Bonds and sureties for landscaping and highway works

7 min readBy PlanScope Editorial Team

Security for landscaping and adopted highway works comes through section 106, section 278 or section 38, never a condition. How bonds are sized, priced and released.

A planning bond for landscaping or highway works is financial security that lets the authority finish the job at your expense if you do not finish it yourself. It is not a fee and it is not a contribution. The money comes back, or the guarantee lapses, once the works are complete and the defects period has run.

What it does cost you is the premium on the instrument, the facility headroom a bank guarantee eats, and the cash tied up where the authority insists on a deposit. On a scheme of 80 units with an estate road to be adopted and five years of landscaping establishment, that is a real line in the appraisal and it is often missed until the agreement is being engrossed.

Why an authority asks for security

Two risks drive it. The first is incomplete work: a developer becomes insolvent with the estate road built to base course and the surface, lighting and footways outstanding, leaving the authority with residents who cannot get a refuse vehicle in. The second is work that fails after completion, most often planting that dies in its first two summers.

Security is the authority's answer to both. A highway authority taking on a road it will maintain in perpetuity wants to know it is not adopting a liability, and a planning officer who has agreed a scheme on the strength of a landscaping plan wants the trees to be there in year five.

A condition cannot normally require you to provide a bond or pay money. Planning Practice Guidance is clear that conditions requiring a financial contribution or other payment are not an appropriate use of the power, so security has to come through an agreement.

That leaves three routes in practice:

  1. A planning obligation under section 106 of the Town and Country Planning Act 1990, used for landscaping maintenance, play area commuted sums and off-site works secured through the planning permission.
  2. An agreement under section 278 of the Highways Act 1980 for works to an existing public highway, where the bond covers the cost of the works the developer is carrying out on the authority's asset.
  3. An agreement under section 38 of the Highways Act 1980 for new roads to be adopted, where the bond stands behind construction until the final certificate is issued.

Where the security comes through a section 106 obligation, it has to satisfy the tests in regulation 122 of the Community Infrastructure Levy Regulations 2010: necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind. A bond demanded for works unconnected to your scheme fails the first and second of those.

Forms of security and what each one costs you

Instrument What it is Where the cost falls
On-demand bank guarantee Bank undertakes to pay on the authority's demand Counts against your facility, so it reduces borrowing capacity and attracts an arrangement and annual fee
Surety bond Insurer or specialist surety stands behind the obligation Annual premium on the bond value, priced on your covenant strength
Cash deposit Money held by the authority or in a joint account Full opportunity cost of the sum for the whole period
Parent company guarantee Group company guarantees performance No premium, but only accepted where the parent's accounts support it

The ranking by cash cost and the ranking by acceptability run in opposite directions. Authorities prefer cash and on-demand guarantees because they are quick to call. Developers prefer surety bonds and parent company guarantees because they leave the facility alone. Most negotiations land on a surety bond from an insurer on an approved list, or an on-demand guarantee from a clearing bank, and the argument is usually about the wording rather than the form.

Read the trigger wording closely. An on-demand instrument pays out on a simple written demand with no requirement to prove default, which is why banks price it as they do. A conditional bond requires the authority to establish the default first, which is better for you and slower for them. Authorities routinely ask for on-demand wording and routinely accept conditional wording where the applicant pushes back with a credible covenant.

Sizing the bond against the works

The figure is normally the estimated cost of the outstanding works plus allowances. The allowances are where the negotiation happens, and they typically cover inflation to the likely date of call, the authority's own supervision and administration, and the premium a replacement contractor would charge to pick up a part-built job.

So the sum often lands meaningfully above the contract value of the works. Three things reduce it honestly.

Stage the security so the bond value steps down as work is certified complete, rather than sitting at its opening figure until the final certificate. Price the works from a tendered figure rather than the authority's rate sheet, where you have one. And separate the landscaping element from the highway element, because they have different durations and the landscaping bond is usually far smaller than a first draft suggests.

An illustrative example: on a 60 unit scheme, an estate road and footways to be adopted under section 38, with a signalised access improvement under section 278 and a landscaped buffer with 40 standard trees. That is three separate pieces of security, with three different release dates, and treating them as one bond at one figure for seven years is what makes the cost look unmanageable.

Release triggers and the defects period

For highway works the sequence is practical completion, a provisional certificate, a maintenance period during which the developer remains liable for defects, then the final certificate and release. The maintenance period for adopted roads is commonly 12 months, and the bond stays in place throughout.

Landscaping runs to a different rhythm. The obligation is usually to replace any plant that dies, is removed or becomes diseased within a stated establishment period, with five years a common figure in section 106 drafting. The security has to last that long, which is why landscaping bonds feel disproportionate to the planting cost.

