The flood sequential test and how to pass it

7 min readBy PlanScope Editorial Team

The sequential test asks whether reasonably available sites exist at lower flood risk. Most failures are evidence failures, starting with an area of search drawn around the applicant's land.

The flood sequential test asks one question: are there reasonably available sites at lower flood risk that could accommodate the proposed development? If the answer is yes, the test is failed and permission should be refused, whatever the merits of the site you own. It comes from the flood risk chapter of the National Planning Policy Framework and the method sits in the Planning Practice Guidance on flood risk and coastal change, which also now directs the test at all sources of flooding rather than rivers and the sea alone.

The test is applied by the local planning authority as decision maker. Your job as applicant is to give them the evidence to apply it with, and most failed tests fail on evidence rather than on principle.

What the test asks, and who applies it

The sequential, risk-based approach steers development towards areas at the lowest risk of flooding. Flood zones give the framework for rivers and the sea:

Zone Annual probability Policy effect
Zone 1 Less than 1 in 1,000 Lowest risk, all uses appropriate in principle
Zone 2 Between 1 in 1,000 and 1 in 100 for rivers, 1 in 200 for the sea Medium risk, sequential test applies
Zone 3a 1 in 100 or greater for rivers, 1 in 200 or greater for the sea High risk, sequential test and often the exception test
Zone 3b Functional floodplain Water compatible and essential infrastructure only

Surface water, groundwater, sewers and reservoirs also count. A site in Zone 1 that sits in a mapped surface water flow path is not automatically outside the test, and the published surface water risk mapping is where an officer will look.

Vulnerability matters as much as the zone. Housing is more vulnerable than a car park, and the combination of flood zone and vulnerability classification determines whether a use is appropriate, needs the exception test, or should not be there at all.

When the test does not apply

Four common situations where you do not need to carry out the test.

The site is in Flood Zone 1 with no other identified source of flood risk. Confirm that with the published flood map for planning and the authority's strategic flood risk assessment rather than assuming.

The development is minor, or a change of use, which guidance treats as outside the sequential test. The exception is a change of use to a caravan, camping or chalet site or to mobile or park homes, where the test does apply because of the vulnerability of those uses.

The site is allocated in an adopted development plan where the sequential test was applied through the plan making process. That is a strong position, though it is not absolute if circumstances have changed materially since adoption.

Householder development, such as an extension to an existing dwelling, is also outside the test, which does not remove the need for a flood risk assessment where the site is in Zone 2 or 3 or on a site of one hectare or more.

Whether a test is required at all is itself a judgement, and like any planning judgement it sits among the broader set of material considerations the authority weighs.

The area of search is where the test is won or lost, and it is the first thing an officer checks.

The default is the local planning authority's area. Narrowing it requires a reason connected to the development rather than to the applicant. Reasons that are usually accepted include these. The development serves a defined catchment, such as a school or a local facility with a service area. The proposal relates to an existing operation that cannot be relocated. Or the plan identifies a regeneration area or settlement boundary within which the need arises.

Reasons that are not accepted: the applicant only owns this site, the applicant's business is based in this town, the site is the only one the applicant can afford, or the search area has been drawn tightly enough that no alternatives appear within it.

State the area of search, justify it in two or three sentences, and show it on a plan. A sequential test that leaves the area of search implicit invites the officer to substitute a wider one.

Evidence on alternative sites

The test compares your site with other sites that are reasonably available. That phrase does work: a site is reasonably available if it is suitable for the development, available within a reasonable period, and achievable.

A defensible search draws on:

  1. The authority's strategic housing and employment land availability assessments, which list sites with their constraints.
  2. Allocated but undeveloped sites in the adopted and emerging plans.
  3. Sites on the brownfield land register.
  4. Sites being marketed through commercial agents at the time of the search, with dates recorded.
  5. Any sites with extant permission that could accommodate the development.

Then assess each one, briefly, against three questions: is it in a lower flood risk zone, could it accommodate this development, and is it available in practice. Record the date of the search, because availability changes and an officer determining the application six months later needs to know what the snapshot represents.

Where a candidate site is discounted, give a reason that would stand up to a sceptical reader. "Too small to accommodate the proposed 18 units at the density of the surrounding area" is a reason. "Not suitable" is not.

An illustrative example. A self-builder with a plot in Flood Zone 2 on the edge of a village. The area of search is the parish, justified by a neighbourhood plan policy supporting local need housing within the settlement. The search identifies four candidate sites in Zone 1 from the land availability assessment and agents' listings, three of which are discounted with reasons, one of which is in fact available. On that evidence the test fails, and the honest advice is to say so before the fee is spent rather than after.

