Waste streams and recovery rates in a waste plan
Recovery and diversion are different numbers. Forecast by activity, name the destinations, and build the reporting format in before work starts.
A construction waste recovery rate is the proportion of waste leaving the site, by weight, that is reused, recycled or otherwise recovered rather than sent to landfill or incineration without energy recovery. Any waste plan submitted with a planning application has to forecast that figure before work starts and then report the actual figure afterwards, and the gap between the two is what a monitoring officer looks at.
Forecasting it properly means working from activities rather than from a single tonnage. Demolition, excavation and construction produce different streams in wildly different quantities, and a plan that gives one combined number for all three cannot be checked.
What the plan has to forecast
The statutory regime changed in 2013, when the Site Waste Management Plans Regulations 2008 were revoked in England. Many local plan policies and planning conditions still require a plan, so the document survives as a planning requirement rather than a statutory one.
The waste hierarchy duty did not go away. The Waste (England and Wales) Regulations 2011 require anyone taking waste management measures to apply the hierarchy of prevention, preparing for reuse, recycling, other recovery and finally disposal, and to confirm they have done so on the waste transfer note. That duty is the backbone of any plan.
So the forecast needs four things: the total arising by stream, the destination for each stream, the recovery rate implied, and the measures that will be taken higher up the hierarchy. A site waste management plan that lists skip types without naming destinations has forecast nothing.
Identifying waste streams by activity
Split the forecast by activity before you split it by material. The three activities behave differently and are often handled by different contractors under different contracts.
| Activity | Dominant streams | Where the tonnage sits |
|---|---|---|
| Demolition | Concrete, brick, timber, metals, plasterboard, asbestos | Largest by weight on most redevelopment sites |
| Excavation | Soils, made ground, hardcore | Largest by volume, and the hardest to divert off site |
| Construction | Packaging, offcuts, plasterboard, timber, insulation, metals | Smallest by weight, highest by number of streams |
Excavated material is the stream that decides the headline figure on most sites. Reusing site-won material in landscaping, level changes or as engineering fill keeps it out of the waste figures altogether, which is prevention rather than recovery and sits at the top of the hierarchy. Where material has to leave, the material resources framework for excavated waste determines whether it can go to another site as a by-product or has to be handled as waste, and that distinction is worth resolving early.
Classify each stream properly using the standard waste classification approach, with the relevant code recorded, because the carrier and the receiving site both need it and a misclassified stream is a duty of care failure.
Recovery and diversion targets
Two numbers appear in planning documents, and they are not the same.
Diversion from landfill measures what avoids landfill, which includes energy recovery and incineration. Recovery measures reuse, recycling and other recovery, which is the narrower and more meaningful figure. A plan claiming 95 per cent diversion with 60 per cent recovery is telling you most of the remainder went to an energy from waste plant.
The policy anchor for non-hazardous construction and demolition waste is the 70 per cent recovery target carried into the Waste (England and Wales) Regulations 2011. Local plans and, in London, the Mayor's policies frequently set higher figures, and some authorities set separate targets for excavation and for construction waste. Read the adopted policy and state which target the plan is written against.
Set the target by stream rather than as an average, and show the arithmetic. A target expressed as a single percentage with no stream breakdown cannot be monitored, and a condition requiring it cannot be enforced.
Hazardous waste and asbestos handling
Hazardous streams change the plan from an exercise in logistics into a compliance programme.
Asbestos is the common one on any pre-2000 building. A refurbishment and demolition survey has to be carried out before work starts, and licensable removal has to be done by a licensed contractor under the Control of Asbestos Regulations 2012. Asbestos waste is hazardous waste, needs consignment notes, and can only go to a permitted site.
Other streams that recur are contaminated soils from made ground, which need classification by analysis rather than by assumption, treated timber, fluorescent tubes and lamps, oils and fuels from plant, paints and sealants, and refrigerant gases from stripped-out plant. Each needs separate storage, separate carriers in some cases, and consignment documentation.
Where contamination is suspected, the waste plan and the contaminated land assessment have to agree. A plan forecasting clean inert soils for a site the desk study describes as a former gasworks will not survive first contact with a laboratory result.
