CIL indexation, exemptions and the liability notice

7 min readBy PlanScope Editorial Team

The self build exemption is generous and unforgiving. Claim it, get it granted, and serve the commencement notice before a spade goes in the ground, or you pay the full charge.

Community infrastructure levy exemptions are almost never lost because someone was ineligible. They are lost because a form went in late, or because work started before the commencement notice was served. The levy is a creature of the Community Infrastructure Levy Regulations 2010 as amended, and the regulations are strict about sequence: assume liability, claim and receive the exemption, serve the commencement notice, then start. Get that order wrong on a self-build and a charge that should have been nil becomes payable in full, with surcharges on top and no discretion for the authority to forgive it.

How the charge is calculated and indexed

The levy is charged per square metre of net additional internal floorspace, at rates set in the charging authority's own charging schedule. Rates vary by use and often by geographical zone within the authority, and the schedule is a published document that went through examination.

The chargeable amount is indexed. Since the 2019 amendments, indexation uses an index published annually by the Royal Institution of Chartered Surveyors for this purpose, applied from 1 January each year, replacing the tender price index used previously. Charging authorities must publish an annual rate summary showing the indexed figures.

The practical effect is that a rate adopted several years ago is not the rate you pay. Take the figures from the authority's current published rate summary rather than from the charging schedule itself.

Existing floorspace is deducted where the building has been in lawful use for a qualifying continuous period within the relevant time before permission. That deduction is often worth more than any relief, and it depends on evidence of use, so gather it early.

In London, two levies can apply: the borough's own charge and the Mayoral levy that funds strategic transport infrastructure. Both are calculated separately and both are payable, which is one of several ways the capital runs its own arrangements, alongside the order making and referral powers covered in mayoral development orders and London referrals.

The self build exemption and its conditions

A self-builder who builds a house and lives in it as their main residence can claim exemption from the whole charge. The conditions are specific.

The claim is made on the published self build exemption form before development begins, and the authority must grant it before you start. Granting is not automatic and it is not instant, so build the processing time into the programme.

Within six months of completion, a second part of the claim must be submitted with evidence. The usual evidence set is proof of title, confirmation that the property is your sole or main residence such as a council tax record, and one of a building control completion certificate, an approved self-build warranty, or an approved VAT reclaim for a new dwelling.

The dwelling must then remain your main residence for three years from completion. Selling or letting it within that period is a disqualifying event, and the exemption is withdrawn with the charge becoming payable.

Residential extension and annexe exemptions

Extensions to an existing dwelling are only chargeable above 100 m² of new internal floorspace, so most householder work is outside the levy altogether. Where an extension does exceed that figure, an exemption is available to an owner who occupies the dwelling as their principal residence.

A self-build annexe within the curtilage of your own home has its own exemption, subject to the annexe being wholly within the curtilage, being a single dwelling, and the main dwelling remaining your principal residence. The annexe cannot be sold separately from the main house for three years.

Both exemptions follow the same discipline: claim before starting, receive the grant, serve the commencement notice. Neither can be applied for retrospectively.

Watch the floorspace measurement. The 100 m² threshold is gross internal area of new floorspace, and a loft conversion, a garage conversion and an extension carried out under a single permission are counted together.

Social housing and charitable relief

Social housing relief applies to qualifying affordable dwellings, and discretionary relief for exceptional circumstances is available where the authority has resolved to offer it. Charitable relief applies where the owner is a charity and the development will be used wholly or mainly for charitable purposes.

Both are claimed on the published forms before commencement, both are subject to clawback if the qualifying use ceases within seven years, and both require the claimant to have assumed liability.

Discretionary relief is narrow and rarely granted. It needs the authority to have adopted the power, a section 106 agreement already in place, and evidence that the charge would make the development economically unviable.

Assumption of liability and the commencement notice

These are the two documents that cause the trouble.

Assumption of liability is a notice telling the authority who will pay. It should be submitted before development begins. Where nobody assumes liability, it defaults to the landowner, and a surcharge applies.

The commencement notice tells the authority the date work will start, and it must be received before that date. There is no grace period and no discretion. Where a commencement notice is not served, the authority can determine a deemed commencement date, the payment instalment policy is lost so the whole sum falls due immediately, a surcharge applies, and any exemption already granted is lost.

That last point is the one that catches self-builders. An exemption properly claimed and properly granted disappears because a digger arrived on a Monday and the notice went in on the Wednesday. The regulations have been amended over time to soften some consequences, so check the current text, but do not plan on being rescued.

Demolition, site clearance and laying services can all amount to a material operation that begins development. Serve the notice before anything happens on site.

