Costs, Fees and Budgeting

Education contributions and how the formula is built

6 min readBy PlanScope Editorial Team

An education contribution is built from pupil yield factors, a cost per place and a capacity test. Rebuild each input from the authority's published evidence before accepting the total.

An education contribution is a sum secured through a planning obligation to fund additional school places generated by new housing. The figure is almost never negotiable in principle, but it is very often wrong in detail, because it is built from three separate inputs that the authority has to evidence: a pupil yield factor applied to your dwelling mix, a cost multiplier per place, and a capacity test showing that local schools cannot absorb the children without new provision. If any of the three is missing, the request fails the statutory tests and should be challenged.

Why the contribution arises at all

Planning obligations under section 106 of the Town and Country Planning Act 1990 must satisfy the tests in regulation 122 of the Community Infrastructure Levy Regulations 2010. An obligation can only be taken into account if it is necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind to it.

Education sits comfortably inside those tests when the evidence is there. New homes generate children, children need places, and if the nearby schools are full the development has created a need that would not otherwise exist. The restriction on pooling more than five obligations towards a single infrastructure item was removed in 2019, so an authority can now collect from many developments towards one expansion project.

Where the authority charges the Community Infrastructure Levy, check whether education is on its regulation 123 style infrastructure list or its current equivalent funding statement. Councils cannot fund the same item twice through both routes, and double recovery is one of the more productive arguments available to an applicant.

Pupil yield factors and dwelling mix

A pupil yield factor is the number of pupils expected per dwelling, usually expressed separately for primary, secondary and post-16, and usually varied by dwelling size.

The mix is what drives the sum. One and two bedroom flats generate materially fewer school age children than four bedroom houses, so an authority that applies a single blended factor across a scheme of mostly small units is overcharging. Ask for the source: most county and unitary authorities publish their yield factors in a developer contributions supplementary planning document or an education strategy, derived from school census data matched against recent completions in their own area.

Questions worth asking about the factors themselves:

  1. What year are they from, and have they been updated since the last census of pupils?
  2. Were they derived locally or borrowed from a neighbouring authority?
  3. Do they distinguish houses from flats, and by bedroom count?
  4. Do they exclude units that cannot generate pupils?
  5. Is affordable housing given a different factor, and if so on what evidence?

That fourth point does real work. Age-restricted accommodation, student accommodation, care provision and one bedroom units generally cannot produce school age occupants, and most published schedules exclude them. If yours does not, say so in writing early.

Cost multipliers per place

The second input is the capital cost of providing a place. Authorities generally take this from Department for Education cost guidance, uprated to current prices, with a regional adjustment and sometimes an abnormals allowance for a constrained site.

Element What to check Common overstatement
Base cost per place Which DfE figure and which year Using a figure already superseded
Inflation uplift The index used and the base date Compounding to a future date with no basis
Regional adjustment Published regional factor Applying a London factor outside London
Abnormals Evidence for the specific school site A flat percentage with no project behind it
Land cost Whether land is actually needed Charged where expansion is within the existing site

Land cost is the one worth close attention. Where a school can expand within its own grounds, there is no land acquisition, and including a land element in the multiplier inflates the sum without justification.

Capacity testing at local schools

This is the step authorities most often present as a conclusion rather than as evidence. The request should be accompanied by forecast capacity and roll figures for the schools in the relevant planning area, showing the position with and without the development, over the period in which the dwellings will be occupied.

Three things to look for. Whether the forecast already includes other committed development, so your scheme is not being charged for need created by someone else's consent. Whether surplus places at a school just outside the stated catchment have been counted, since statutory walking distances rather than informal catchments are the relevant measure. And whether the authority's own expansion programme already addresses the shortfall with funding in place.

A contribution sought for a shortfall that the authority has already funded does not meet the necessity test.

Testing the request against the obligations tests

Work through regulation 122 explicitly in your response. Is the need caused by this development, on the authority's own forecasts? Is the sum proportionate to the pupils this specific mix will generate? Is the money tied to an identified project, with a spend deadline and a clawback provision if it is not spent?

A well drafted obligation names the project or at least the planning area, sets a period within which the money must be committed, and returns unspent funds with interest. Open-ended payments into a general education fund with no project and no deadline are weaker in planning terms and worth resisting.