Diary the release dates when the agreement completes. Bonds that should have been released years earlier sit on company balance sheets more often than anyone would like, because the final certificate was issued to a site manager who left.

Where a bond is not a reasonable requirement

Push back where the works are wholly within your own site, are secured by a condition the authority can enforce directly, and do not involve an asset the authority will adopt. Pushing back also makes sense where the same works are already covered by a section 38 bond and the section 106 draft duplicates the security, or where the amount bears no relation to the works because it was lifted from a standard template.

Regulation 122 gives you the language for a section 106 argument. For a highways agreement the argument is commercial rather than statutory, so it turns on your covenant, the authority's experience with your contractor, and whether you can offer staged release instead.

Putting it in the appraisal

Treat the premium as a cost and the deposit as working capital, because confusing the two distorts the return. Then check three timing points: the date each instrument has to be in place, the date each steps down, and the date each is released. Model the release after the last home is sold where that is the reality, since a bond running past practical completion extends the period over which you are paying for it.

The same discipline applies to the other obligations that attach to a permission. A travel plan and its monitoring contribution is a cost with a defined end date, utilities capacity enquiries are front-loaded, and nutrient neutrality mitigation can be a capital purchase years ahead of a start on site. Pull all of them into one schedule with dates, then feed that into the Viability Assessment rather than discovering them during drafting.

If you are costing the document side of an application, PlanScope pricing is one free report, £50 per report, or Professional at £150 per month for unlimited reports.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can a planning condition require a bond?

Not normally. Planning Practice Guidance treats conditions requiring a financial contribution or other payment as an inappropriate use of the power, so security has to be secured by agreement instead. In practice that means a section 106 planning obligation, or a section 278 or section 38 agreement under the Highways Act 1980.

How is the value of a planning bond calculated?

It usually starts from the estimated cost of the outstanding works, then adds allowances for inflation to the likely call date, the authority's supervision and administration, and the premium a replacement contractor would charge to take over a part-built job. Staged step-downs as work is certified are the most effective way to reduce the exposure.

What is the difference between an on-demand guarantee and a conditional bond?

An on-demand instrument pays out on a written demand without the authority having to prove default, which is why banks price it accordingly. A conditional bond requires default to be established first. Authorities tend to ask for on-demand wording and often accept conditional wording where the applicant has a credible covenant.

How long does a landscaping bond stay in place?

As long as the establishment period in the obligation, which is commonly five years in section 106 drafting, during which failed or diseased planting has to be replaced. That duration is why landscaping security can look large against the planting cost, and it is a separate instrument from any highway bond with its own release date.

When can I argue that a bond is not a reasonable requirement?

Where the works are wholly within your own site, do not involve an asset the authority will adopt, and are already secured by an enforceable condition. Regulation 122 of the Community Infrastructure Levy Regulations 2010 also requires a section 106 obligation to be necessary, directly related to the development and fairly related in scale and kind.

Sources and further reading

planning bondsection 278section 106landscapinghighway worksappraisal

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting7 min read

Outline or full planning application: fees and risk

The reserved matters fee is calculated as if it were a full application, so the outline route rarely saves fees. What it saves is abortive design cost and risk.

Read article →
Costs, Fees and Budgeting6 min read

Screening and scoping opinions cost nothing, so use them

Neither a screening nor a scoping opinion attracts a planning fee, and both narrow what consultants can charge you for. Few tools in the system are better value.

Read article →
Costs, Fees and Budgeting7 min read

Demolition prior notification: cost and when it applies

Demolition is development. Part 11 of the GPDO turns most of it into a 28 day prior approval, but conservation areas, listed buildings and the Building Act notice all sit outside that route.

Read article →
Costs, Fees and Budgeting7 min read

Free planning applications for disabled adaptations

The 2012 fee regulations remove the planning fee for works providing access or greater safety, health or comfort for a disabled person, in homes and in buildings open to the public. It must be claimed on the application.

Read article →
Costs, Fees and Budgeting6 min read

The costs that arrive after planning permission is granted

Permission is the start of the spending, not the end. Condition discharge, verification reporting, the levy, section 278 works, Building Regulations and utility connections all arrive after the build cost is fixed.

Read article →
Costs, Fees and Budgeting6 min read

What a biodiversity net gain shortfall costs in credits

Where a scheme cannot deliver its 10 per cent gain on site or off site, statutory credits fill the gap at a published tiered price set deliberately high. The hierarchy, the rounding and the 30 year obligation all affect the budget.

Read article →