Costs, Fees and Budgeting

Demolition prior notification: cost and when it applies

7 min readBy PlanScope Editorial Team

Demolition is development. Part 11 of the GPDO turns most of it into a 28 day prior approval, but conservation areas, listed buildings and the Building Act notice all sit outside that route.

The demolition prior notification fee is one of the cheapest items in a demolition budget, and the procedure around it is where the programme risk sits. Demolition of a building is a building operation under section 55(1A) of the Town and Country Planning Act 1990, so it is development. Part 11 of Schedule 2 to the General Permitted Development Order 2015 grants permitted development rights for most of it, subject to a prior approval application dealing with the method of demolition and the restoration of the site, determined in 28 days. Conservation areas and listed buildings sit outside that route entirely, and a separate notice to building control under the Building Act 1984 runs alongside it.

Demolition as development, and the exceptions

Not every demolition needs anything from the planning department. A direction made by the Secretary of State describes buildings whose demolition is not development at all, and the main exclusions are buildings with a cubic content of 50 cubic metres or less and most gates, fences, walls and other means of enclosure outside conservation areas.

The direction was narrowed in 2014 following litigation about the demolition of unlisted buildings, and the effect is that demolishing a dwellinghouse, or a building adjoining a dwellinghouse, is development. Partial demolition is a different question again and often forms part of an alteration rather than a demolition, which is usually dealt with in the main planning application.

Start by measuring the cubic content. A single garage is often under the threshold and a pair of them is not.

Prior notification of method and restoration

Where Part 11 applies, the developer applies to the local planning authority for a determination as to whether prior approval is required for the method of demolition and any proposed restoration of the site. Those two matters are the whole scope. The authority cannot use the application to reconsider whether the building should go.

What goes in is modest: a site location plan, a plan of the building to be demolished, a method statement describing the sequence and the plant, and a restoration proposal describing how the site will be left, usually hoarded, levelled and seeded or surfaced. Where the building adjoins others, the method statement needs to deal with temporary support and party structures.

Urgent demolition in the interests of health or safety is treated differently. The work can proceed, but the developer has to notify the authority as soon as reasonably practicable, describing the building, the works and why they were urgent. Do not use that route for programme convenience.

The fee and the determination period

The fee for a Part 11 prior approval application is set by the national fee regulations and sits in the low tens of pounds band for prior approval applications where no specific category applies. National planning fees were uplifted in December 2023 and are indexed annually from April, so check the current figure in the fee regulations or on the Planning Portal before you fix the budget rather than relying on a figure quoted anywhere else.

The determination period is 28 days from receipt of a valid application. The developer must not begin before one of three things happens: a written notice that prior approval is not required, a written grant of prior approval, or the expiry of 28 days without the authority responding. That third limb is real, and the deemed consent on expiry is one reason this route is faster than a planning application.

Against the fee, the cost that matters is the professional time in the method statement and the survey work behind it. Budget for the structural engineer and the asbestos surveyor, which together will dwarf the application fee. The arithmetic is similar to the way the costs stack up in what a Class Q prior approval application costs, where the fee is a small fraction of the total.

Conservation areas and listed buildings

Part 11 does not apply to a building in a conservation area. Demolition of an unlisted building in a conservation area is relevant demolition, needs planning permission, and carrying it out without permission is a criminal offence under section 196D of the Town and Country Planning Act 1990. There is no prior approval shortcut and no deemed consent.

Listed buildings need listed building consent under the Planning (Listed Buildings and Conservation Areas) Act 1990 for demolition in whole or in part, including structures within the curtilage that are treated as part of the listing. Demolition without consent is a criminal offence, and the practice of demolishing first and applying later is both unlawful and, since a court is unlikely to treat the loss as a fait accompli, commercially pointless.

Scheduled monuments need scheduled monument consent, which is a separate regime run by the Secretary of State on advice from Historic England.

Where heritage is engaged, the evidence expected before consent is granted usually includes recording of the building to an agreed level. A pre-redevelopment audit covering materials, hazardous substances and salvageable elements is also increasingly asked for by councils with circular economy policies.

Asbestos and the separate notification regime

Any building constructed or refurbished before 2000 needs a refurbishment and demolition asbestos survey before work starts. That is a duty under the Control of Asbestos Regulations 2012 and sits with the Health and Safety Executive, not the council.

Licensed asbestos removal work must be notified to the HSE, with a statutory notice period before work begins, and the licensed contractor handles that. Non-licensed and notifiable non-licensed work has its own requirements. The planning method statement should record that the survey has been done and that removal precedes demolition, because an authority that reads a method statement silent on asbestos will ask.

The programme effect is the point for budgeting. A survey, a tender, a notification period and the removal itself can take six to eight weeks before the demolition contractor can start on the structure.