Where the sum threatens the deliverability of the scheme, the route is a Viability Assessment setting out the full obligation package against the residual value, rather than an argument about the education formula alone. Authorities weigh education against affordable housing when a scheme cannot carry both, and the Affordable Housing Statement needs to tell the same story.

An illustrative example

A scheme of 60 dwellings: 30 one and two bedroom flats, 20 three bedroom houses, 10 four bedroom houses. This example is illustrative only. Applying a blended yield factor to all 60 units produces a markedly higher pupil number than applying banded factors to each group, because half the scheme is small flats. The difference in the final contribution can be the margin between a viable and an unviable scheme, and the only way to find it is to rebuild the calculation from the authority's own published factors rather than accepting the total.

Challenging an unevidenced sum

Do it early and in writing, before the committee report is drafted. Ask for the yield factors with their source and date, the cost multiplier with its base figure and indexation, and the capacity forecast for the named schools. Set out your own calculation using the same published inputs so the officer can see exactly where you differ.

If the authority cannot produce the evidence, say which limb of regulation 122 fails and why. And keep the point live in your statement of case if the application goes to appeal, because an inspector will give a contribution little weight where the need is not demonstrated. Monitoring fees attached to the obligation deserve the same scrutiny, in the same way as a travel plan monitoring contribution.

Budgeting for the obligation package early is the difference between a deal and a stalled consent. For the drafting side of the evidence base, PlanScope pricing covers one free report, fifty pounds per report, or the Professional tier for practices preparing these documents regularly.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How is a section 106 education contribution calculated?

Pupil yield factors are applied to the dwelling mix to give an expected number of primary, secondary and post-16 pupils. That number is multiplied by a capital cost per place, uprated for inflation and adjusted regionally. The authority must also show that local schools cannot absorb the pupils without new provision.

Can small flats be excluded from the calculation?

Most published schedules apply lower yield factors to one and two bedroom units because they generate far fewer school age children, and some exclude them. Age-restricted, student and care accommodation are commonly excluded altogether. If the authority applies a single blended factor across a scheme of mostly small units, ask for the banded figures instead.

What are the statutory tests for an education obligation?

Regulation 122 of the Community Infrastructure Levy Regulations 2010 requires an obligation to be necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind. A contribution sought for a shortfall the authority has already funded fails the necessity test.

Can a council collect both the levy and a section 106 education sum?

Not for the same item. Where the Community Infrastructure Levy is charged and education appears on the authority's infrastructure funding statement, a separate section 106 education contribution risks double recovery. Check the current funding statement and raise the overlap in writing before the committee report is drafted.

Should an education obligation have a spend deadline?

Yes. A well drafted obligation identifies the project or at least the planning area, sets a period within which the money must be committed, and returns unspent funds with interest. Open-ended payments into a general fund with no named project and no deadline carry less weight and are worth resisting.

Sources and further reading

education contributionssection 106planning obligationsdeveloper contributionspupil yield

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting7 min read

Serving notice on owners and the searches it needs

If anyone else owns part of the land in your red line, certificate B and a served notice are required before submission. The title searches that make that possible are quick and best done first.

Read article →
Costs, Fees and Budgeting7 min read

Press and site notices: the costs councils recover

Article 15 publicity is the authority's duty, paid for from the application fee. The advertisement costs that land on a developer come from highway orders, late Environmental Statements and performance agreements.

Read article →
Costs, Fees and Budgeting7 min read

Outline or full planning application: fees and risk

The reserved matters fee is calculated as if it were a full application, so the outline route rarely saves fees. What it saves is abortive design cost and risk.

Read article →
Costs, Fees and Budgeting7 min read

Bonds and sureties for landscaping and highway works

Security for landscaping and adopted highway works comes through section 106, section 278 or section 38, never a condition. How bonds are sized, priced and released.

Read article →
Costs, Fees and Budgeting6 min read

Screening and scoping opinions cost nothing, so use them

Neither a screening nor a scoping opinion attracts a planning fee, and both narrow what consultants can charge you for. Few tools in the system are better value.

Read article →
Costs, Fees and Budgeting7 min read

Demolition prior notification: cost and when it applies

Demolition is development. Part 11 of the GPDO turns most of it into a 28 day prior approval, but conservation areas, listed buildings and the Building Act notice all sit outside that route.

Read article →