Gateway Two and Three and how they affect programme
For a higher-risk building, construction cannot start before Gateway Two approval and occupation cannot start before the Gateway Three certificate. Both belong in the programme from day one.
Gateway two three building safety approvals are programme events, not paperwork. For a higher-risk building, construction cannot start until the Building Safety Regulator has granted building control approval at Gateway Two, and the building cannot be occupied until the regulator has issued a completion certificate at Gateway Three. Neither can be run in parallel with the work it gates.
That is the change the Building Safety Act 2022 made, and it is a change of habit as much as of law. The old pattern of starting on site with the design 80 per cent resolved, and settling the rest through the build, does not survive a hard stop before the first spade.
What each gateway does
Gateway One sits at the planning application stage. For a relevant building, a Fire Statement accompanies the application and the regulator is a statutory consultee. It is a planning step, and passing it says nothing about the later two.
Gateway Two is the building control approval application for the higher-risk building, made to the regulator before work starts. The application has to show a design that demonstrates compliance, supported by the competence declarations for the dutyholders and the information the regulations require.
Gateway Three is the completion certificate application, made when the work is finished. The regulator checks that the building as built matches what was approved, including the changes recorded along the way, and issues a certificate. Registration follows before occupation of a new higher-risk building.
Who decides, and in what period
The regulator decides, drawing on a multi-disciplinary team that can include fire and structural specialists. Local authority building control does not approve a higher-risk building, which is a reversal worth stating plainly to clients who have worked with the same building control team for 20 years.
Decision periods are published, longer for a new higher-risk building than for work to an existing one, and extendable by agreement with the applicant. Check the current published figures rather than working from a number someone quoted last year. And treat the published period as the floor: an application with gaps attracts requests for further information, and the elapsed time between submission and approval is routinely longer than the headline period for applications that were not complete on the day they went in.
The practical consequence is a different pre-construction programme. Design freeze earlier, more coordination before submission, and a procurement route that does not assume design development during the enabling works.
The hard stop before construction
No building control approval, no start. The regime removes the mechanisms that previously allowed work to begin while details were resolved, and that is deliberate.
Three programme effects follow.
| Effect | Consequence for the programme |
|---|---|
| Earlier design freeze | Coordination and competence declarations complete before submission |
| Fixed approval period | A non-compressible activity between design and construction |
| Reduced tolerance for change | Late design development becomes a change control event, not a drawing revision |
Contract strategy has to reflect this. A two-stage arrangement with the contractor involved during design works more comfortably than a traditional route where the tender follows a design that then changes. And the enabling works question deserves attention early, because what counts as building work on the higher-risk building, and what sits outside it, affects when anyone can be on site at all.
Change control during construction
The regime splits changes into categories. Major changes require the regulator's approval before the work proceeds. Notifiable changes are submitted and recorded. Everything else is logged in the golden thread of building information, which has to be kept current and handed on.
Budget time for the major ones. A change that would once have been a site instruction and a revised drawing is now an application with a decision period, and the affected work waits. Teams that keep a running change log and discuss borderline cases with the regulator early fare better than teams that categorise changes themselves and defend the categorisation later.
The golden thread is a discipline rather than a document. Information has to be accurate, accessible and kept up to date through construction and into occupation, which means deciding at the outset who owns it and in what system.
Completion, registration and occupation
At Gateway Three the regulator checks the finished building against the approved design and the recorded changes, and issues the completion certificate. Occupation of a new higher-risk building also requires registration.
Phased occupation is possible in defined circumstances. Raise it with the regulator early if the commercial plan depends on handing over the lower floors while the upper floors complete, because a sales or letting programme built on an assumption about phasing is the kind of risk that surfaces at the worst moment.
Dutyholders and competence
The regime names dutyholders under the Building Regulations: the client, the principal designer and the principal contractor, each with duties to plan, manage and monitor the work and to satisfy themselves about competence. Those roles are not the same as the health and safety roles with similar names, although the same organisations often hold both.
Competence has to be demonstrated rather than claimed, and the declarations form part of the Gateway Two submission. Leaving the appointments late is a common way to lose a month, because an organisation that cannot evidence its arrangements holds up an otherwise complete application. And a change of principal contractor during construction is a notification in its own right.
Where planning conditions overlap
Planning conditions and the gateways run on separate tracks and intersect at a few points. Pre-occupation conditions, such as landscaping, parking or a travel plan, have to be discharged alongside the Gateway Three process. Materials conditions interact with the external wall requirements, so an approved material that cannot be used on a relevant building creates a variation application nobody planned for.
Keep the fire safety strategy and the planning documents consistent as the design develops. Where a change made for Gateway Two alters something the planning permission fixed, a section 96A or section 73 application may be needed, and that has its own period. The sequencing issues are set out further in what follows planning permission.
Programming around the gateways
- Confirm whether the building is a higher-risk building, by height, storeys and use.
- Set the design freeze date by working backwards from the Gateway Two submission.
- Programme the decision period as a fixed activity, with contingency for requests for information.
- Appoint dutyholders and record competence before submission rather than during assessment.
- Set up the golden thread and the change log at the start of construction.
- Programme Gateway Three and registration before any committed handover or occupation date.
Follow changes to the regime on the planning law timeline and verify the current decision periods with the regulator before you fix a programme on them.
This is general guidance, not legal advice. Check the position with your local planning authority, the Building Safety Regulator or a qualified professional before relying on it.
If you are at the planning stage of a tall residential scheme, enter the postcode and the constraint check will tell you whether Gateway One applies before you start the document set.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Which buildings go through Gateways Two and Three?
Higher-risk buildings, defined by height and use: at least 18 metres or seven storeys, containing at least two residential units, with hospitals and care homes also caught during design and construction. The definition is set out in the Building Safety Act 2022 and the regulations under it, and the measurement rules matter, so confirm the position for your building before programming.
Is Gateway Two really a hard stop?
Yes. Building work on a higher-risk building cannot begin until the Building Safety Regulator has given building control approval. There is no equivalent of starting on site under an initial notice while details are resolved, which is the habit the regime deliberately breaks. Programme the approval period as a fixed activity rather than an overlap.
How long does the regulator take?
The published decision periods are measured in weeks, with a longer period for a new higher-risk building than for work to an existing one, and they can be extended by agreement. Check the current published periods before relying on a figure, and assume that an application with gaps will generate requests for information that extend the elapsed time well beyond the headline.
What happens if the design changes during construction?
Change control applies. Major changes need the regulator's approval before the work proceeds, notifiable changes are recorded and submitted, and other changes are logged in the golden thread. Build the approval time for major changes into the programme, because a change treated casually can stop work on the affected element.
Can the building be occupied before Gateway Three?
No. A completion certificate from the regulator is required, and for a new higher-risk building registration is required before occupation. Phased occupation of parts of a building is possible in defined circumstances, so raise it with the regulator early rather than assuming it will be available at the end.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.