Challenging a CIL liability: review and appeal routes

7 min readBy PlanScope Editorial Team

Request a review of the chargeable amount within 28 days, appeal to the Valuation Office Agency within 60 days, and take surcharges to the Planning Inspectorate within 28 days. None of these periods can be extended.

A Community Infrastructure Levy liability notice is challengeable, and the deadlines are short. Ask the charging authority for a review of the chargeable amount within 28 days of the liability notice being issued, then appeal to the Valuation Office Agency within 60 days of that notice if the review does not resolve it. Surcharges follow a different route, to the Planning Inspectorate, within 28 days of the surcharge being imposed. None of these periods can be extended, and an authority has no discretion to accept a late request.

Most successful challenges are about floorspace rather than policy. The charging schedule rate is not appealable once adopted, and nor is the decision to charge the levy. What is arguable is how much floorspace there is, what deduction applies for existing buildings, and whether a surcharge was properly imposed.

Reviewing the chargeable amount with the authority

Regulation 113 of the Community Infrastructure Levy Regulations 2010 gives the right to request a review. The request goes to the collecting authority within 28 days of the liability notice, and the review has to be carried out by a person senior to whoever made the original calculation and not involved in it.

Keep the request factual. State the figure you say is correct, set out the measurement or the deduction you rely on, and attach the drawings and evidence. A review request arguing that the levy is unfair will be refused, because fairness is not a ground.

The authority notifies its decision, and if the calculation changes it issues a revised liability notice. If it does not change, or the authority does not respond, the Valuation Office Agency route is open. The review is a precondition for that appeal on the chargeable amount, so skipping it loses the appeal.

Appeal grounds and who decides each

Different grounds go to different bodies, and sending an appeal to the wrong one wastes a deadline.

Issue Decided by
Chargeable amount, after a regulation 113 review Valuation Office Agency
Apportionment of liability between owners Valuation Office Agency
Charitable relief or social housing relief decisions Valuation Office Agency
Residential annexe and extension exemption decisions Valuation Office Agency
Surcharges Planning Inspectorate
The deemed date work started Planning Inspectorate
A CIL stop notice Planning Inspectorate

The split follows the subject matter. Valuation questions, including measurement and relief entitlement, go to the valuation body. Procedural and enforcement questions go to the planning appeals body. Both routes are free of charge to the appellant, which is unusual and worth knowing.

The charging schedule itself is examined before adoption, not on appeal. If the rate is wrong for your development type, that argument belonged at examination.

Deadlines that cannot be extended

Write these down at the point the liability notice arrives, because the clock runs from the notice and not from when you read it.

  1. Request a regulation 113 review within 28 days of the liability notice.
  2. Appeal the chargeable amount to the Valuation Office Agency within 60 days of the liability notice.
  3. Appeal a surcharge to the Planning Inspectorate within 28 days of the surcharge being imposed.
  4. Appeal a deemed start date within 28 days of that decision.

Two further points matter. Starting work on the development can close off some appeal routes, so take the decision to challenge before anyone goes on site. And the relief and exemption regime has its own fatal deadlines: a self-build or residential extension exemption has to be claimed and granted before work starts, and the required notice has to be submitted before work starts, or the relief is lost entirely with no appeal on the merits.

That last point generates more lost money than every appeal ground combined. The paperwork sequence is assumption of liability, then the exemption claim and its grant, then the notice that work is starting, then the first material operation. Do them out of order and the saving disappears.

Evidence for a floorspace dispute

Gross internal area is the measure, and the arguments are usually about three things.

What counts as existing floorspace. The deduction for an existing building depends on it being in lawful use for a continuous period of at least six months within a defined window before permission, and on its gross internal area being measured properly. Evidence of use is where these cases are won or lost: business rates records, utility bills, tenancy agreements, photographs, accounts.

Where the measurement line runs. Internal faces of external walls, including internal walls and columns, excluding open external areas. Canopies, voids, plant enclosures and open balconies are the recurring disputes.

Whether a building is a building. A structure the authority has included as new floorspace may be open-sided and therefore outside the measure, and the reverse applies too.

Prepare the appeal as a measured survey with annotated plans showing both calculations side by side, your figure and the authority's, with the difference itemised. A surveyor's measured drawing with areas scheduled by floor carries weight. A spreadsheet with no drawings does not.

Appeals about surcharges separately

Surcharges are penalties for procedural failure, and they are separate from the levy itself. The common ones are failure to assume liability before work starts, failure to submit the notice that work is starting, failure to notify a disqualifying event after relief, and late payment.

The appeal grounds are narrow and factual: that the claimed breach did not happen, that the surcharge was calculated incorrectly, or that it was imposed without the required notice. Arguing that the surcharge is disproportionate will not succeed, because the amounts are set by the Regulations.

Which is why the evidence that matters is documentary. A dated email with the submitted notice attached and a delivery receipt defeats a surcharge for failing to submit it. A recollection does not. Keep the portal receipts and the acknowledgements from the collecting authority in the project file, because a surcharge can arrive many months after the event.

