Budgeting a variation of condition during construction

7 min readBy PlanScope Editorial Team

A departure from the approved drawings breaches a condition. The budget item that matters is the standing time while the amendment or section 73 application runs.

A change on site that departs from the approved drawings is a breach of condition, and the cost of putting it right is rarely the application fee. Budget instead for the standing time while the application runs, because that is where the money goes. A section 96A non-material amendment has no statutory determination period and many councils turn one round in two to four weeks. A section 73 application to vary a condition is a full planning application with 21 days of publicity and an eight week determination period, and the realistic allowance on a live site is closer to 10 to 12 weeks.

Work out which of the two routes applies before you price anything, because the difference between them drives the whole budget.

Spotting the change that breaches a condition

Almost every permission carries a condition requiring development to be carried out in accordance with the approved drawings, listed by number and revision. Any departure from those drawings breaches that condition, whether or not it is visible from the street.

The changes that catch sites out are mundane. A window moved 300 millimetres to clear a structural opening. A different brick because the specified one has a 20 week lead time. A heat pump relocated to the flank because the original position fouls a drainage run. A finished floor level raised 150 millimetres after the ground investigation came back.

Set a rule on site that any deviation from an approved drawing goes to the planning lead before it is built. Retrospective applications cost more, carry a real risk of refusal, and expose the scheme to an enforcement notice under section 171A of the Town and Country Planning Act 1990.

Choosing between section 96A and section 73

Section 96A of the 1990 Act allows the authority to make a non-material amendment to an existing permission. There is no statutory test of what is non-material beyond the requirement that the authority must have regard to the effect of the change, so it is a judgement for the council and it varies between authorities. Material considerations raised by neighbours do not formally apply, and there is no statutory consultation.

Section 73 allows an application to develop land without complying with a condition previously imposed. It produces a new planning permission sitting alongside the original, with its own decision notice and its own full set of conditions.

Factor Section 96A Section 73
Statutory determination period None prescribed 8 weeks
Publicity and consultation Not required 21 days
Outcome Amendment to the original permission A new permission alongside the original
Can change the description of development No No
Conditions Original conditions stand All conditions reimposed on the new permission
Fee Lower, set nationally Full application fee band

Fees are set by the national fee regulations and have been indexed annually since April 2025, so check the current schedule on the Planning Portal or the council website rather than working from a figure in an old appraisal.

Section 73B, inserted by the Levelling-up and Regeneration Act 2023, creates a further route for variations whose effect is not substantially different from the existing permission. Check whether it is in force on legislation.gov.uk before you build a programme around it, because the 2023 Act provisions have been brought into effect in stages.

Standing time while the application runs

This is the number that matters and the one that gets left out of the budget.

Price the following for every week the change is unresolved: site establishment and welfare, plant on hire, the preliminaries bill, supervision, finance on drawn-down funding, and any liquidated damages exposure under the building contract. On a small residential site those costs commonly exceed the professional fees for the application several times over.

Three ways to compress the exposure. Carry on with work that is unaffected by the change where the contract and the condition allow it. Submit on the day the change is identified rather than when the full package is drawn. And ask the case officer at the outset whether they consider the change non-material, because a ten minute call can save six weeks.

Illustrative example: a developer of 12 houses discovers at foundation stage that the approved finished floor levels on plots 7 to 9 sit 200 millimetres below the level the drainage design needs. Treated as a section 73 variation, the application takes 11 weeks from submission to decision. The applicant keeps plots 1 to 6 moving and reprogrammes the groundworks gang, which limits the standing time to the three week gap at the end. The application fee is a minor part of the total cost of the change.

Building control and warranty consequences

A planning variation is not the end of it. Any change affecting the structure, drainage, fire strategy, thermal performance or access needs to go back through building control as an amendment to the approved documents or the initial notice.

Warranty providers hold their own position. Most require notice of design changes and some require sign-off before the work is covered, so a change built ahead of the warranty inspection can create a defect in the cover that only surfaces on sale.

Where the building is higher risk under the Building Safety Act 2022, the change control regime at Gateway Two is separate again and a notifiable change cannot be built before it is approved. Build that into the programme rather than treating it as paperwork.

Conditions that cannot be varied at all

Section 73 has limits that are easy to miss.

The description of development cannot be changed. The Court of Appeal in Finney v Welsh Ministers confirmed that a section 73 permission cannot be granted where the variation would conflict with the operative part of the permission, so a scheme described as 12 dwellings cannot become 14 by varying a drawings condition.

The time limit for implementation cannot be extended by varying the condition that imposes it. That was removed as a route in 2012, and the only option for an expiring permission is a fresh application.

A condition that goes to the heart of the permission is also outside the scope. Where the proposed variation would produce a development wholly different from the one permitted, the authority should require a new application.

