Abnormal costs and how a viability reviewer tests them
Abnormal costs are site-specific costs an ordinary site would not carry. Reviewers test whether they are evidenced and whether they have already been reflected in the land value.
Abnormal costs are site-specific costs that an ordinary site would not carry. Demolition, remediation, piling, retaining structures, service diversions, archaeological mitigation, off-site highway works. In a planning viability assessment they sit outside the base build rate and are itemised, and that is exactly why a reviewer looks at them hardest. Abnormal costs in planning viability are where an appraisal either holds up or falls apart.
The reviewer's starting assumption is that abnormals have already been reflected in what the land was worth. If you are claiming them as a reason to reduce affordable housing, you need to show they were not also priced into the land.
What counts as abnormal rather than normal
The test is whether a reasonably typical site for that type of development would incur the cost. Foundations are normal. Piling 18 metres through made ground because the site was a former gasworks is abnormal.
Items that are generally accepted as abnormal:
- Demolition and the removal of existing substructures, slabs and basements.
- Remediation of contamination, including disposal of hazardous waste by classification and volume.
- Piled or otherwise engineered foundations driven by ground conditions rather than by building height.
- Retaining structures and earthworks on a sloping site, beyond standard level tolerance.
- Diversion of public sewers, high voltage cables, gas mains or water mains crossing the site.
- Utility reinforcement where the network cannot supply the development without upstream works.
- Attenuation storage or pumped drainage required by a constraint such as a source protection zone.
- Archaeological excavation and recording secured by condition.
- Asbestos removal, party wall works and underpinning of adjoining property.
- Section 278 highway works and new access construction.
Items that are not abnormal, however irritating: standard professional fees, planning application fees, marketing, finance, and the ordinary cost of meeting Building Regulations.
Why the distinction matters in an appraisal
National viability guidance sets the framework. The benchmark land value is established using existing use value plus a premium to the landowner, and the guidance is clear that the price actually paid for land is not determinative. It also makes the point that land value should reflect the policy requirements and the site's abnormal costs.
That is the crux. A site with £800,000 of remediation is worth less than an identical site without it, and the reduction should show up in the land value rather than in the affordable housing offer. Where an applicant has paid a price that ignored the abnormals, the overpayment is the applicant's commercial risk, not a planning justification.
So the reviewer tests two things at once. Are the abnormal costs real and properly evidenced? And has the benchmark land value been set on a basis that already accounts for them?
Viability is a material consideration rather than a policy override, and the weight it carries depends on the quality of the evidence. Where that evidence is weak, the authority is entitled to apply policy in full, and the appraisal becomes an argument you lose quietly.
Evidence a reviewer will accept
There is a clear hierarchy, and the top of it is specific to your site.
The strongest evidence is a measured cost plan from a quantity surveyor, with quantities taken off drawings and rates attributed, setting out each abnormal as a separate line with its basis. Behind that sit the technical reports the costs come from: a remediation strategy with volumes and waste classifications, a foundation design from the structural engineer, a connection offer from the distribution network operator, a diversion quotation from the sewerage undertaker, a written scheme of investigation for archaeology with an agreed scope.
Weaker, and usually challenged: a percentage allowance for abnormals applied to the build cost. A round figure with no derivation. A contractor's budget letter with no quantities. An allowance for a risk that the technical reports do not support.
Viability work is in the group of report types where authorities expect a suitably qualified author and professional review is strongly advised, because the review will be carried out by someone applying professional standards for financial viability reporting. A Viability Assessment draft can structure the argument and the policy framework, and the cost plan and valuation evidence have to come from the quantity surveyor and the valuer.
Double counting against contingency and base rates
This is the most common finding in a review report, and it is usually unintentional.
Three places the same money gets counted twice. A base build rate taken from the upper quartile of published cost data, which already reflects complex sites, with abnormals then added on top. A contingency set at a level appropriate to a difficult site, applied to a cost plan that already itemises the difficulties. And an abnormal that duplicates a condition cost already included elsewhere, such as drainage attenuation appearing both in the abnormals schedule and in the external works allowance.
The way through it is transparency. State the base rate source and the quartile. State the contingency percentage and what it covers. Cross-reference each abnormal to the technical report it derives from. A reviewer who can follow the arithmetic is far less likely to apply a blanket reduction.
