Costs, Fees and Budgeting

Budgeting an application for one to nine dwellings

7 min readBy PlanScope Editorial Team

On a minor residential scheme the evidence base and the survey seasons drive the budget, not the application fee. A stage by stage way to build the cash flow.

A planning application for one to nine dwellings is a minor application, and the fee is the smallest line in the budget. The money goes on surveys, and the programme goes on survey seasons. Budgeting a minor application cost realistically means pricing the evidence base first, then the fee, then the liabilities that land after permission is granted.

The number that catches self-builders out is not the application fee. It is the gap between submitting in October and getting a bat survey in May.

The fee calculation for dwellings

Planning application fees in England are set by the national fee regulations. They were uplifted in December 2023 and are indexed annually from 1 April, so any figure in an older guide is wrong. Take the current numbers from the published fee guidance or the fee calculator on the Planning Portal.

What you need to know is the structure rather than the amounts.

  • For outline and full applications for dwellings, the fee is charged per dwelling up to a threshold, with a banded amount above it. On a scheme of one to nine units you pay per unit.
  • Householder applications have their own flat fee, which is lower, and apply only to works to a single existing dwelling.
  • Reserved matters approval, a section 73 variation, a non-material amendment under section 96A and each request to discharge conditions carry their own fees.
  • An application for a lawful development certificate for an existing use is charged at a multiple of the equivalent application fee.
  • Pre-application advice is discretionary, locally priced, often banded by scheme size, and usually subject to VAT. It is not covered by the national regulations.

One further point. The planning guarantee entitles you to a fee refund where an application is not determined within 26 weeks and no extension of time has been agreed. Check the current fees guidance for how it operates before relying on it.

Surveys that are effectively unavoidable

On a site of one to nine dwellings, the following tend to be required rather than optional, and the local validation list is the document that decides.

Document When it is needed
Topographical survey Any new build, and essential where levels change
Planning Statement Expected on most minor applications
Design and Access Statement Major development, or one or more dwellings in a conservation area or World Heritage Site under Article 9 of the DMPO 2015
Preliminary Ecological Appraisal Almost always for a greenfield or garden site
Biodiversity net gain information Unless an exemption applies
Tree survey to BS 5837 Where trees are on or adjacent to the site
Flood Risk Assessment Flood Zone 2 or 3, or a site of one hectare or more
Drainage strategy Where surface water cannot discharge to a sewer, or the authority requires SuDS detail
Land contamination Phase 1 desk study Any previous industrial, agricultural or commercial use
Heritage Statement Within or adjacent to a conservation area, or affecting a listed building

Several of these need a suitably qualified author. Land contamination reports require a suitably qualified and experienced person working to BS 10175, protected species work requires a licensed ecologist, and the biodiversity metric expects a competent person under the Environment Act 2021 regime. Those are legal requirements rather than preferences.

A Flood Risk Assessment and a Biodiversity Net Gain Assessment are the two that most often arrive late and hold up validation, so check both at the outset.

Where the small site exemptions help

Three exemptions change the budget materially at this scale.

Biodiversity net gain. Small sites, broadly fewer than ten dwellings on a site under 0.5 hectares, use the small sites metric rather than the full statutory metric, which reduces the assessment cost. There is an exemption for self-build and custom build development of up to nine dwellings on a site of less than 0.5 hectares, an exemption for householder applications, and a de minimis exemption where the development affects less than 25 m² of on-site habitat and no priority habitat. Check the current guidance against your site, because the conditions are specific and the exemptions are claimed on the application form.

Affordable housing. The national policy threshold for seeking affordable housing contributions is normally ten or more dwellings, so schemes of one to nine are generally outside it. Designated rural areas are the exception, where a lower threshold can apply, so check the local plan.

Community Infrastructure Levy. Self-build exemption relieves a dwelling built by or for the owner for their own occupation, and there is a separate exemption for residential extensions and annexes. The procedure is unforgiving: claim before work starts, serve the notice the regulations require before any work begins, and remain in occupation for three years. Miss a step and the full liability becomes payable.

Season-driven survey costs

The seasons set the programme, and a missed window is the most expensive mistake available at this scale.

Survey Window
Preliminary roost assessment for bats Any time
Bat emergence surveys May to September, best May to August
Great crested newt eDNA 15 April to 30 June
Reptile presence surveys April to October, best April to May and September
Breeding bird surveys March to August
Botanical surveys April to September

The practical consequence: commission the preliminary ecological work before the design is finished, so you know which window you are working to. A design frozen in September and an emergence survey needed the following May means a nine month delay that no amount of money shortens.

Where a nutrient neutrality or water neutrality catchment applies, add mitigation cost and a longer programme. The note on budgeting nutrient neutrality mitigation sets out what that involves.

Obligations and levy liabilities

At one to nine dwellings a section 106 agreement is less likely than on a major scheme, but not rare. Authorities use them for access rights, drainage adoption, open space maintenance and occasionally for a contribution where a local policy requires one below the affordable housing threshold.

Budget for the legal cost on both sides. The council's legal fees for drafting or reviewing the agreement are normally payable by the applicant, and the sum is agreed before completion.

Community Infrastructure Levy, where the authority has a charging schedule, is calculated on net additional floorspace at the rate for the zone and the use, indexed. The liability notice arrives after permission, and payment is triggered by the start of work. On a small scheme with no exemption, this can be the largest single planning cost, so look up the charging schedule before you buy the site.

