Higher-risk buildings and the 18 metre test
The higher-risk building test has two limbs and both must be met. Here is how height and storeys are measured, which buildings the 2023 Regulations exclude, and how the gateways relate to the planning fire statement.
A higher-risk building is one that is at least 18 metres in height or has at least seven storeys, and that also contains at least two residential units. Both halves have to be satisfied. A seven-storey office block is not a higher-risk building. A four-storey block of flats is not one either. A 19-metre building with two flats in it is.
The arithmetic looks simple until you have to decide whether a plant enclosure counts as a storey, or where ground level is on a sloping site. Those marginal cases are where the regime bites, and getting them wrong means an application goes in without a fire statement, or a project reaches site without building control approval from the Building Safety Regulator.
The height and storey test
The two limbs are alternatives, so a building qualifies on height or on storeys, whichever is reached first. A seven-storey residential building with generous floor-to-floor heights will exceed 18 metres as well. A seven-storey building with low ceilings may sit below 18 metres and still be in scope on the storey count alone.
That is deliberate. The storey limb catches buildings where the number of floors creates the evacuation problem even though the measured height does not reach the threshold.
For design and construction, the definition also brings in hospitals and care homes meeting the same height or storey test, whether or not they contain residential units. For the occupation regime that applies once the building is in use, hospitals and care homes drop out and the definition rests on the two residential units.
How height and storeys are measured
The measurement rules sit in the Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023, and they are more specific than most design teams assume.
Height is measured from ground level to the top of the floor surface of the top storey. Not to the parapet, not to the ridge, and not to the top of a lift overrun. A storey consisting only of roof-top machinery or plant is left out of that measurement, so a tall plant enclosure above the top flat does not push a building over the line.
Ground level on a sloping site is taken at the lowest point of the surface of the ground next to the building. That single rule has pushed buildings into scope that the team believed were comfortably below 18 metres, because the measurement starts at the bottom of the slope rather than at the entrance level.
| Element | Treatment |
|---|---|
| Datum for height | Lowest point of the ground surface adjacent to the building |
| Top of measurement | Floor surface of the top storey |
| Roof-top plant or machinery storey | Excluded from height and from the storey count |
| Storey below ground level | Not counted as a storey |
| Mezzanine | Counted where its internal floor area is at least half that of the largest storey |
Measure it early, record the drawing and the assumptions, and keep that record. On a marginal building the measurement will be revisited by the Building Safety Regulator, by building control and probably by a purchaser's solicitor.
Buildings in scope and buildings excluded
The 2023 Regulations exclude several categories even where the height or storey test is met. Prisons and other secure residential institutions are out. Military barracks and similar service accommodation are out. Hotels are out, which is why a 20-storey hotel is treated differently from a 20-storey block of flats. Temporary leisure structures are out.
Student accommodation is the question that comes up most, and the answer depends on the configuration rather than the label. Where the building contains residential units in the statutory sense, the test applies. Purpose-built student accommodation of any scale should be checked against the definition rather than assumed to be outside it.
Mixed-use buildings follow the residential units. Two flats above commercial floors in a 19-metre building bring the whole building into scope, and the gateway process then applies to the building rather than to the residential part of it.
The three gateways and who is consulted
The regime splits a project into three control points.
- Gateway One sits inside the planning application. For a relevant building, the applicant submits a fire statement on the prescribed form and the Health and Safety Executive is a statutory consultee on fire safety matters relating to land use and site layout.
- Gateway Two sits before construction starts. A building control approval application goes to the Building Safety Regulator, which is the building control authority for higher-risk buildings, and work cannot begin until it is approved.
- Gateway Three sits at completion. A completion certificate application goes to the same regulator, and the building cannot be occupied until the certificate is issued and the building is registered.
The Building Safety Regulator sits within the Health and Safety Executive. It is not the local authority building control service, and for higher-risk buildings there is no option to use an approved inspector instead. What happens after planning permission is set out in Gateway Two and Gateway Three.
Change control between the gateways is the part that catches programmes. Major changes after Gateway Two approval need the regulator's agreement before they are built, and a design-and-build contractor accustomed to resolving details on site will find that uncomfortable.
Overlap with the planning fire statement
The planning trigger and the Building Safety Act definition use the same height and storey figures but describe buildings slightly differently, and conflating them causes validation problems.
Article 9A of the Town and Country Planning (Development Management Procedure) (England) Order 2015 requires a fire statement for development involving a relevant building. A relevant building for that purpose contains two or more dwellings or educational accommodation, and meets the height condition of 18 metres or more, or seven or more storeys. Educational accommodation appears in the planning test and not in the higher-risk building definition for the gateway regime.
So a scheme can need a Gateway One fire statement while falling outside part of the wider higher-risk regime, and the reverse is possible for care homes and hospitals. Check each definition against its own instrument rather than carrying one conclusion across.
A Fire Statement is a fire-engineering document. It has to be prepared by someone with the necessary fire-engineering competence, and an AI-assisted draft can structure the submission and the policy references around that work without replacing it. The report types and their professional requirements are set out across the 66 report types.
Existing buildings and works to them
The regime is not limited to new buildings. Works to an existing higher-risk building, including some refurbishment and any work that creates additional storeys, engage the gateways. Converting a 20-metre office building into flats creates a higher-risk building where none existed, because the residential units limb is now satisfied.
Separately, existing occupied high-rise residential buildings carry duties under the Fire Safety (England) Regulations 2022 and the in-occupation parts of the Building Safety Act, including registration, the safety case and the accountable person. Those duties sit alongside planning rather than inside it, and they are covered in the Fire Safety (England) Regulations and existing blocks.
Where the definitions are published
The primary definition is in the Building Safety Act 2022 itself, with the detail of descriptions and measurement in the 2023 Regulations. The planning trigger is in Article 9A of the 2015 Order. The gateway procedures sit in the building control regulations made under the Act, and the regulator publishes its own procedural guidance.
As at late October 2026, those are the instruments to read. The regime has been amended repeatedly since the Act received Royal Assent, so check the current consolidated text on legislation.gov.uk rather than a secondary summary, and follow changes through the planning law updates timeline.
This is general guidance, not legal advice. Check the position with your local planning authority, the Building Safety Regulator or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.
Frequently asked questions
How is the 18 metre height measured?
From ground level to the top of the floor surface of the top storey, not to the parapet or ridge. A storey containing only roof-top plant or machinery is excluded. On a sloping site, ground level is taken at the lowest point of the ground next to the building, which has brought buildings into scope that teams expected to be below the threshold.
Does a seven-storey office count as a higher-risk building?
No. The definition needs the height or storey test to be met and the building to contain at least two residential units. A purely commercial building falls outside it. For design and construction, hospitals and care homes meeting the height or storey test are also included even without residential units.
Which buildings are excluded from the definition?
The Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023 exclude prisons and other secure residential institutions, military barracks and similar service accommodation, hotels, and temporary leisure structures. That is why a tall hotel is treated differently from a block of flats of the same height.
Is the planning fire statement trigger the same test?
Almost, but not quite. Article 9A of the Development Management Procedure Order 2015 uses the same 18 metre or seven storey condition, but defines a relevant building as containing two or more dwellings or educational accommodation. Educational accommodation appears in the planning test and not in the higher-risk building definition for the gateway regime.
Do the gateways apply to conversions of existing buildings?
Yes, where the works create or affect a higher-risk building. Converting a 20-metre office block into flats satisfies the residential units limb and creates a higher-risk building, so Gateway Two building control approval from the Building Safety Regulator is needed before construction and Gateway Three before occupation.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.