Surcharges and the loss of exemption

The regulations set a schedule of surcharges. Failing to assume liability attracts a fixed sum per owner. Failing to serve a commencement notice attracts a percentage of the chargeable amount subject to a cap, as does a disqualifying event. Late payment attracts further surcharges at set intervals and interest above the Bank of England base rate.

Check the current figures in the regulations as amended rather than relying on a secondary source, because they have been revised.

The cumulative effect on a self-build plot can be severe: a charge that was exempt, plus a surcharge for the missing notice, plus interest running from the deemed commencement date. Authorities have limited discretion to waive any of it.

Where the project is phased, each phase has its own commencement notice and its own liability, and the levy is calculated phase by phase. Get the phasing right in the permission itself rather than trying to retrofit it.

Appeals and review routes

There are several, and each has a short deadline.

A request for review of the chargeable amount goes to the charging authority within 28 days of the liability notice. If the review does not resolve it, an appeal on the chargeable amount goes to the Valuation Office Agency. Appeals against surcharges, against the apportionment of liability between owners, against refusal of charitable or annexe relief, and against a deemed commencement date each have their own route, and most go to the Valuation Office Agency rather than to the Planning Inspectorate.

The exception is an appeal against a levy stop notice, which goes to the Planning Inspectorate.

Read the liability notice as soon as it arrives and diarise the review deadline. The commonest reason an incorrect chargeable amount stands is that nobody challenged it in time. Reform affecting the levy and its possible replacement is tracked on the planning law timeline, and the supporting documents a scheme needs are listed on the planning documents index.

You can draft the planning statement for a self-build application on PlanScope by entering the postcode and answering the guided questions, then handle the levy forms directly with your charging authority.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

When must a commencement notice be served?

Before development begins, and the authority must have received it by then. There is no grace period. Demolition, site clearance and laying services can all amount to a material operation that starts development, so serve the notice before anything happens on site, not on the day the main contractor mobilises.

What happens if I start before the self build exemption is granted?

The exemption is lost and the full charge becomes payable, along with a surcharge and interest running from the deemed commencement date. The authority has very limited discretion. Claim the exemption, wait for the written grant, serve the commencement notice, and only then begin.

Is a house extension liable for the levy?

Only where it creates more than 100 m² of new gross internal floorspace, and even then an exemption is available to an owner occupying the dwelling as their principal residence. Floorspace created under a single permission is counted together, so an extension plus a loft and garage conversion can cross the threshold.

How is the levy indexed?

Since the 2019 amendments, the chargeable amount is indexed using an annual index published by the Royal Institution of Chartered Surveyors for this purpose, applied from 1 January each year. Charging authorities must publish an annual rate summary, and that document, not the original charging schedule, gives the rate you pay.

Can I appeal the amount charged?

Yes. Request a review by the charging authority within 28 days of the liability notice, and if that does not resolve it, appeal the chargeable amount to the Valuation Office Agency. Separate routes exist for surcharges, apportionment, relief refusals and deemed commencement dates, each with its own deadline.

Sources and further reading

cilself-buildexemptionslevycommencement noticeindexation

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Planning Law Updates

View all →
Planning Law Updates7 min read

The nationally described space standard and its status

Minimum dwelling sizes are not building regulations. The standard only applies through a local plan policy that has been tested for need and viability, or where the Order imposes it.

Read article →
Planning Law Updates6 min read

Class E: what the 2020 Use Classes revision merged

The 2020 amendment folded the old A1, A2, A3, B1, D1 and D2 classes into Class E, created F1 and F2, and pushed pubs, takeaways, cinemas and music venues into sui generis.

Read article →
Planning Law Updates6 min read

The ten year enforcement immunity period in England

The Levelling-up and Regeneration Act 2023 replaced the four year immunity for operational development and single dwelling conversions with ten years, from 25 April 2024. Earlier breaches keep the old period.

Read article →
Planning Law Updates6 min read

Gateway Two and Three and how they affect programme

For a higher-risk building, construction cannot start before Gateway Two approval and occupation cannot start before the Gateway Three certificate. Both belong in the programme from day one.

Read article →
Planning Law Updates6 min read

Short-term lets: the C5 use class and registration

The announced C5 use class and the register for short-term lets are not in force in England. What controls a let today is the material change of use test, and in London a night limit.

Read article →
Planning Law Updates6 min read

The Housing Delivery Test and what follows a low result

The Housing Delivery Test measures what an authority built against what it needed, and three thresholds decide what follows. This is how each consequence works in practice.

Read article →