And a section 73 permission must be capable of being implemented, so the original permission has to be live. Varying a condition on a permission that expires in four weeks produces a new permission with the same expiry date.

Evidence that the change is acceptable

The application has to show the change, not describe it. Supply superseded and proposed drawings with the revision letters and a drawing schedule that makes the substitution unambiguous.

Where the change touches a technical matter, the supporting evidence has to be updated rather than referenced. A raised floor level engages the flood risk evidence. A relocated plant item engages noise. A revised roof form engages daylight to the neighbour. Councils refuse variations where the original technical report no longer describes the scheme and nobody has said what the new position is.

A short covering Planning Statement that lists each change, the condition it engages, the original assessment and why the conclusion is unchanged will carry most straightforward variations. Keep it to the changes and resist reopening settled matters.

A change control process that keeps the cost down

Four habits reduce the number of variations and the cost of the ones you cannot avoid.

  1. Hold a pre-start workshop that walks the contractor through every condition and every approved drawing, so the site team knows what is fixed.
  2. Discharge the conditions that must be cleared before work starts early and in groups, because a variation submitted while conditions are outstanding usually sits behind them in the queue. Our note on pre-start condition discharge costs on a phased site sets out the sequencing.
  3. Keep a single register of approved drawing numbers and revisions, held by one person, and reconcile it against the construction issue set monthly.
  4. Check the levy position before submitting, because a section 73 permission triggers a recalculation of the chargeable amount under the Community Infrastructure Levy Regulations 2010, with relief for the original liability. Our guide to challenging a CIL liability covers what to do when the recalculation looks wrong.

Budget a contingency for variations at the outset. On a site with any ground uncertainty or a long lead material, assuming no changes at all is the optimistic case rather than the base case.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.

PlanScope drafts the supporting statements for variations and resubmissions, and its pricing is one free report, £50 per report, or £150 per month for unlimited reports. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is the difference between section 96A and section 73?

Section 96A produces a non-material amendment to the existing permission with no prescribed determination period and no statutory consultation. Section 73 is a full application to vary a condition, carries 21 days of publicity and an eight week period, and produces a new permission alongside the original with all conditions reimposed.

Can section 73 be used to change the description of development?

No. The Court of Appeal in Finney v Welsh Ministers confirmed that a section 73 permission cannot conflict with the operative part of the permission. A scheme described as 12 dwellings cannot become 14 by varying a drawings condition, so a change of that kind needs a fresh application.

Can I extend the life of a permission by varying the time limit condition?

No. That route was removed in 2012 and section 73 cannot be used to extend the implementation period. A section 73 permission also carries the same expiry date as the original, so varying a condition on a permission with four weeks left produces a new permission expiring at the same time.

Does a section 73 permission change my Community Infrastructure Levy liability?

It triggers a recalculation of the chargeable amount under the Community Infrastructure Levy Regulations 2010, with credit given for the liability under the original permission. Check the recalculation before you submit, because a change in floorspace or in the relief position can produce an unwelcome demand notice.

Do I need to go back to building control as well?

Usually yes. Changes affecting structure, drainage, fire strategy, thermal performance or access need an amendment to the approved documents or initial notice. Warranty providers set their own notice requirements, and higher-risk buildings have a separate change control regime at Gateway Two under the Building Safety Act 2022.

Sources and further reading

section 73section 96aconditionsconstructionbudgetingcil

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting7 min read

Press and site notices: the costs councils recover

Article 15 publicity is the authority's duty, paid for from the application fee. The advertisement costs that land on a developer come from highway orders, late Environmental Statements and performance agreements.

Read article →
Costs, Fees and Budgeting7 min read

Outline or full planning application: fees and risk

The reserved matters fee is calculated as if it were a full application, so the outline route rarely saves fees. What it saves is abortive design cost and risk.

Read article →
Costs, Fees and Budgeting7 min read

Bonds and sureties for landscaping and highway works

Security for landscaping and adopted highway works comes through section 106, section 278 or section 38, never a condition. How bonds are sized, priced and released.

Read article →
Costs, Fees and Budgeting6 min read

Screening and scoping opinions cost nothing, so use them

Neither a screening nor a scoping opinion attracts a planning fee, and both narrow what consultants can charge you for. Few tools in the system are better value.

Read article →
Costs, Fees and Budgeting7 min read

Demolition prior notification: cost and when it applies

Demolition is development. Part 11 of the GPDO turns most of it into a 28 day prior approval, but conservation areas, listed buildings and the Building Act notice all sit outside that route.

Read article →
Costs, Fees and Budgeting7 min read

Free planning applications for disabled adaptations

The 2012 fee regulations remove the planning fee for works providing access or greater safety, health or comfort for a disabled person, in homes and in buildings open to the public. It must be claimed on the application.

Read article →