Prior approval: what the procedure actually involves

7 min readBy PlanScope Editorial Team

Prior approval under the General Permitted Development Order 2015 asks the council to sign off a short list of matters, not the principle of development. Here is how the procedure, the clocks and the deemed approval provisions work.

The prior approval planning procedure is not a planning application in the ordinary sense. Permission has already been granted by the General Permitted Development Order 2015. What the authority is being asked to do is sign off a short, closed list of matters before you start, and if it says nothing within the statutory period the approval is deemed to be given. That difference in legal starting point changes almost everything about how you prepare the submission and how you argue with a case officer who strays off the list.

For a landlord converting a shop or an office, this is usually the lowest-cost route to a residential unit. It is also the route that most often goes wrong at the validation stage, because the clock only runs on a valid application.

Where permission comes from

Under a full planning application, the local planning authority decides whether to grant permission at all, weighing the adopted development plan and any other material considerations. Under a permitted development class, the Order grants permission directly, subject to limitations and conditions. One of those conditions, for certain classes, is that the developer must apply to the authority for a determination as to whether its prior approval will be required for specified aspects of the development.

So the question in front of the officer is narrow. The principle of the development is settled by the Order. What remains is whether the listed aspects are acceptable and what conditions should attach to them. An officer who refuses prior approval on a ground that is nowhere in the relevant class has made a decision you can appeal with some confidence.

The classes that use the procedure

The procedure appears in several parts of Schedule 2, and the detail differs in each:

  • Part 1 Class A, for larger rear extensions to a house, through the neighbour consultation scheme.
  • Part 3, covering changes of use, including Class MA from commercial, business and service use to dwellinghouses and Class Q from an agricultural building to a dwellinghouse.
  • Part 6, for agricultural and forestry buildings and operations, where the determination covers siting, design and external appearance.
  • Part 14, for larger solar installations.
  • Part 16, for electronic communications apparatus.
  • Part 20, for new flats built upward on existing buildings and for demolition and rebuild.

The conditions attached to Class MA in particular have been amended more than once since it came into force in August 2021, so read the current text of the Order rather than an older summary. Listed buildings and scheduled monuments are outside the class altogether. In a conservation area there is an extra matter the authority may weigh, which is the effect of losing a ground-floor commercial use on the character or sustainability of the area.

What the authority may consider

Each class sets out its own list. For Class MA the matters are transport and highways impacts, the risk of contamination on the site, flooding risk, the impact of noise from commercial premises on the future residents, the provision of adequate natural light to all habitable rooms, and in a conservation area the ground-floor point above. Class Q adds whether the location or siting of the building makes the residential use impractical or undesirable, plus design and external appearance.

Part 20 is wider again, taking in external appearance, the impact on the amenity of the existing building and neighbours, air traffic and defence safeguarding, and protected views. It also brings in fire safety, which is where most upward extension submissions need specialist input.

Natural light is the matter that surprises people. A deep retail unit with a single shopfront may simply fail, whatever you do to the internal layout, and no amount of policy argument fixes a floor plate with no second elevation. If flooding is one of the listed matters and the building sits in Flood Zone 2 or 3, you will need a flood risk assessment and a sequential test argument that stands on its own, because the authority cannot grant prior approval on an unevidenced assumption.

The determination period and deemed approval

The headline figure that circulates is deemed approval 56 days after a valid application, and for Part 3 and Part 20 that is right. Other parts run to different clocks. Part 6 agricultural determinations run on 28 days, and the larger home extension scheme under Part 1 runs on 42 days.

Class Period What happens at expiry
Part 3 (including MA and Q) 56 days Development may proceed in accordance with the application
Part 20 (upward extensions) 56 days Development may proceed in accordance with the application
Part 1 Class A (larger extensions) 42 days Development may proceed if no notification is received
Part 6 (agricultural buildings) 28 days Development may proceed, subject to the class conditions

Two practical warnings about relying on the clock. The period runs from receipt of a valid application, so a missing plan, a missing fee or a missing ownership certificate can reset it without the authority telling you clearly. And deemed approval is approval of what you applied for, nothing wider. If the drawings you submitted show four flats and you build five, the fifth is unauthorised.

Agreeing a written extension of time is common and usually sensible. Refusing one and then relying on the 56 days works, but it leaves you holding a development with no conditions tailored to it, which can make discharge of other consents harder later.

Fees and the information to submit

Each class specifies the information required, and the authority may also ask for a site plan, elevations and floor plans where the class calls for design and external appearance to be assessed. Fees for prior approval applications are set in the national fee regulations and are indexed, so check the current schedule on the Planning Portal or the authority's own page before you pay.

