Sales value evidence and the new build premium
Revenue moves a viability conclusion more than any other line. How to build a sales schedule from real transactions, derive the new build premium from paired evidence, and deduct incentives properly.
Revenue is the line that moves a viability conclusion more than any other, and it is usually the line with the thinnest evidence behind it. Good sales values viability evidence is a schedule of real transactions, each one adjusted for a stated reason, with the adjustment for the new build premium derived from paired evidence rather than asserted as a percentage. An authority's reviewer will test the schedule before anything else, because a five per cent error on revenue swamps every argument about build cost.
What comparables an authority will accept
The hierarchy is fairly settled, and knowing it tells you where to spend your effort.
| Evidence | Weight | Why |
|---|---|---|
| Completed sales on comparable new build schemes nearby | Strongest | Same product, same market, actual prices paid |
| Reservations and exchanges on a current new build scheme | Strong | Current, but subject to completion and incentives |
| Second-hand transactions adjusted for the premium | Moderate | Plentiful, but needs a defensible adjustment |
| Asking prices and agents' opinions of value | Weak | Not transactions, and often optimistic |
| Published index movements | Context only | Useful for adjusting dates, not for setting a price |
Price paid data from the Land Registry is the backbone. It gives the address, the date, the price and the property type, and it marks new build transactions separately, which is what makes the premium analysis possible at all.
Published indices are for time adjustment, not for valuation. Taking a 2023 transaction and uplifting it by a national index to a 2026 figure is weaker than finding a 2026 transaction, and a reviewer will say so.
Second-hand transactions and the premium question
Buyers pay more for a new home than for an equivalent second-hand one. The reasons are concrete: a structural warranty, better energy performance and running costs, no chain, no immediate repairs, and the ability to choose finishes.
The mistake is treating the premium as a fixed figure. It varies by market, by product type, by the strength of the local second-hand stock and by the point in the cycle, and in a weak market with heavy incentives it can compress to very little. Any appraisal that applies a round percentage to every unit without showing where it came from invites the reviewer to substitute their own number.
The defensible method is paired evidence. Identify new build and second-hand transactions of similar size, type and location within a similar period, compute the price per square metre for each group, and present the difference as the observed premium with the sample set out. Then say what the sample size is and acknowledge its limits. A premium derived from six pairs is weak evidence honestly described, which is a stronger position than a confident assertion with no evidence at all.
Specification differences and how to adjust
Work in price per square metre of net internal area, then adjust unit by unit. Price per unit hides too much.
The adjustments that matter most, in rough order of effect:
- Floor area, because larger units usually achieve a lower rate per square metre.
- Parking, which can carry a substantial separate value in a constrained area and almost none elsewhere.
- Floor level and outlook in a flatted scheme, where a top floor with a view and a ground floor beside the bin store are different products.
- A lift, private outdoor space and storage.
- Tenure, since a flat on a long lease and a house on a freehold are not comparable without adjustment.
State each adjustment as a figure with a reason. "Adjusted upwards 4 per cent for parking, by reference to the two comparables on the same street with and without a space" is evidence. "Adjusted for specification" is not.
Ground rents, service charges and incentives
Three revenue details get overlooked and all three are checked.
Ground rents on new long residential leases were effectively abolished by the Leasehold Reform (Ground Rent) Act 2022, so an appraisal that still capitalises a ground rent income stream on new flats is working from an outdated model. Remove it.
Service charges reduce what a buyer will pay. A scheme with a concierge, lifts, extensive communal landscaping and a plant-heavy energy strategy carries a service charge that depresses capital value, and the comparables need to be drawn from schemes with similar charges or adjusted.
Incentives have to be deducted to reach net revenue. Stamp duty paid, part exchange, upgrade packages, deposit contributions and agents' fees all reduce what the developer receives. An appraisal showing gross list prices with no deduction for incentives overstates revenue, and that is the single most common revenue defect a reviewer finds.
Sensitivity testing the revenue line
Run the appraisal at a range of revenue assumptions and show the result. Testing the revenue line up and down by five and ten per cent is conventional, and the output should be expressed as the obligation package the scheme can support at each level rather than only as a residual land value.
That presentation is more useful to a committee than a single answer, and it is more honest. It also protects the applicant, because a conclusion that holds across a range is far harder to dismiss than one that depends on a single set of inputs.
Where the scheme is marginal, say which input the conclusion is most sensitive to and why. Reviewers trust an appraisal that identifies its own weak point.
Presenting the schedule
Set it out unit by unit, in a table the reviewer can audit without asking questions.
- Unit reference, type, number of bedrooms, net internal area in square metres.
- Proposed price, and price per square metre.
- The comparable or comparables relied on, with address, date and price.
- Each adjustment applied, as a percentage or a figure, with its reason.
- Incentives assumed, and net revenue after them.
- A separate section for the affordable units, priced on the registered provider's offer or on the relevant transfer value basis rather than on open market comparables.
Keep the affordable revenue visibly separate, because it attracts a different profit margin and a different risk assessment, which is why the tenure mix and its transfer values should be read with the affordable housing cascade mechanism.
The whole schedule belongs in the Viability Assessment, with the summary figures carried into the Affordable Housing Statement so the two documents cannot be read against each other. Where values are being revisited years after the original consent, the schedule has to be reconstructed at both dates, which is the harder exercise described in renegotiating obligations on a stalled scheme.
Valuation evidence is judgement work and a RICS registered valuer has to stand behind it. For specialist technical reports, qualified professional input may be required. Browse all 66 PlanScope report types and start a draft.
This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
What sales evidence carries most weight in a viability appraisal?
Completed sales on comparable new build schemes nearby, because they are actual prices paid for the same product in the same market. Reservations and exchanges on a current scheme come next, then adjusted second-hand transactions. Asking prices and agents' opinions carry little weight, and published indices should be used for time adjustment rather than to set a price.
How do you evidence the new build premium?
By paired analysis. Identify new build and second-hand transactions of similar size, type and location within a similar period, calculate the price per square metre for each group, and present the observed difference with the sample disclosed. State the sample size and its limits. A small sample honestly described is stronger than a round percentage with no evidence.
Should ground rent income still be capitalised?
No, not on new long residential leases. The Leasehold Reform (Ground Rent) Act 2022 effectively removed ground rents on those leases, so an appraisal that still shows a capitalised ground rent income stream for new flats is using an outdated model. Reviewers look for this, and finding it undermines confidence in the rest of the schedule.
Do incentives have to be deducted from sales values?
Yes. Stamp duty contributions, part exchange, upgrade packages, deposit contributions and agents' fees all reduce what the developer actually receives, so net revenue is what belongs in the appraisal. Showing gross list prices with no deduction is the most common revenue defect reviewers find, and it overstates the scheme's capacity to carry obligations.
How should sensitivity testing be presented?
Run revenue up and down by five and ten per cent, and express the output as the obligation package the scheme can support at each level rather than as a single residual land value. A conclusion that holds across a range is far harder to dismiss. Say which input the conclusion is most sensitive to, since that builds credibility rather than reducing it.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.