The Housing Delivery Test measures what an authority built against what it needed, and three thresholds decide what follows. This is how each consequence works in practice.

Housing delivery test consequences follow three thresholds, and knowing which one an authority has fallen below tells you most of what you need to know about how an application there will be determined. Below 95 per cent, the authority must publish an action plan. Below 85 per cent, it adds a 20 per cent buffer to the supply of deliverable sites it has to demonstrate. Below 75 per cent, the presumption in favour of sustainable development applies to decisions on housing applications.

The test itself is a simple ratio. Net additional dwellings delivered in the authority's area over the previous three years, divided by the homes required over the same three years. The method is in the measurement rule book published by the ministry, and the results are published annually for every authority in England.

What the test measures, and what it does not

Delivery is counted as net additions, which includes conversions and changes of use as well as new build, and subtracts demolitions. The requirement side uses the figure derived under the rule book rather than whatever number the authority prefers to quote.

Two features of the design matter when you argue it. The test looks backwards at completions, so a recent surge of permissions does not help the authority. And it is an area-wide measure, which means a strong performance by one large site can carry an authority whose smaller sites are stalled.

Conversions matter more than people expect. An authority with a steady flow of office to residential prior approvals can post a delivery figure that bears little relation to the number of houses actually built on allocated sites, which is worth checking in the authority monitoring report before you lean on the headline percentage.

That is why the test and the five year housing land supply calculation can disagree. One is a record of what was built, the other a forecast of what is deliverable. Treat them as separate arguments in the planning statement and give each its own evidence, because a report that merges them invites an officer to answer both with one paragraph.

The thresholds and what each one brings

Result Consequence
Below 95 per cent Action plan to be published within six months, identifying causes and measures
Below 85 per cent A 20 per cent buffer added to the five year supply of deliverable sites
Below 75 per cent The presumption in favour of sustainable development applies to housing decisions

The consequences are cumulative. An authority at 70 per cent is doing all three things, and its decision-making should reflect that. In practice the action plan is often the weakest of the three, which makes it useful evidence rather than a reason to ignore it.

The buffer is the consequence most often misunderstood. It does not require the authority to find more land in the abstract. It increases the requirement against which its deliverable supply is measured, so an authority that was marginally able to demonstrate five years frequently cannot once the buffer is applied, and that failure engages the presumption through the separate out of date policies route.

Read the action plan properly before you cite it. The useful parts are the authority's own account of why delivery fell short, any admission that allocated sites are not coming forward, and the measures it has committed to. An applicant proposing a site that answers one of those causes directly has an argument that is hard for the officer report to dismiss.

When the presumption is engaged, and what it does

Below 75 per cent the presumption applies to applications involving the provision of housing. It also applies, separately, where the policies most important for determining the application are out of date, which includes the position where a five year supply cannot be demonstrated.

What the presumption does is reverse the default. Permission should be granted unless the adverse impacts of doing so would significantly and demonstrably outweigh the benefits when assessed against the Framework taken as a whole. The weighting is deliberately asymmetric, which is why the shorthand of a tilted balance stuck.

What it does not do is switch off the rest of national policy. The Framework's protections for designated heritage assets, Green Belt, irreplaceable habitats and areas at risk of flooding continue to apply on their own terms, and a scheme that fails one of those does not get rescued by the tilt. Cite the current edition of the Framework when you set the test out, since it was re-issued on 17 August 2026 with policy-coded chapters and readers may be holding the December 2024 text.

Arguing the balance on a real application

The balance is a written exercise and it rewards structure. Set out the benefits with weight attached and a source for each: market and affordable homes against the authority's own requirement, the delivery timescale, economic benefits during construction, biodiversity gain above the statutory minimum, infrastructure secured by agreement. The affordable housing statement carries the tenure detail, and the weight you claim should match what the obligation actually secures.

Then set out the harms honestly, with the mitigation offered against each. An assessment that finds no harm at all is read as advocacy. One that concedes a moderate landscape effect and explains why it does not outweigh 80 homes in an authority delivering at 68 per cent reads as planning judgement.

Keep the delivery evidence current. The test is published annually, supply positions are updated in authority monitoring reports and five year supply statements, and the build-out reporting duties introduced for larger sites add another source on whether permissions are converting into completions.

