Costs, Fees and Budgeting

Section 278 highway works: the cost elements nobody budgets

7 min readBy PlanScope Editorial Team

Section 278 of the Highways Act 1980 lets a developer build on the public highway at its own expense, and the authority charges for everything around it. The lines that appear on real accounts and rarely on early budgets.

The works themselves are the smallest part of a section 278 cost. An agreement under section 278 of the Highways Act 1980 lets a developer carry out works on the public highway at its own expense, and the highway authority charges for everything it does around those works: preparing the agreement, checking the design, auditing the safety, supervising the construction, taking on future maintenance of anything non standard, and holding security until the work is certified. Budget the construction estimate and nothing else and you will be short by a wide margin.

Each element is published somewhere. The trick is knowing what to ask for.

The agreement itself and the authority's charges

Before any ground is broken there is a legal agreement to negotiate, and most authorities charge a fee for preparing it plus their legal costs on an indemnity basis. The agreement will define the works, the standards, the programme, the inspection regime, the security and the commuted sums.

Authorities publish a fees schedule covering highway agreements. Rates are frequently expressed as a percentage of the estimated construction cost, with a minimum charge, and they are revised annually. Ask for the current schedule at the first meeting and ask specifically whether the percentage is applied to the works estimate, the approved tender sum or the final account, because the three are not the same number.

Two related consents often arrive with it. A section 38 agreement deals with the adoption of new highway inside the site, and the two are usually negotiated together even though they are separate instruments. A section 184 notice covers a vehicle crossing, which is a smaller process with its own charge.

Technical approval and design development

The authority checks the design and the developer pays for the checking. On anything beyond a simple access that means a technical approval process with submissions, comments and resubmissions.

Price the design properly at the outset. The scheme shown on the planning drawings is a layout, not a construction design, and the gap between the two is where budgets fail. Levels, drainage connections, construction build-ups, street lighting design and calculations, signing and lining, traffic signal design and any structural element all have to be produced to the authority's standards and then checked.

Where the works affect the strategic road network, the national highway authority is the relevant body and operates its own technical approval and agreement processes, with its own charges. Confirm which authority owns the length of road in question before pricing anything.

Road safety audits and designer responses

Road safety audits are a separate cost line and an independent service. A scheme of any substance will need an audit at preliminary design and at detailed design, a further audit on completion of construction, and in some cases a monitoring audit after the works have been open to traffic for a period.

Audit stage When What it costs you beyond the audit fee
Stage 1, preliminary design Before detailed design begins Design changes while they are still on paper
Stage 2, detailed design Before construction Redesign, re-approval, sometimes re-audit
Stage 3, completion After construction, before opening Remedial works on site, the expensive kind
Stage 4, monitoring After a period in service Possible further works under the agreement

Each audit produces problems and recommendations, and the designer has to produce a formal response to each one, agreed with the authority. Exception reports where a recommendation is not accepted take time and are sometimes escalated. The fee for the audit is modest. The cost of what the audit finds is not, and a Stage 3 finding costs an order of magnitude more than the same finding at Stage 1.

So bring the audit forward. An early audit on the planning layout, before the access design is fixed, is the single most effective spend in this whole process.

Supervision, inspection and testing

The authority will supervise and inspect the works, and the charge for that is normally the largest of its fees. It covers site visits, witnessing of tests, review of materials certification and the eventual issue of a certificate of completion.

Expect also to pay for materials testing, for traffic management design and approval, for temporary traffic regulation orders where the works require closures or restrictions, and for any permanent traffic regulation order the scheme needs. Permanent orders carry a consultation process with statutory advertisement and a decision stage that can take months and can fail, which is a programme risk as much as a cost.

Street naming and numbering, the removal of redundant furniture and the alteration of bus stops or crossings all appear on real accounts and rarely on early budgets.

Commuted maintenance sums

This is the element most often missed entirely. Where a developer asks the authority to adopt something that costs more to maintain than the standard specification, the authority will usually require a commuted sum representing the extra maintenance cost over a defined period.

The usual candidates are block paving and other decorative surfacing, street trees and planting, traffic signals, lit bollards and non standard lighting columns, structures such as retaining walls and culverts, and sustainable drainage features within the highway. Each authority sets its own rates and periods, and a scheme designed with a generous palette of materials can carry a commuted sum that rivals the construction cost of those elements.

The design decision and the cost decision are the same decision here. Specify adoptable standard materials unless there is a planning reason not to, and if a design code or a conservation area requires something better, price the commuted sum before you commit to it in a planning document.

Bonds, securities and their duration

The authority takes security for the works so that it is not left with an unfinished highway if the developer fails. That is normally a surety bond or a cash deposit, set at a proportion of the estimated works cost and sometimes above it to cover the authority's cost of completing the work itself.