Duty of care and carrier records
Section 34 of the Environmental Protection Act 1990 imposes the duty of care on everyone in the waste chain, and it is the part of the regime most often failed through paperwork rather than through bad practice.
The records that have to exist are a waste transfer note for every non-hazardous movement, a consignment note for every hazardous movement, confirmation that the carrier is registered, confirmation that the receiving site holds the relevant permit or exemption, and the written statement that the hierarchy has been applied. Keep transfer notes for two years and hazardous consignment notes for three.
Check the carrier registration and the receiving site's permit yourself rather than relying on an assurance. Both are verifiable from the public registers, and a plan that names the registers as the verification route is more credible than one that does not.
And be realistic about who holds these records. On a site with a demolition contractor, a groundworks contractor and a principal contractor, the records sit in three places unless someone is made responsible for collating them. Name that person in the plan.
Reporting actual against forecast
The closing report is where most plans fall apart, because nobody collected the data as the job went along.
Build the reporting format into the plan at the start: a table by stream showing forecast tonnage, actual tonnage, destination, and recovery rate, with the transfer notes referenced. Reconcile monthly rather than at the end. Weighbridge tickets are the primary evidence and skip volumes are not, so where a waste contractor reports by skip the conversion factors used have to be stated.
Explain the variances rather than restating the numbers. A demolition tonnage 40 per cent above forecast usually means the structure contained more concrete than the survey suggested, and saying so is better than presenting a figure that looks like a failure of control. Where the recovery rate came in below target, say which stream caused it and why.
A pre-redevelopment audit carried out before demolition gives a far better forecast than a benchmark figure, because it records what is actually in the building and what can be reclaimed for reuse.
What belongs in a condition
A workable condition asks for three things at three points in time, and nothing else.
- A waste plan submitted and approved before demolition or construction starts, setting out streams, destinations, targets and responsibilities.
- Compliance with the approved plan during the works, with records kept and made available on request.
- A closing report within a stated period after completion, giving actual tonnages, destinations and recovery rates by stream against the forecast.
Conditions that require a particular percentage without defining diversion or recovery, or without specifying the measurement basis and the reporting point, are unenforceable in practice. Where the authority offers pre-application discussion, agree the wording then. Tie the plan to the construction management plan so that haulage routes, wheel washing and storage areas are consistent across both documents.
PlanScope drafts waste documents structured to UK planning policy, with site quantities flagged where they are not yet known. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Are site waste management plans still a legal requirement?
Not as a statutory duty in England. The Site Waste Management Plans Regulations 2008 were revoked in 2013, so the plan survives as a planning requirement imposed through local plan policy or a condition. The waste hierarchy duty under the Waste (England and Wales) Regulations 2011 still applies to every project regardless of whether a plan is required.
What is the difference between diversion and recovery?
Diversion from landfill counts anything that avoids landfill, including incineration and energy recovery. Recovery counts reuse, recycling and other recovery, which is the narrower and more meaningful measure. A plan reporting high diversion and much lower recovery is telling you most of the balance went to an energy from waste plant, so state which measure the target uses.
How is excavated soil counted in the recovery rate?
Material reused on site in landscaping, level changes or as engineering fill does not become waste at all, which is prevention at the top of the hierarchy rather than recovery. Where material has to leave the site, whether it can go elsewhere as a by-product or must be handled as waste affects the figures, so resolve that question early.
Who is responsible for keeping waste transfer notes?
Everyone in the chain carries the duty of care under section 34 of the Environmental Protection Act 1990. On a site with separate demolition, groundworks and principal contractors the records sit in three places, so the plan should name the person responsible for collating them. Keep transfer notes for two years and hazardous consignment notes for three.
What does a waste plan need to say about asbestos?
That a refurbishment and demolition survey will be carried out before work starts, that licensable removal will be done by a licensed contractor under the Control of Asbestos Regulations 2012, and that asbestos waste will be consigned as hazardous waste to a permitted site. Asbestos tonnage should appear as a separate stream rather than inside a mixed demolition figure.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.