Marketing evidence before a commuted sum is accepted
A commuted sum argument usually fails on the terms offered rather than on a lack of interest. Offer the units at the transfer value in your own appraisal, and record everything.
Before an authority accepts a commuted sum instead of affordable homes on site, it will want to see that registered providers were genuinely offered the units and genuinely declined. The marketing evidence commuted sum argument fails more often on the terms offered than on the lack of interest, because an authority that sees an offer priced to be refused will treat the exercise as a formality rather than a market test.
National policy treats on-site provision as the starting point, with off-site provision or a financial contribution requiring justification. The marketing exercise is how that justification is built.
Why authorities ask for marketing first
Affordable housing delivered on site produces mixed communities and homes in the location where the need was identified. A commuted sum produces money, which the authority then has to spend, often at a different price point and on a different site.
So the policy preference is structural rather than ideological. An authority agreeing a sum is accepting delivery risk, a time lag and a smaller number of homes for the same money. It is entitled to ask whether on-site delivery was really impossible.
Most section 106 agreements build this into a cascade: the units are offered to a registered provider on defined terms, and only if no provider contracts within a stated period does an alternative apply. The drafting of that cascade decides what the marketing has to prove, and our note on the affordable housing cascade mechanism sets out how the steps interlock.
Read the cascade before you start marketing. Marketing that does not match the clause proves nothing.
How long and how widely to market
There is no national standard, so the period and the audience come from the deed, the authority's supplementary planning document, or negotiation. Six months and a defined list of providers is a common shape.
Build the list properly:
- Every registered provider with existing stock in the district, from the regulator's register.
- Providers with stock in adjoining districts who have taken schemes of your size.
- Specialist providers where the units suit them, for example older persons or supported housing.
- The authority's own housing company or arm's length management organisation, where one exists.
- Any provider the authority names in its planning documents as a preferred partner.
Then approach each one in writing, with enough information for a real answer: unit schedule, floor areas, tenure split sought, service charge estimate, build specification, programme, and the proposed transfer value.
A marketing exercise aimed at four providers with national footprints and no local stock is the version authorities reject. Scale the list to the scheme, and record why anyone on the register was left off.
The terms, and why they decide the outcome
This is where the exercise is won or lost. The transfer value you offer has to be consistent with the appraisal you have given the authority.
| Term | What the authority checks |
|---|---|
| Transfer value per unit | Consistency with the viability appraisal and with local benchmarks |
| Tenure split | Whether it matches the policy mix or your preferred mix |
| Unit mix and sizes | Compliance with the nationally described space standard and local standards |
| Service charge | Whether it is deliverable for an affordable rented tenant |
| Programme and payment stages | Whether a provider could finance it |
| Building safety position | Fire strategy, cladding and gateway compliance for taller blocks |
A transfer value set at the top of the range, with payment on completion only, and a service charge driven by a lift and a concierge, will produce declines that say nothing about the market. The authority's adviser will read the offer letter as closely as the replies.
Where your appraisal assumes a particular transfer value, offer at that value. If the appraisal is wrong, change the appraisal, which is the discussion a Viability Assessment is for.
Recording approaches and responses
Keep a register from the first approach, not reconstructed afterwards. For each provider record the name, the date of the approach, the method, the material sent, the date of any response, the named individual who responded, and the reason given.
Then group the reasons, because the pattern is the evidence. Declines because the scheme is too small to manage, because the provider has no local presence, or because the mix does not suit their waiting list all point in different directions, and only some of them support a commuted sum.
Non-responses need handling honestly. A provider who did not reply has not declined, and an exercise where most of the list is silent suggests the approach did not reach decision makers. Follow up twice, by different routes, and record it.
Where a provider makes a conditional offer, that is interest. An offer at a lower transfer value than you wanted is a market answer, and presenting it as a decline is the kind of thing that unravels at committee.
Where the mix is the obstacle
Often the barrier is not price but product. A block of 30 one-bedroom flats in a district with a waiting list dominated by families is hard to place. Flats above commercial units with shared service charges are hard to place. Units pepper-potted across four cores with no management block are hard to place.
That is useful evidence, but it cuts both ways. If providers decline because the mix is wrong, the authority's first response will be to ask you to change the mix rather than to take money. Expect that question and answer it in advance: show what mix changes were tested, what they did to the scheme and to the appraisal, and why they were not pursued.
An illustrative example. A 48 unit scheme offers 12 affordable units, all one-bedroom, in a single core with a lift and a shared plant room, at a transfer value matching the appraisal. Eight providers are approached, two do not respond, four decline citing the absence of two and three-bedroom units, and two decline citing the service charge. The authority's likely answer is a revised mix with four two-bedroom units in place of six one-bedroom flats, not a commuted sum. The marketing was sound; the product was the problem.
Submitting the evidence
Assemble it as a standalone document rather than an appendix to the appraisal, because it will be read by the housing officer rather than the viability adviser.
- The relevant clause of the section 106 agreement, quoted.
- The provider list, with the basis on which it was compiled and any omissions explained.
- The offer letter and information pack as sent, dated.
- The register of approaches and responses, with the responses themselves appended.
- An analysis grouping the reasons for decline, and what was tested in response.
- The proposed sum, its calculation method, and the source of that method in the authority's own policy.
The calculation is the last item for a reason. A sum computed from the difference between open market value and the affordable transfer value, or from the cost of providing equivalent units elsewhere, has to follow a method the authority publishes. Picking a method that produces the lowest figure is the fastest route to a refusal.
Where the obligation is already in place and the scheme has moved on, the route is different, and our note on renegotiating obligations on a stalled scheme covers that position.
Set out the policy case and the evidence together in the Affordable Housing Statement, so the officer reads the marketing exercise alongside the need assessment rather than after it.
Market the units as if you wanted them taken. That is both the honest approach and the one that survives scrutiny.
This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.
Frequently asked questions
How long should affordable units be marketed to registered providers?
There is no national period, so it comes from the section 106 cascade, the authority's supplementary planning document or negotiation. Six months to a defined list of providers is a common shape. Read the cascade clause before starting, because marketing that does not match the terms in the clause does not discharge it.
Which registered providers should be approached?
Every provider with existing stock in the district from the regulator's register, providers in adjoining districts who take schemes of your size, specialist providers where the units suit them, and the authority's own housing company or preferred partners where it names any. Record why anyone on the register was left off the list.
Why do authorities reject marketing evidence?
Most often because the terms were never capable of attracting interest: a transfer value at the top of the range, payment on completion only, or a service charge that no affordable rented tenant could carry. The authority's adviser reads the offer letter as closely as the replies, so the offer has to match the viability appraisal.
Does a non-response count as a decline?
No. A provider who did not reply has not declined, and an exercise where most of the list is silent suggests the approach never reached decision makers. Follow up at least twice by different routes, record each attempt, and report non-responses separately from declines in the analysis.
How is the commuted sum itself calculated?
Usually from the difference between open market value and the affordable transfer value, or from the cost of providing equivalent units elsewhere, following a method the authority publishes in its policy or supplementary guidance. Choosing the method that produces the lowest figure, rather than the published one, invites refusal.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.