Section 278 works and how they sit in viability
Section 278 works cost more than the tarmac. How design and supervision fees, statutory undertaker diversions and commuted maintenance sums belong in a viability appraisal.
Section 278 works viability is one of the lines reviewers look at hardest, because it is the easiest place for a cost to be either missed or double counted. A section 278 agreement under the Highways Act 1980 covers works to the existing public highway carried out at the developer's expense where the highway authority is satisfied the works are of benefit to the public. The cost is real, it is more than the cost of the tarmac, and it does not sit inside a published build cost rate.
What a highway agreement covers
Two agreements usually appear on a residential scheme and they do different things. Section 278 covers alterations to the existing highway: the site access, a new junction, a signalised crossing, a footway widening, a right-turn lane, traffic calming, drainage alterations and street lighting. Section 38 of the same Act covers the adoption of new estate roads built within the site.
Treat them separately in the appraisal. Section 38 roads are usually inside the build contract and inside the construction cost, while section 278 works are off-site, carried out under the highway authority's technical approval and inspection, and priced separately.
Where the boundary between them sits is not always obvious, and the agreement that covers a particular element should be settled early, because it affects both the cost and who carries the risk. That boundary is set out in more detail in where a section 278 agreement ends and a section 106 starts.
Design, inspection and supervision fees
The works cost is only part of it. Highway authorities recover their own costs through published fee scales, normally charged as a percentage of the estimated works value, and these are the items most often absent from a submitted appraisal.
| Cost item | What it covers | Typical treatment |
|---|---|---|
| Technical approval and design check | The authority checking the developer's design | Percentage of works value, per published scale |
| Inspection and supervision | Site inspection during construction | Percentage of works value, per published scale |
| Legal fees | Preparing and completing the agreement | Fixed or time-charged |
| Statutory undertakers | Diversion of services in the highway | Quoted by each undertaker, often the largest variable |
| Traffic management and road space booking | Lane closures, permits, out of hours working | Priced separately, varies hugely by road |
| Bond or security | Protecting the authority if works stop | Premium or facility cost, in finance |
The percentages differ between authorities, so take them from the highway authority's own published schedule rather than applying a figure from the last scheme. Statutory undertaker diversions are the genuine wild card: a single apparatus diversion on a busy road can cost more than the carriageway works it enables, and the quote takes weeks to obtain.
Allow for inflation between the estimate and the works, and for the possibility that the authority requires a design change at technical approval stage. Both are normal rather than exceptional.
Commuted sums for maintenance
Where the works introduce something the authority would not otherwise have to maintain, it will usually ask for a commuted sum covering future maintenance. Signalised junctions, non-standard surfacing, street trees, planted islands, bollards and certain lighting all attract one.
The sum is normally calculated as a capitalised maintenance cost over a stated period using the authority's own figures. It is a real cost to the scheme and it falls due before or on completion of the works, so it belongs in the appraisal at full value and in the cash flow at the right date.
Two negotiation points are worth making. A design that uses the authority's standard details may avoid the commuted sum altogether, and the saving can exceed the extra design cost. And where the sum is calculated over a long period, ask for the basis and the discount rate, because the arithmetic is sometimes conservative in the authority's favour.
Whether the cost is an abnormal
This is where appraisals go wrong. Published build cost rates, such as those derived from tender price indices, cover the building and sometimes a nominal allowance for external works. They do not cover off-site highway works, and they do not cover abnormals.
So section 278 costs have to be added explicitly, as their own line, with the supporting estimate. Whether they are labelled an abnormal or an external works item matters less than making sure they are not buried in a rate that was never intended to include them.
Reviewers test three things. That the cost appears somewhere at all. That it is not also included in the build rate through a generic external works percentage. And that the estimate is supported by something better than a round figure. An appraisal showing section 278 works at exactly £250,000 with no backing schedule invites a reduction.
Double counting against contributions
The other common defect runs in the opposite direction. Where a section 106 obligation includes a financial contribution towards a highway improvement, and the same improvement is also being delivered by the developer under a section 278 agreement, counting both overstates the cost.
Regulation 122 of the Community Infrastructure Levy Regulations 2010 requires a planning obligation to be necessary to make the development acceptable, directly related to the development, and fairly and reasonably related in scale and kind. An obligation that funds works the developer is separately obliged to build does not meet those tests. The restriction on pooling more than five obligations was removed in 2019, but the regulation 122 tests continue to apply to every obligation.
Set out the package in one table: each highway item, the mechanism delivering it, the cost, and where it appears in the appraisal. That single table resolves most arguments with a reviewer before they start, and it carries across into the Viability Assessment and the committee report.
Evidencing the estimate
Six things make a section 278 estimate hard to argue with.
- A drawing of the proposed works, at a stage the highway authority has at least seen informally.
- A priced schedule prepared by a highways engineer or a quantity surveyor, with quantities.
- The highway authority's published fee scale, with the percentages applied shown as a calculation.
- Written quotations or budget figures from statutory undertakers for any known diversions.
- A stated allowance for inflation to the expected works date, and a contingency with the percentage disclosed.
- The commuted sum calculation, taken from the authority's figures.
Where the scheme is at outline stage and the design is not fixed, say so and present a range rather than a false precision. Reviewers accept a range with a method. They do not accept a single figure with no derivation.
The highway evidence base itself sits in a Transport Assessment, and the costs in the appraisal should match the works the transport work recommends. Where obligations are being revisited on a scheme that has stalled, the highway package often needs repricing at the current date as well as the original one, which is the exercise described in renegotiating obligations on a stalled scheme.
Browse all 66 PlanScope report types and start a draft.
This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
What does a section 278 agreement cover?
Works to the existing public highway carried out at the developer's expense where the highway authority is satisfied they benefit the public: the site access, junction alterations, crossings, footway widening, traffic calming, drainage and lighting. Section 38 of the Highways Act 1980 covers the adoption of new estate roads inside the site, which usually sit within the build contract instead.
Are section 278 costs included in published build cost rates?
No. Rates derived from tender price indices cover the building and sometimes a nominal external works allowance, not off-site highway works and not abnormals. Section 278 costs have to be added as an explicit line with a supporting estimate, and reviewers check both that the cost appears and that it is not also buried in a generic external works percentage.
What are design and supervision fees?
Charges the highway authority makes for checking the developer's design and inspecting the works on site, normally calculated as a percentage of estimated works value under the authority's own published fee scale. The percentages differ between authorities, so take them from the relevant published schedule rather than applying a figure from a previous scheme.
When is a commuted maintenance sum required?
Where the works introduce something the authority would not otherwise maintain, such as a signalised junction, non-standard surfacing, street trees, planted islands or particular lighting. The sum capitalises future maintenance over a stated period using the authority's figures. Using standard details can avoid it altogether, and the saving often exceeds the extra design cost.
Can a section 106 contribution and section 278 works both be counted?
Not for the same improvement. Regulation 122 of the Community Infrastructure Levy Regulations 2010 requires an obligation to be necessary, directly related to the development and fairly and reasonably related in scale and kind, and an obligation funding works the developer must separately build fails those tests. Set the package out in one table showing mechanism and cost.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.