Evidence on supply and where to find it

Four documents do most of the work. The published delivery test measurement for the authority. The authority's latest five year housing land supply statement. Its authority monitoring report, which usually sets out completions by site. And its action plan, where one exists.

Where the authority's supply statement relies on sites you know to be stalled, say so with reasons that can be checked: an unimplemented permission approaching expiry, an unresolved access, an outstanding section 106, a site in an ownership that has not promoted it. Specifics carry weight here in a way that general scepticism does not.

One honest uncertainty is worth naming. The relationship between the delivery test, the buffer and the supply position has been adjusted more than once in recent editions of the Framework, and the ministry has signalled further change to plan-making under the Levelling-up and Regeneration Act 2023. Check the current text rather than a note from a previous application, and say in the statement which edition you worked from.

Appeal decisions on the same authority are useful as an indication of how inspectors have approached its supply position, though they are not binding precedent and the figures move each year. Follow changes to the national position on the planning law timeline rather than relying on a note made two years ago, and verify the current thresholds in the Framework before you submit.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it, and confirm the latest published measurement.

For a site you are scoping now, enter the site postcode and work out the document bundle before you commit to the policy argument.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What does the Housing Delivery Test actually measure?

Net additional dwellings delivered in an authority's area over the previous three years, set against the number of homes required over the same period, expressed as a percentage. It is a backward-looking delivery measure published by the ministry, which makes it different from the five year housing land supply calculation, which looks forward at deliverable sites.

Is a low result the same as having no five year supply?

No. They are separate tests that can point in different directions. An authority can pass the delivery test and still be unable to demonstrate a five year supply, or the reverse. Where both are failing, the arguments reinforce each other, and you should present them separately so the officer report can address each on its own terms.

How long does an action plan take to appear?

National policy expects an authority to publish an action plan within six months of a result below the threshold, setting out the causes of under-delivery and the measures it will take. Action plans vary widely in quality. A thin one is itself worth citing, because it shows the authority has not identified a route back to delivery.

Does the presumption mean permission will be granted?

No. The presumption means permission should be granted unless the adverse impacts of doing so would significantly and demonstrably outweigh the benefits, assessed against the Framework as a whole. Certain policies, including those protecting designated heritage assets, Green Belt and irreplaceable habitats, still apply with full force, so the balance can still come out against a scheme.

Where are the results published?

On gov.uk, as an annual measurement for every authority in England, alongside the rule book that sets out the method. Check the publication date and use the latest figures, because an application argued on a superseded result loses credibility quickly and officers will have the current table in front of them.

Sources and further reading

housing delivery testtilted balancehousing land supplynppfplanning policy

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Planning Law Updates

View all →
Planning Law Updates7 min read

CIL indexation, exemptions and the liability notice

The self build exemption is generous and unforgiving. Claim it, get it granted, and serve the commencement notice before a spade goes in the ground, or you pay the full charge.

Read article →
Planning Law Updates7 min read

The nationally described space standard and its status

Minimum dwelling sizes are not building regulations. The standard only applies through a local plan policy that has been tested for need and viability, or where the Order imposes it.

Read article →
Planning Law Updates6 min read

Class E: what the 2020 Use Classes revision merged

The 2020 amendment folded the old A1, A2, A3, B1, D1 and D2 classes into Class E, created F1 and F2, and pushed pubs, takeaways, cinemas and music venues into sui generis.

Read article →
Planning Law Updates6 min read

The ten year enforcement immunity period in England

The Levelling-up and Regeneration Act 2023 replaced the four year immunity for operational development and single dwelling conversions with ten years, from 25 April 2024. Earlier breaches keep the old period.

Read article →
Planning Law Updates6 min read

Gateway Two and Three and how they affect programme

For a higher-risk building, construction cannot start before Gateway Two approval and occupation cannot start before the Gateway Three certificate. Both belong in the programme from day one.

Read article →
Planning Law Updates6 min read

Short-term lets: the C5 use class and registration

The announced C5 use class and the register for short-term lets are not in force in England. What controls a let today is the material change of use test, and in London a night limit.

Read article →