Which Reports Do I Need

Reports needed for 10 units on 0.4 hectares

7 min readBy PlanScope Editorial Team

Ten dwellings makes a scheme major even on 0.4 hectares, so affordable housing and the full biodiversity net gain regime apply while the area-based flood trigger does not.

Ten dwellings on 0.4 hectares is major development. The definition in the Development Management Procedure Order 2015 counts a residential scheme as major where the number of dwellings is 10 or more, and the 0.5 hectare figure is the alternative trigger used where the number of dwellings is not known. So the site area does not save you: the unit count puts the application into the major stream, with a 13 week determination period, newspaper publicity and the statutory consultations that follow.

What the 0.4 hectares does change is a short list of area-based requirements. Knowing which is which saves a lot of money.

Which threshold the site crosses and which it does not

Threshold Trigger At 10 units on 0.4 ha
Major development 10 or more dwellings Crossed
Flood risk assessment by site area 1 hectare or more Not crossed
Affordable housing under national policy Major development Crossed
Biodiversity net gain small site exemption from the simplified route 1 to 9 dwellings Not available
Transport Assessment rather than a Statement Commonly 50 or more dwellings Not crossed
Statement of Community Involvement Commonly 50 or more dwellings Not crossed
Environmental Impact Assessment screening for urban development More than 150 dwellings or site area above 5 hectares, subject to sensitive areas Not crossed
Fire Statement at Planning Gateway One Relevant buildings of 18 metres or seven storeys Not crossed

The two that matter most are the first and the fourth. Being major brings procedural weight, and being above the small sites definition brings the full biodiversity net gain regime.

Major development and what follows from it

Four practical consequences, in the order you will meet them.

The determination period is 13 weeks rather than eight, and an extension of time is common on a ten unit scheme where drainage or ecology needs resolving. Budget for five months from validation rather than three.

Publicity is wider. Major applications require a site notice and a newspaper advertisement under the Development Management Procedure Order, which means more neighbours see it and the consultation period is more likely to generate objections.

The lead local flood authority becomes a statutory consultee on surface water drainage for major development. That is the single most useful thing to know on this scheme, because it means a drainage strategy with hydraulic calculations is required even though no flood risk assessment is triggered by the site area.

And the application is more likely to go to committee, depending on the authority's scheme of delegation and whether objections are received. That affects timing, not the evidence, but it changes how the planning statement should be written: committee members read the officer's summary rather than your document.

Affordable housing at the tenth unit

National policy expects affordable housing contributions on major development, which this scheme is. Below the major threshold, contributions are generally not sought outside designated rural areas, where a lower threshold applies.

So the tenth unit is the expensive one. On a nine unit scheme there is normally no affordable housing requirement. On a ten unit scheme the adopted policy percentage applies to the whole scheme, not to the tenth unit, and on a site of this size it is usually taken as a commuted payment rather than on-site provision because a registered provider will not take two units.

Three things to prepare. The authority's adopted policy percentage and tenure split. The authority's published approach to off-site contributions and how the sum is calculated. And, where the numbers do not work, a viability assessment prepared on the authority's own methodology rather than yours.

An Affordable Housing Statement setting out the provision, the tenure and the delivery mechanism belongs in the submission from the start. Leaving it to negotiation after validation adds weeks.

It is worth stating the obvious commercial point. If the scheme can be designed as nine dwellings without losing much value, do the arithmetic on both versions before committing. The cost difference is rarely trivial.

Biodiversity net gain on a scheme above the small site threshold

This is where the 0.4 hectares does not help at all.

The small sites route under the biodiversity net gain regime applies to residential development of between one and nine dwellings on a site below one hectare. At ten dwellings the scheme falls outside that, which means the full statutory metric rather than the small sites metric, and the full process: a pre-development baseline assessed on site, a 10 per cent net gain, a biodiversity gain plan approved by the local planning authority before development starts, and a 30 year management and monitoring commitment for any significant on-site habitat created or enhanced.

The practical consequences on a 0.4 hectare site are real. There is not much room to create habitat, so the gain often has to come from off-site units or statutory credits, and the cost of those lands on the scheme rather than on the landscape budget. A Biodiversity Net Gain Assessment with the baseline measured early tells you whether the scheme works before the drawings are finished.

The metric must be completed by a competent person, and habitat condition assessment has its own survey season, so this is the first thing to commission rather than the last.

Drainage where the site is under one hectare

No flood risk assessment is triggered by area alone below one hectare, and in Flood Zone 1 with no other source of flooding a full assessment is normally unnecessary. Check the Environment Agency mapping for surface water risk and the authority's strategic flood risk assessment for any critical drainage area before concluding that.

A Drainage Strategy is a different matter and will be required, because the lead local flood authority is consulted on surface water for major development. The strategy needs the discharge hierarchy applied in order, infiltration testing results where infiltration is proposed, greenfield or pre-development runoff rates, attenuation volumes with the current climate change allowance, exceedance routes and a maintenance plan with named responsibility.

Infiltration testing first. A strategy built on soakaways that fails testing at the detailed design stage means redesigning the layout, and on a small site the attenuation has to fit somewhere.