Reserved matters, conditions and the second round of fees

Permission is not the end of the spending.

Each condition discharge application carries a fee and an eight week determination period, and a permission with twelve conditions may need three or four separate submissions. Where you went down the outline route, reserved matters approvals come with their own fees and their own eight week periods. The cost of a Class Q prior approval application is a useful comparison if you are weighing routes on a rural site.

Group the discharges sensibly. One submission covering materials, landscaping and boundary treatments is one fee and one eight week wait, where three separate submissions are three of each.

Building the cash flow

Set the budget out by stage rather than as a single number, because the stages are months apart.

  1. Site appraisal and pre-application advice, including the pre-app fee and the first ecological walkover.
  2. Surveys and specialist reports, phased around the seasonal windows.
  3. Design and drawings to application standard.
  4. Application fee and submission.
  5. Validation and determination, with a contingency for further information requests.
  6. Section 106 legal costs, where applicable.
  7. Condition discharge submissions.
  8. Levy payment before work starts, net of any exemption.

Illustrative example of sequencing rather than cost: an ecological walkover in February identifies moderate bat roost potential in an outbuilding. Emergence surveys run in May and June, the application is submitted in July, validated in August, and determined in October. Conditions are discharged over the following three months, and work starts in February of the following year, twelve months after the first walkover. The budget has to carry the site for all of it.

PlanScope covers the narrative documents in that list. One report is free, any single report is £50 with in-platform editing and PDF export, and the Professional tier is £150 per month or £600 per year for unlimited reports with your own branding. You can see PlanScope pricing or browse the 66 report types to work out which ones your scheme needs.

This is general guidance, not legal or financial advice; fees, levy rates and exemptions change and are set locally in part, so check the current national fee schedule, your authority's charging schedule and the current biodiversity net gain guidance before relying on any figure here. For specialist technical reports, qualified professional input may be required. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How is the fee calculated for one to nine dwellings?

Per dwelling, under the national fee regulations, up to a threshold above which a banded amount applies. Fees were uplifted in December 2023 and are indexed annually from 1 April, so use the current published fee guidance or the Planning Portal fee calculator rather than a figure from an older appraisal.

Which surveys are unavoidable at this scale?

A topographical survey, a Planning Statement and a preliminary ecological appraisal on almost any new build site, plus biodiversity net gain information unless an exemption applies. Add a BS 5837 tree survey where trees are present, a flood risk assessment in Flood Zone 2 or 3, and a Phase 1 desk study where there is a previous commercial or agricultural use.

Does biodiversity net gain apply to a small scheme?

Usually, but through the small sites metric rather than the full statutory metric. There are exemptions for self-build and custom build of up to nine dwellings on a site under 0.5 hectares, for householder applications, and where less than 25 m² of on-site habitat and no priority habitat is affected. Check the current guidance against your site.

Will I have to provide affordable housing?

Generally not below ten dwellings, since the national policy threshold is normally ten or more units. Designated rural areas are the exception, where a lower threshold can be applied, so check the adopted local plan. Some authorities seek other contributions below the threshold through a section 106 agreement.

How do I avoid losing the self-build levy exemption?

Follow the procedure exactly. Claim the exemption before work starts, serve the notice the levy regulations require before any work begins, and occupy the dwelling as your sole or main residence for three years. Missing any step makes the full liability payable, and authorities apply the rules strictly.

What costs come after permission?

Condition discharge fees, with an eight week period for each submission, reserved matters fees if you took the outline route, section 106 legal costs where an agreement is needed, and the levy payment triggered by the start of work. Grouping condition discharges into one submission saves both fees and time.

Sources and further reading

planning feesself buildbudgetingbiodiversity net gaincilminor development

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting6 min read

The costs that arrive after planning permission is granted

Permission is the start of the spending, not the end. Condition discharge, verification reporting, the levy, section 278 works, Building Regulations and utility connections all arrive after the build cost is fixed.

Read article →
Costs, Fees and Budgeting6 min read

What a biodiversity net gain shortfall costs in credits

Where a scheme cannot deliver its 10 per cent gain on site or off site, statutory credits fill the gap at a published tiered price set deliberately high. The hierarchy, the rounding and the 30 year obligation all affect the budget.

Read article →
Costs, Fees and Budgeting7 min read

Budgeting a variation of condition during construction

A departure from the approved drawings breaches a condition. The budget item that matters is the standing time while the amendment or section 73 application runs.

Read article →
Costs, Fees and Budgeting7 min read

What a local validation list adds to application cost

Two neighbouring councils can require very different documents for an identical scheme. How local validation lists are adopted and limited, which items cost most, and how to build a document budget before quoting.

Read article →
Costs, Fees and Budgeting7 min read

Section 278 highway works: the cost elements nobody budgets

Section 278 of the Highways Act 1980 lets a developer build on the public highway at its own expense, and the authority charges for everything around it. The lines that appear on real accounts and rarely on early budgets.

Read article →
Costs, Fees and Budgeting7 min read

Budgeting a planning inquiry appeal: what drives the cost

Section 78 appeals carry no fee, so an inquiry budget is professional time: topics in dispute, witnesses needed and sitting days programmed. How to price those three before instructing anyone, and how to cut them without weakening the case.

Read article →