Paying under protest

An appeal does not suspend liability. Payment remains due on the dates in the demand notice, and late payment attracts interest and a surcharge of its own, so withholding payment while an appeal runs converts one dispute into two.

The practical course is to pay in accordance with the demand notice and recover any overpayment if the appeal succeeds, which the Regulations provide for. Where the sum is large enough that paying it would stop the scheme, raise the position with the collecting authority in writing before the due date and ask whether it will agree to hold enforcement pending the appeal. Some will, some will not, and nothing obliges them to.

Instalment policies help here. Many charging authorities publish an instalment policy, and eligibility usually depends on having assumed liability and submitted the notice that work is starting on time. Another reason the paperwork sequence matters.

Cost of the process against the saving

Both appeal routes are free, so the cost is professional time. A measured survey and a surveyor's statement for a floorspace appeal is a few thousand pounds of work on a typical minor scheme. A planning consultant's time on a surcharge appeal is less.

Set that against the sum in dispute. Where the disputed floorspace is 200m² on a schedule charging a three-figure rate per square metre, the arithmetic favours the appeal comfortably. Where the dispute is 20m², it probably does not, and the regulation 113 review alone may be the sensible limit of effort.

Rates are indexed annually, so check the current charging schedule and the index date before working out what is at stake. And budget the cost of the challenge in the appraisal rather than treating it as a surprise, in the same way as the other fees set out in our note on what a planning agent's fixed fee usually includes. Where the levy is large enough to affect scheme deliverability, the viability evidence becomes relevant too, which our note on budgeting a viability appraisal and the review it triggers deals with.

PlanScope drafts the planning documents that sit around a levy question, including the Viability Assessment structure, and you can see the current tiers on PlanScope pricing. Reports should be reviewed before submission, and for specialist technical reports, qualified professional input may be required.

This is general guidance, not legal advice; check the current Regulations and the position with your collecting authority or a qualified professional before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is the deadline to challenge a CIL chargeable amount?

Request a review from the collecting authority within 28 days of the liability notice under regulation 113, then appeal to the Valuation Office Agency within 60 days of that notice. The review is a precondition for the appeal, so skipping it loses the appeal, and neither period can be extended.

Who decides a surcharge appeal?

The Planning Inspectorate, within 28 days of the surcharge being imposed. Surcharges are penalties for procedural failure such as not assuming liability or not submitting the notice that work is starting. The grounds are factual, so documentary evidence of what was submitted and when is what wins them.

Can I appeal the charging schedule rate?

No. The rate and the decision to charge the levy are settled when the charging schedule is examined and adopted, not on appeal. What remains arguable on an individual liability notice is the floorspace measurement, the deduction for existing buildings, relief entitlement and whether a surcharge was properly imposed.

Do I still have to pay while an appeal runs?

Yes. An appeal does not suspend liability, and withholding payment adds interest and a late payment surcharge. Pay in accordance with the demand notice and recover any overpayment if the appeal succeeds, or ask the collecting authority in writing beforehand whether it will hold enforcement pending the outcome.

What evidence wins a floorspace dispute?

A measured survey with annotated plans showing your calculation and the authority's side by side, with the difference itemised floor by floor. For an existing building deduction you also need proof of lawful use for the required continuous period: business rates records, utility bills, tenancy agreements and accounts.

Sources and further reading

cilcommunity infrastructure levyappealsbudgetingfloorspace

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting6 min read

Screening and scoping opinions cost nothing, so use them

Neither a screening nor a scoping opinion attracts a planning fee, and both narrow what consultants can charge you for. Few tools in the system are better value.

Read article →
Costs, Fees and Budgeting7 min read

Demolition prior notification: cost and when it applies

Demolition is development. Part 11 of the GPDO turns most of it into a 28 day prior approval, but conservation areas, listed buildings and the Building Act notice all sit outside that route.

Read article →
Costs, Fees and Budgeting7 min read

Free planning applications for disabled adaptations

The 2012 fee regulations remove the planning fee for works providing access or greater safety, health or comfort for a disabled person, in homes and in buildings open to the public. It must be claimed on the application.

Read article →
Costs, Fees and Budgeting6 min read

The costs that arrive after planning permission is granted

Permission is the start of the spending, not the end. Condition discharge, verification reporting, the levy, section 278 works, Building Regulations and utility connections all arrive after the build cost is fixed.

Read article →
Costs, Fees and Budgeting6 min read

What a biodiversity net gain shortfall costs in credits

Where a scheme cannot deliver its 10 per cent gain on site or off site, statutory credits fill the gap at a published tiered price set deliberately high. The hierarchy, the rounding and the 30 year obligation all affect the budget.

Read article →
Costs, Fees and Budgeting7 min read

Budgeting an application for one to nine dwellings

On a minor residential scheme the evidence base and the survey seasons drive the budget, not the application fee. A stage by stage way to build the cash flow.

Read article →