Build the submission around the listed matters and nothing else. A short covering note that takes each matter in turn, states the evidence relied on, and attaches the supporting document is worth more than a long planning statement about housing need. Where contamination is a listed matter, a desk study is the proportionate answer for most urban conversions. Where noise is listed, a measured survey beats an assertion that the neighbouring unit is quiet. If you want a drafting start for those documents, the report types grouped by category show what each one normally contains.

An illustrative example under the householder class

Illustrative example. A homeowner wants a single-storey rear extension projecting five metres from the rear wall of a semi-detached house. Beyond three metres, the extension needs the neighbour consultation scheme, so the owner applies to the authority with a written description, plans showing the siting and dimensions, the addresses of the adjoining properties and the fee.

The authority notifies the two adjoining owners. One objects on loss of light. The authority must then consider the amenity impact on adjoining premises, and only that, before deciding whether prior approval is required and whether to grant it. If 42 days pass with no notification to the owner at all, the owner may build in accordance with what was submitted. The figures here are for illustration only and the limits in Part 1 change with the house type and its location.

Starting before the decision

If you begin the development before prior approval has been granted or deemed, the development is not permitted by the Order. That makes it a breach of planning control from day one, and the usual consequence is an enforcement notice or an invitation to submit a retrospective application. Where an enforcement notice is already in effect, the authority may decline to entertain that application at all under section 70C of the Town and Country Planning Act 1990, which is a trap worth reading about before you take the risk.

The only formal way to confirm that what you have built is lawful is a lawful development certificate under section 192 for proposed works or section 191 for existing ones. A solicitor acting for a buyer will ask for one, and an informal email from a planning officer will not do. Articles on refusing to entertain a retrospective application set out how narrow that route becomes once enforcement has started.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it, because the limitations and conditions in each class are detailed and are amended regularly.

Enter your postcode on PlanScope to see which supporting documents a prior approval submission on your site is likely to need.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is prior approval the same as planning permission?

No. Permission is granted by the General Permitted Development Order 2015 itself, and prior approval is a condition attached to that permission for certain classes. The authority only considers the matters listed in the relevant class, such as transport, flooding, contamination or external appearance, rather than the principle of the development or its fit with the local plan.

What happens if the council misses the 56 days?

For Part 3 and Part 20 classes, if the authority has not notified you of its determination within 56 days of a valid application, approval is deemed to be given and you may proceed in accordance with what you applied for. The period only runs on a valid application, so a missing fee, plan or certificate can delay the start of the clock.

Can a refusal of prior approval be appealed?

Yes. A refusal, or a grant with conditions you object to, can be appealed to the Planning Inspectorate in the same way as a refusal of planning permission. Appeals that succeed often do so because the authority refused on a ground that is not in the list of matters the class allows it to consider.

Do I need prior approval for a larger rear extension?

A single-storey rear extension beyond the standard limits needs the neighbour consultation scheme in Part 1 Class A. You give the authority a description, plans, dimensions and the adjoining addresses, it notifies the neighbours, and it then considers the amenity impact on adjoining premises before deciding. The period here is 42 days, not 56.

What confirms that completed works were lawful?

A lawful development certificate is the only formal confirmation. Section 192 of the Town and Country Planning Act 1990 covers proposed works and section 191 covers works already carried out. Conveyancing solicitors routinely ask for one on permitted development schemes, and correspondence with a case officer is not a substitute.

Sources and further reading

prior approvalpermitted developmentgpdoclass machange of useplanning procedure

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Glossary

View all →
Glossary6 min read

Abnormal load route: what it means in a planning case

An abnormal load route is the agreed path an oversized indivisible load takes to site, with the bridges, junctions and street furniture it affects. The planning evidence and the statutory notification are separate processes.

Read article →
Glossary6 min read

No satisfactory alternative: the second derogation test

The second derogation test asks whether the purpose of a development could be achieved another way with less harm to a European protected species. It is judged on purpose, not on the applicant's preference.

Read article →
Glossary7 min read

Protected building: the 400 metre farm rule explained

Part 6 of the General Permitted Development Order uses protected building to mean a permanent building people normally occupy. It sets a 400 metre buffer around livestock housing and slurry storage, measured from the curtilage.

Read article →
Glossary7 min read

Specific sound level

The specific sound level is the contribution of the source alone, not what the meter reads. How BS 4142 defines it, how it is determined and where it is misused.

Read article →
Glossary6 min read

First Homes: the discount, the caps and the 25% share

First Homes are discounted market sale units secured in perpetuity by a section 106 agreement and a title restriction. The discount, the price cap and the first-charge ordering all shape a scheme's affordable mix.

Read article →
Glossary7 min read

Ransom strip and the ha-ha of access rights

A retained sliver between a site and the highway blocks implementation rather than permission. How ransom strips arise, what the certificates require, and how they are resolved.

Read article →