
Planning Practice Guidance on viability expects costs to be based on evidence reflective of local market conditions, and points to recognised cost data as the source. It does not resolve which of those three dates to use, which is why the convention has to be set out rather than assumed.
Cost indices and tender price indices are not the same
This is the error that produces the largest swings. A general building cost index measures input costs: labour, materials and plant. A tender price index measures what contractors actually charge, so it carries contractor overheads, profit and the state of the market on top of those inputs.
In a market where contractors are busy and bidding selectively, tender prices rise faster than input costs. In a slack market they can fall while input costs rise. Using an input cost index in a tight market understates your real exposure, and using a tender price index in a falling market overstates it.
| Measure | What it tracks | Where it fits |
|---|---|---|
| General building cost index | Labour, material and plant input costs | Adjusting a cost plan built up from first principles |
| All-in tender price index | Prices contractors are winning work at | Adjusting a figure derived from tendered or benchmarked rates |
| Construction output price indices | Output prices across construction sectors | Cross-checking at a national level |
| Price index of private new housing | New build house prices | Value side, never the cost side |
The Building Cost Information Service publishes the first two and is the dataset Planning Practice Guidance refers to. The Office for National Statistics publishes construction output price indices and the price index of private new housing. Pick the measure that matches how your cost figure was derived, and say which one you picked.
Keeping costs and values on the same basis
The cleanest appraisal uses current costs and current values at a single valuation date, with no growth on either side. That is the approach Planning Practice Guidance points towards, and it is the one an authority's consultant will expect to see.
Problems start when the two sides are treated differently. Inflating costs to the mid point of a three year build while holding revenues at today's achieved prices builds in a negative margin that has nothing to do with the scheme. If you do run a cashflow with inflation on both sides, use defensible rates, state them separately for cost and value, and show the sensitivity. An appraisal that applies 4 per cent a year to costs and nothing to values is not a viability case. It is an arithmetic choice dressed as one.
Where the scheme really does face abnormal cost escalation, say so directly and evidence it with the specific items: a tendered groundworks package, a quoted remediation cost, an energy centre priced by a specialist. Named abnormals survive scrutiny far better than a general inflation uplift.
Updating a cost plan during a long determination
Major applications take months, and a cost plan that was current at submission may be a year old at committee. Two approaches work and one does not.
Re-running the appraisal on request works where the authority asks once, at a defined point, on an agreed basis. Agreeing a review mechanism in the section 106 works where the outcome is still uncertain, and the affordable housing cascade mechanism is often drafted alongside it so the tenure mix adjusts with the result.
What does not work is re-running the numbers every time an input moves. It costs fees, it signals that the figures are soft, and it invites the authority's consultant to pick the version least favourable to you.
Where a scheme has already stalled and the obligations were fixed on an older cost base, the route is different again, and the considerations in renegotiating obligations on a stalled scheme apply rather than a simple re-indexation.
When the authority's consultant uses a different source
Authorities commonly instruct a consultant who prices the scheme from published median rates per square metre of gross internal floor area, adjusted by a location factor. Your tendered figure may be higher. The gap is usually explicable, and four questions normally close most of it.
What does the published rate include? Median rates of that kind are typically for the building works alone, excluding external works, abnormal groundworks, professional fees, contingency and value added tax. If those are being added separately in one appraisal and sitting inside the rate in the other, you are comparing different things.
Has a location factor been applied, and which one? The same building costs materially different amounts in different parts of England, and the factor is published.
Is the rate for the right building type and storey height? A six storey block with a concrete frame and a single stair core does not price like a three storey timber frame terrace.
Is your tendered figure a real tender? A contractor's budget estimate from an early design is not the same evidence as a competitively tendered package, and claiming otherwise damages the rest of your case.
Where a real difference remains after those four, it is usually about contractor preliminaries, overheads and profit, and about whether the market the median reflects is the market you are actually buying in.
Stating the basis so it cannot be unpicked
Put a short basis of cost note in the Viability Assessment itself. It should give the base date of the cost plan, the index used and its published values at the base date and the valuation date, the location factor applied, the scope of what the rate covers, the abnormals listed separately with their evidence, and the fees, contingency and finance assumptions.
That note does two things. It lets the authority's consultant replicate your arithmetic, which removes a whole category of argument. And it protects you later, because when the scheme is reviewed in three years under a review mechanism, the person doing the review will not be you.
Reporting of this kind is what the RICS professional statement on conduct and reporting in financial viability work is aimed at, and an assessment that ignores it tends to carry less weight with an inspector. Where affordable housing is the issue in dispute, the Affordable Housing Statement should carry the same figures and the same dates, because a mismatch between the two documents is the first thing a reviewer notices.
Enter your postcode on PlanScope to see which reports your scheme is likely to need alongside the appraisal.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. For specialist technical reports, qualified professional input may be required. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
What is the base date of a cost plan?
It is the date at which the rates in the cost plan were current. Any adjustment to a later valuation date depends on that base date, so a cost plan without one cannot be checked. State it on the first page, alongside the index used and the published index values at both dates.
Should I use a building cost index or a tender price index?
Match the index to how the cost figure was derived. A general building cost index tracks labour, material and plant inputs and suits a cost plan built up from first principles. A tender price index tracks what contractors are actually charging, including overheads and profit, and suits a figure derived from tendered or benchmarked rates.
Can I inflate costs to the mid point of the build?
Only if you treat values the same way. Inflating costs across a three year programme while holding sales revenues at today's achieved prices creates a deficit that has nothing to do with the scheme. The cleaner approach is current costs against current values at a single stated valuation date, with sensitivities shown separately.
Why is the council's cost figure lower than my tender?
Usually because a published median rate per square metre covers the building works alone, excluding external works, abnormal groundworks, fees, contingency and value added tax, and because a location factor may or may not have been applied. Check the inclusions, the location factor, the building type and whether your figure is a real tender.
How often should a viability appraisal be updated during determination?
Once, at a defined point and on an agreed basis, or not at all if a review mechanism is secured in the section 106 instead. Re-running the figures every time an input moves costs fees, suggests the numbers are soft, and lets the authority's consultant choose the least favourable version.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.