Hoardings, highway licences and the street

Demolition next to a public highway almost always needs a hoarding licence from the highway authority under the Highways Act 1980. Scaffolding over the footway, skips on the carriageway and any temporary footway closure each need their own permission, and the highway authority sets the fees and the notice periods.

These are not planning matters, and the planning officer will not chase them. They do appear in the construction management plan that larger schemes submit, which is the document that ties the hoarding line, the wheel washing, the route for muck away lorries and the working hours together.

Allow for utility disconnections too. Electricity, gas, water and telecoms disconnections are ordered separately, each has its own lead time, and a live gas service is an absolute stop on demolition.

Sequencing demolition with the main permission

The most common sequencing error is demolishing before the ecology work is done. Buildings with roof voids, soffits, hanging tiles or cellars can support roosting bats, and all bat species are protected. A preliminary roost assessment and, where triggered, an emergence bat survey during the May to September season is a legal constraint on the programme, not a planning nicety. A licensed ecologist is legally required for the survey work and for any mitigation licence.

The second error is demolishing early to make a site look deliverable, then discovering that the main permission is refused and the site now has no lawful building to fall back on. Where the building has value as a fallback position, or as the basis of a floorspace comparison in a future application, demolishing it throws that away.

Third, check the conditions on the main permission. Pre-commencement conditions often bite on demolition, because demolition can be a material operation. Where a condition requires approval of a construction management plan or an archaeological written scheme of investigation before any works begin, starting demolition in breach puts the whole permission at risk.

You can draft the construction management plan and the supporting statements for a demolition and redevelopment scheme on PlanScope, and see what each report costs on the pricing page at PlanScope pricing.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Do I always need prior notification before demolishing a building?

No. Demolition of buildings with a cubic content of 50 cubic metres or less, and of most gates, fences and walls outside conservation areas, is not development at all. Above that, Part 11 of the General Permitted Development Order requires a prior approval application on the method of demolition and the restoration of the site before work begins.

How long does a Part 11 prior approval take?

The determination period is 28 days from a valid application. Work may begin once the authority confirms prior approval is not required, grants it, or lets the 28 days pass without responding. The deemed consent on expiry is why this route is normally faster than applying for planning permission for the same demolition.

Can I demolish an unlisted building in a conservation area under Part 11?

No. Part 11 does not apply in conservation areas. Demolition there is relevant demolition and needs planning permission, and carrying it out without permission is a criminal offence under section 196D of the Town and Country Planning Act 1990. Expect the council to ask for recording and for a scheme for the cleared site.

Is the Building Act demolition notice the same thing?

No, it is separate. Section 80 of the Building Act 1984 requires notice to the local authority before most demolition, and the authority can serve a counter-notice setting requirements on shoring, weatherproofing adjoining buildings, sealing drains and making good. Budget both the planning prior approval and the Building Act notice into the programme.

What should the demolition method statement contain?

The sequence of works, the plant to be used, temporary support and protection of adjoining structures, dust and noise control, hours of working, the route for removal of material, and how the site will be left afterwards. Where asbestos is present, record that a refurbishment and demolition survey has been carried out and that removal precedes demolition.

Sources and further reading

demolitionprior approvalcostsconservation areaasbestosgpdo

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting6 min read

Screening and scoping opinions cost nothing, so use them

Neither a screening nor a scoping opinion attracts a planning fee, and both narrow what consultants can charge you for. Few tools in the system are better value.

Read article →
Costs, Fees and Budgeting7 min read

Free planning applications for disabled adaptations

The 2012 fee regulations remove the planning fee for works providing access or greater safety, health or comfort for a disabled person, in homes and in buildings open to the public. It must be claimed on the application.

Read article →
Costs, Fees and Budgeting6 min read

The costs that arrive after planning permission is granted

Permission is the start of the spending, not the end. Condition discharge, verification reporting, the levy, section 278 works, Building Regulations and utility connections all arrive after the build cost is fixed.

Read article →
Costs, Fees and Budgeting6 min read

What a biodiversity net gain shortfall costs in credits

Where a scheme cannot deliver its 10 per cent gain on site or off site, statutory credits fill the gap at a published tiered price set deliberately high. The hierarchy, the rounding and the 30 year obligation all affect the budget.

Read article →
Costs, Fees and Budgeting7 min read

Budgeting an application for one to nine dwellings

On a minor residential scheme the evidence base and the survey seasons drive the budget, not the application fee. A stage by stage way to build the cash flow.

Read article →
Costs, Fees and Budgeting7 min read

Budgeting a variation of condition during construction

A departure from the approved drawings breaches a condition. The budget item that matters is the standing time while the amendment or section 73 application runs.

Read article →