Foul drainage needs its own answer. Where there is a public sewer, capacity confirmation from the undertaker. Where there is not, the sequence is set out in the guide to reports for a site with no mains foul drainage.

Transport evidence proportionate to ten units

A Transport Assessment is normally reserved for larger schemes, and at ten dwellings a Transport Statement is usually the right document. It should cover the access design with visibility splays to the relevant standard, trip generation from a recognised database with the comparison sites stated, the effect on the nearest junction if it is already constrained, parking against the adopted standard with cycle parking, refuse vehicle access with a swept path, and construction access.

Two items often requested on top. A road safety review of the access where the local highway authority has a record of incidents, and confirmation that the internal layout meets adoption standards if the road is to be offered for adoption under section 38 of the Highways Act 1980.

The report bundle and the order to produce it in

The bundle itself is predictable: Planning Statement, Design and Access Statement, Affordable Housing Statement, Biodiversity Net Gain Assessment with a Preliminary Ecological Appraisal and any species surveys, Drainage Strategy, foul drainage evidence, Transport Statement, Arboricultural Impact Assessment, a Construction Management Plan, an energy and sustainability statement where local policy requires one, and a waste and recycling strategy.

The order is what saves time.

  1. Ecology and habitat condition first, because the survey seasons govern everything.
  2. Infiltration testing and the drainage concept second, because they shape the layout.
  3. Tree survey third, with root protection areas plotted before the footprint is fixed.
  4. Layout and design fourth, now constrained by the first three.
  5. Transport and the access design fifth, once the layout exists.
  6. The written statements last, when there is something to describe.

Most ten unit schemes run that list backwards, producing drawings first and then discovering that the attenuation does not fit or that the metric does not balance. The sequence above costs the same money in a different order and avoids a redesign.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. Biodiversity net gain and protected species work require a licensed or competent professional, and a draft is a starting point for that professional rather than a substitute.

You can browse all 66 report types and start a draft to assemble the submission. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is ten dwellings on 0.4 hectares major development?

Yes. The Development Management Procedure Order 2015 treats a residential scheme as major where the number of dwellings is 10 or more. The 0.5 hectare figure is the alternative trigger used where the number of dwellings is not known, so a small site with ten units is still major, with a 13 week determination period.

Does affordable housing apply at ten units?

National policy expects contributions on major development, which a ten unit scheme is, with a lower threshold in designated rural areas. The adopted policy percentage applies to the whole scheme rather than the tenth unit alone, and on a small site it is usually taken as a commuted payment because a provider will not take two units.

Can a ten unit scheme use the small sites biodiversity metric?

No. The small sites route applies to residential development of between one and nine dwellings on a site below one hectare. At ten dwellings the full statutory metric applies, with a 10 per cent gain, a biodiversity gain plan approved before development starts and a 30 year management commitment for habitat created on site.

Do I need a flood risk assessment on 0.4 hectares?

Not from site area alone, since the area trigger is one hectare, and in Flood Zone 1 with no other flood source a full assessment is usually unnecessary. Check surface water mapping and the authority's strategic flood risk assessment for a critical drainage area first. A drainage strategy is still required because the scheme is major.

Transport Statement or Transport Assessment at ten units?

A Transport Statement is normally proportionate, since an Assessment is usually reserved for larger schemes. The Statement should cover access design and visibility, trip generation from a recognised database with the comparison sites named, parking against the adopted standard, refuse vehicle swept paths and construction access.

Sources and further reading

major developmentten unitsaffordable housingbiodiversity net gaindrainageself-build

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Which Reports Do I Need

View all →
Which Reports Do I Need7 min read

Reports needed for a funeral directors in a shop parade

Funeral directing falls within Class E, so a move within the class may need no permission. The preparation room, trade effluent, cortege standing and refrigeration noise are the real issues.

Read article →
Which Reports Do I Need7 min read

Reports needed for a climbing wall in an industrial unit

Indoor climbing is Class E(d) and there is no permitted development route from an industrial unit. Employment land policy, the evening parking peak and impact noise through the party wall decide the application.

Read article →
Which Reports Do I Need8 min read

Reports needed for a sixth form block on a playing field

Building on a school playing field needs Sport England consultation under the DMPO 2015 and separate section 77 consent. The pitch evidence comes before the building evidence.

Read article →
Which Reports Do I Need7 min read

Reports needed for a holiday lodge park on a former quarry

A lodge park on a former quarry needs restoration conditions checked, faces and fill tested for stability, and the habitat that has colonised the site surveyed. This is the evidence base that follows.

Read article →
Which Reports Do I Need7 min read

Reports needed to deck an existing surface car park

Trip generation barely moves when parking goes vertical. Daylight, overlooking, vehicle fire risk, raised lighting and collected drainage are what decide the application.

Read article →
Which Reports Do I Need7 min read

Reports needed for a garden centre cafe and canopy

A cafe reached through the plant area is ancillary. A destination restaurant on an out-of-centre site is not. Here is the document list and the conditions that catch people.

Read article →