How abnormals interact with benchmark land value
Where the existing use value is low, a paddock or a vacant yard, the abnormals usually have to be absorbed by the scheme rather than by the land, because there is little land value to erode. Where the existing use value is high, a trading industrial building for instance, there is more room for the abnormals to reduce the residual.
Reviewers will look for the circular argument: a benchmark land value derived from comparable transactions on unconstrained sites, with abnormals then deducted as costs. If the comparables are clean sites, they are not comparable.
The better approach is to evidence the benchmark on an existing use value plus premium basis, explain what the premium reflects, and then run the abnormals as costs. Where market comparables are used as a cross-check, adjust them explicitly for site constraints and show the adjustment.
An illustrative worked example
Illustrative only, with figures chosen to show the method rather than to represent any real site.
A brownfield plot of 0.6 hectares, former vehicle repair use, 24 flats proposed. The base build cost is taken at the median published rate for the building type. Abnormals are itemised as demolition and slab removal, remediation of hydrocarbon contamination with 1,200 tonnes classified for disposal, piled foundations to 12 metres, a 15 metre sewer diversion, and an attenuation tank.
The reviewer accepts demolition, remediation and piling, each supported by the ground investigation and the structural design. The sewer diversion is reduced because the undertaker's quotation covers a longer diversion than the final layout needs. The attenuation tank is removed entirely, because the external works allowance already includes drainage at a rate that covers it.
Net effect: abnormals reduced by about a fifth, and the affordable housing offer increases accordingly. Nothing in that outcome was unreasonable, and all of it was avoidable with a cross-referenced cost plan.
Getting through the review
Four practical points.
Commission the technical reports before the appraisal, not alongside it. An appraisal built on assumptions is an appraisal that gets discounted.
Expect the assessment to be published. National guidance favours transparency in viability assessment, so write it on the basis that objectors will read it.
Deal with the policy costs properly. Community Infrastructure Levy liability is a cost line and the rules on what is chargeable development under the Community Infrastructure Levy determine the figure, while the affordable housing position belongs in an Affordable Housing Statement rather than being left to the appraisal narrative.
And expect a review mechanism. Where viability is used to reduce contributions, authorities increasingly secure a late-stage review in the section 106 agreement, so that a scheme that performs better than forecast pays more. Negotiate the trigger and the methodology at the same time as the headline offer, because the mechanism is where the value sits.
Where contamination drives the abnormals, the Contaminated Land Assessment stages are the evidence base for the figures, and weak reporting there weakens the whole appraisal. Viability arguments also sit alongside the broader question of what counts as a material consideration.
This is general guidance, not legal advice, and viability is site specific, so take advice from a qualified professional. For specialist technical reports, qualified professional input may be required. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
What makes a cost abnormal rather than normal?
Whether a reasonably typical site for that type of development would incur it. Foundations are normal; piling through made ground because the site was a former gasworks is abnormal. Demolition, remediation, retaining structures, service diversions, utility reinforcement, archaeology and section 278 works are the usual accepted items.
Should abnormal costs reduce affordable housing or the land value?
The land value. National viability guidance establishes benchmark land value using existing use value plus a premium, and says land value should reflect both policy requirements and the site's abnormal costs. The price actually paid is not determinative, so an overpayment that ignored the abnormals is a commercial risk rather than a planning justification.
What evidence do reviewers accept for abnormals?
A measured cost plan from a quantity surveyor, with quantities taken from drawings and each abnormal as a separate line, cross-referenced to the technical report it derives from. That means a remediation strategy with volumes, a foundation design, a network connection offer and a diversion quotation. Percentage allowances and round figures are routinely challenged.
Where does double counting usually occur?
Three places. A base build rate taken from the upper quartile of published cost data, which already reflects complex sites, with abnormals added on top. A contingency set for a difficult site applied to a cost plan that already itemises the difficulties. And abnormals that duplicate items already inside the external works allowance, drainage being the common one.
Will my viability assessment be published?
Expect it to be. National guidance favours transparency in viability assessment, so assessments submitted with applications are normally made publicly available. Write it on the basis that objectors, local members and a third-party reviewer will read it, and avoid any assertion you would not want to defend in those terms.
Sources and further reading