The sequential approach within a site

Passing the test for the site does not end the exercise. Where any part of the site is at higher risk, the layout should put the more vulnerable uses in the lower risk part.

Practical versions of this: habitable accommodation above ground floor level with parking, storage or plant below, access and egress routes designed to remain dry or safe in the design event, finished floor levels set above the modelled level with freeboard, and open space or landscape in the part of the site that floods.

Show this in the design and explain it in the flood risk assessment. It is also what the second limb of the exception test is looking for, so the work is not wasted if you end up there.

Why tests get rejected

The recurring reasons are consistent enough to use as a checklist.

The area of search was drawn around the applicant's land interests. No alternative sites were examined at all, only asserted not to exist. The search ignored allocated sites because the applicant judged them unlikely to come forward. Only river and sea flooding was considered, with surface water risk left out. The vulnerability classification was wrong, treating housing as less vulnerable than it is. And the test was presented as a paragraph in a flood risk assessment rather than as a document the authority can rely on in its own decision.

Where the test cannot be passed but the development is still justified, the route is the exception test, which requires both wider sustainability benefits that outweigh the flood risk and a demonstration that the development will be safe for its lifetime without increasing risk elsewhere. That is a higher bar, and it needs the flood risk assessment and the layout to be doing real work rather than describing the risk.

Enter your postcode on PlanScope to see whether your site is in a flood zone and which reports it is likely to need, then confirm the position with the authority's strategic flood risk assessment.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Who carries out the sequential test?

The local planning authority applies it as decision maker. The applicant supplies the evidence: the area of search and its justification, the candidate sites identified, and the reasons each is or is not reasonably available. The Environment Agency is a consultee on flood risk but does not apply the test on the authority's behalf.

When is the test not required?

Where the site is in Flood Zone 1 with no other source of flood risk, for minor development and changes of use, for householder development, and where the site was allocated through a plan in which the test was already applied. Change of use to caravan, camping, chalet, mobile or park home sites is an exception and does need the test.

How wide should the area of search be?

The local planning authority area by default. Narrowing it needs a reason connected to the development, such as a defined catchment for a school or local facility, or a settlement boundary within which the need arises. Ownership, affordability and the applicant's business location are not accepted reasons.

What counts as a reasonably available alternative site?

One that is suitable for the development proposed, available within a reasonable period and achievable. Draw candidates from the authority's land availability assessments, allocated but undeveloped sites, the brownfield land register and sites being marketed at the time of the search, and record the date the search was carried out.

What happens if the test is failed?

Permission should normally be refused, unless the development can satisfy the exception test, which requires wider sustainability benefits that outweigh the flood risk and a demonstration that the development will be safe for its lifetime without increasing flood risk elsewhere. That is a higher bar and needs substantive design evidence.

Sources and further reading

sequential testflood riskflood zonesexception testself buildglossary

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Glossary

View all →
Glossary6 min read

First Homes: the discount, the caps and the 25% share

First Homes are discounted market sale units secured in perpetuity by a section 106 agreement and a title restriction. The discount, the price cap and the first-charge ordering all shape a scheme's affordable mix.

Read article →
Glossary7 min read

Ransom strip and the ha-ha of access rights

A retained sliver between a site and the highway blocks implementation rather than permission. How ransom strips arise, what the certificates require, and how they are resolved.

Read article →
Glossary6 min read

Section 184 vehicle crossings and the dropped kerb

Section 184 of the Highways Act 1980 governs vehicle crossings over a footway or verge, and it is decided separately from planning permission. When both are needed, the technical objections to expect, and how to sequence the applications.

Read article →
Glossary6 min read

Local Development Orders and when councils use them

Made under sections 61A to 61C of the Town and Country Planning Act 1990, a local development order removes the application stage for development it specifies. What it can grant, how to read its limitations, and what happens when it expires.

Read article →
Glossary6 min read

Lapsed permissions and what to do when time runs out

Once the three-year clock runs out without a lawful start, the permission is gone and section 73 cannot extend it. The options before expiry, the position afterwards, and the policy changes a fresh application now has to meet.

Read article →
Glossary7 min read

Prior approval: what the procedure actually involves

Prior approval under the General Permitted Development Order 2015 asks the council to sign off a short list of matters, not the principle of development. Here is how the procedure, the clocks and the deemed approval provisions work.

Read article →