Three things drive the real cost. The premium or the cost of capital for the duration. The duration itself, which covers the period between the agreement and the final certificate and therefore includes any maintenance period, commonly twelve months after provisional certification. And the release process, which needs chasing, because an unreleased bond carries on costing money long after the road is finished.

Where the works are tied to a Grampian condition requiring completion before occupation, the bond duration and the programme interact with the sales programme, which is the same cash flow problem described in pre-start condition discharge costs on a phased site.

Statutory undertaker diversions

Services under the road belong to the utility companies, and moving them is governed by the New Roads and Street Works Act 1991 rather than by the highway agreement.

The process has its own vocabulary and its own timescales. A budget estimate comes first, then a detailed quotation once the design is fixed, then a programme slot, and the lead times for a diversion are measured in months rather than weeks. Electricity diversions are usually the longest and the most expensive. Costs are apportioned under the statutory rules, so the developer does not always pay all of it, and a specialist is worth paying for on anything complicated.

An illustrative example of a budget structure, with no figures attached. A single new priority junction with footways, a short length of carriageway widening, street lighting and a new crossing involves: the section 278 agreement fee and legal costs, the technical approval fee, detailed design and lighting design, Stage 1 and Stage 2 audits with designer responses, supervision and inspection, a temporary traffic order, a permanent order for waiting restrictions, commuted sums for the lit bollards and two street trees, a bond for 14 months, and a low voltage electricity diversion. Twelve cost lines, one of which is the construction.

List those lines in the appraisal before the planning application is submitted, and get them repriced when the access design changes. Highway costs are also outside the levy regime, so they sit on top of anything payable under the Community Infrastructure Levy, and errors in that liability have their own route of challenge, as challenging a CIL liability sets out. Fix the scope of your consultants' appointments early, in the way capping abortive costs in a consultant appointment describes, because repeated audit cycles are the classic source of unbudgeted fees.

The transport evidence that justifies the access in the first place belongs in a Transport Assessment, and construction phase movements in a Construction Traffic Management Plan.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. Highway design and road safety audits must be carried out by suitably qualified specialists. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What does a highway authority charge for a section 278 agreement?

Most authorities publish a fees schedule covering agreement preparation, legal costs, technical approval and supervision, often expressed as a percentage of the estimated construction cost with a minimum charge. Ask for the current schedule and ask whether the percentage applies to the works estimate, the approved tender sum or the final account.

How many road safety audits will a scheme need?

A scheme of any substance normally needs an audit at preliminary design, a second at detailed design and a third on completion of construction, with a monitoring audit after a period in service in some cases. Each produces problems requiring a formal designer response agreed with the authority.

What is a commuted maintenance sum?

A payment to the highway authority representing the extra cost of maintaining something that is more expensive than the standard specification. Block paving, street trees, traffic signals, lit bollards, structures and drainage features within the highway all commonly attract one. Rates and periods are set by each authority.

How long does a section 278 bond stay in place?

From the agreement until the final certificate, which includes any maintenance period, commonly twelve months after provisional certification. The cost is the premium or cost of capital over that whole duration, and release needs actively chasing because an unreleased bond keeps costing money after the works are finished.

Who pays to move utilities under the road?

Diversions are governed by the New Roads and Street Works Act 1991, not the highway agreement, and costs are apportioned under statutory rules so the developer does not always bear all of them. Lead times run to months, with electricity diversions usually the longest and most expensive element.

Sources and further reading

costs and feeshighwayssection 278road safety auditcommuted sumstransport

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting6 min read

Education contributions and how the formula is built

An education contribution is built from pupil yield factors, a cost per place and a capacity test. Rebuild each input from the authority's published evidence before accepting the total.

Read article →
Costs, Fees and Budgeting7 min read

Serving notice on owners and the searches it needs

If anyone else owns part of the land in your red line, certificate B and a served notice are required before submission. The title searches that make that possible are quick and best done first.

Read article →
Costs, Fees and Budgeting7 min read

Press and site notices: the costs councils recover

Article 15 publicity is the authority's duty, paid for from the application fee. The advertisement costs that land on a developer come from highway orders, late Environmental Statements and performance agreements.

Read article →
Costs, Fees and Budgeting7 min read

Outline or full planning application: fees and risk

The reserved matters fee is calculated as if it were a full application, so the outline route rarely saves fees. What it saves is abortive design cost and risk.

Read article →
Costs, Fees and Budgeting7 min read

Bonds and sureties for landscaping and highway works

Security for landscaping and adopted highway works comes through section 106, section 278 or section 38, never a condition. How bonds are sized, priced and released.

Read article →
Costs, Fees and Budgeting6 min read

Screening and scoping opinions cost nothing, so use them

Neither a screening nor a scoping opinion attracts a planning fee, and both narrow what consultants can charge you for. Few tools in the system are better value.

Read article →