Budgeting a planning inquiry appeal: what drives the cost

7 min readBy PlanScope Editorial Team

Section 78 appeals carry no fee, so an inquiry budget is professional time: topics in dispute, witnesses needed and sitting days programmed. How to price those three before instructing anyone, and how to cut them without weakening the case.

There is no fee to lodge a section 78 appeal, so the whole of a planning inquiry appeal cost is professional time. The number is driven by three variables and almost nothing else: how many topics are in dispute, how many witnesses you need to cover them, and how many sitting days the inspector programmes. Get those three down and the budget falls with them. Everything else, including the hotel bills and the transcript, is noise around the edges.

That is the useful way to build the estimate, because it lets you price the case before you have appointed anyone.

Who decides the procedure, and when

You state a preference when you submit the appeal. The Planning Inspectorate decides, against its published criteria, and it can move a case between written representations, a hearing and an inquiry in either direction. Cross-examination is the test that matters. If the case turns on contested expert evidence that needs to be probed, it goes to inquiry. If it turns on planning judgement about matters of fact that are agreed, it does not.

Two practical points follow. First, you may be budgeting for an inquiry you did not ask for, which is an argument for setting the appeal up so that either route works. Second, the decision comes early, and once it is made the timetable is front loaded, with statements of case, proofs, statements of common ground and the conditions discussion all falling before the inquiry opens. The Inspectorate works to published timetable targets measured in months rather than years, so the spend is concentrated.

Proofs of evidence and the witness count

The witness list is the single largest lever. Each witness means a proof of evidence, appendices, a rebuttal in most cases, a summary where the proof runs beyond 1,500 words, preparation for cross-examination, and the days spent in the room.

A typical allocation on a residential appeal looks like this.

Topic in dispute Who normally gives evidence Can it be agreed instead
Planning balance and policy Planning witness No, this is the core case
Highway capacity and access Transport planner Often, through a technical note
Heritage harm Heritage consultant Sometimes, on the level of harm
Landscape and visual effects Landscape architect Rarely where the refusal cites it
Affordable housing and viability Viability surveyor Often, by agreeing inputs
Drainage and flood risk Engineer Usually, by condition

Every row you move into the agreed column removes a proof, a rebuttal and part of a sitting day. That is the exercise to run before you instruct, not after.

Watch for the witness whose evidence is needed for one narrow point. A short written technical note agreed with the council, appended to the planning witness's proof, often does the same work. And where a specialist report already exists from the application stage, the marginal cost is the proof rather than the underlying assessment, which is why a complete application pack is worth paying for first time. A properly argued Planning Statement at application stage gives the planning witness a foundation rather than a blank page.

Counsel, advocacy and who speaks

Appellants at inquiry are usually represented by counsel, and councils increasingly instruct counsel too. The choice is not purely a matter of money. Cross-examining a professional witness is a skill, and so is resisting it.

Where an appeal involves a single topic, agreed facts and a planning witness who is comfortable being questioned, a planning consultant can present the case. Where there are three or more disputed topics, a section 106 to negotiate and a council with counsel, the saving from doing without an advocate tends to be swallowed by the extra days.

Counsel's fees are normally quoted as a brief fee covering preparation and the opening, plus a daily refresher for each sitting day. That structure is why inquiry length matters twice over: it adds refreshers and it adds witness attendance at the same time.

Statements of common ground and round table sessions

The statement of common ground is the least expensive document at an inquiry and the one most often left late. It records what is agreed about the site, the planning history, the development plan, the technical inputs and the conditions. Each agreed item is an item nobody gives evidence about.

Round table sessions do the same work in the room. Conditions and section 106 obligations are routinely dealt with round the table rather than through evidence, which takes hours instead of days. Arrive with an agreed draft set of conditions and a signed or near-signed agreement, and the conditions session shrinks to a tidying exercise. Turning up with neither is how an inquiry gains a day.

Inquiry length and what each day costs

Price the inquiry as a daily rate for the whole team and then multiply. On a sitting day you are usually paying for the advocate's refresher, the witnesses who are being called or who need to be present, the planning consultant running the case, and someone taking a note.

An illustrative example of the arithmetic, with no figures attached. A four day inquiry with four witnesses means four proofs, four rebuttals, four sets of appendices, roughly four witness-days of attendance each spread across the sitting days, four refreshers and four days of consultant time. Agreeing the drainage and viability topics in advance takes it to a three day inquiry with two witnesses, which removes two proofs, two rebuttals, a refresher and a day of everyone's time. The reduction is far more than proportionate, because the fixed preparation cost per witness is the expensive part.

Site visits, accompanied or unaccompanied, add little. Venue hire falls to the council. Travel and accommodation for a team at an inquiry away from home is real money but it follows the day count, so it reduces with the same decisions.

Your exposure to the other side's costs

Costs do not follow the event in planning appeals. Either party may apply for an award, and the test is unreasonable behaviour that has caused the other party to incur wasted expense. The Planning Practice Guidance on appeals sets out the categories, which include withdrawing an appeal late, failing to substantiate a refusal reason and introducing evidence that should have been produced earlier.

Two exposures are worth pricing. Withdrawing an appeal after the council has prepared its evidence is the clearest route to an award against an appellant. Pursuing an inquiry on a case that the appellant's own evidence does not support runs the same risk. On the other side, a council that cannot substantiate a refusal reason, or that abandons one at the inquiry, may be exposed, which is sometimes the reason a refusal reason is quietly dropped in the statement of case.

Judicial review of the decision is a separate budget entirely and is not an appeal. Treat it as a different decision with different advice.

Getting the number down without weakening the case

Reduce the topics before you reduce the resourcing. The order of operations that works is: read the refusal reasons and the officer report, decide which you will fight, agree everything else in writing with the council, then instruct witnesses only for what remains.

Contract for it properly as well. Fixed fees for proofs, a capped number of rebuttal rounds and a clear instruction that further work needs authorisation all help, and the same discipline applies to any appointment, as capping abortive costs in a consultant appointment sets out. Front load the conditions and obligations work, because pre-start condition discharge costs on a phased site will arrive whether you win at inquiry or not.

Finally, test whether an appeal is the right instrument. A revised application with the refusal reasons addressed costs a fraction of an inquiry, and where the dispute is about a liability rather than a permission, the route may be a review or a separate appeal mechanism altogether, as with challenging a CIL liability.

For the application stage documents that keep an appeal narrow in the first place, see PlanScope pricing: one free report, £50 per report, or Professional for unlimited reports.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is there a fee to appeal a planning refusal?

No fee is charged for lodging a section 78 appeal with the Planning Inspectorate. The cost of an appeal is professional time: statements of case, proofs of evidence, advocacy and attendance. That is why the budget tracks the number of disputed topics and sitting days rather than any published tariff.

Who decides whether an appeal goes to inquiry?

The appellant states a preference and the Planning Inspectorate decides against its published criteria. The determining question is whether contested expert evidence needs to be tested by cross-examination. Cases resting on planning judgement over agreed facts are normally dealt with by written representations or a hearing, which cost considerably less.

Do I need counsel at a planning inquiry?

Not always. A single topic appeal with agreed facts and a confident planning witness can be presented by a planning consultant. Where several topics are in dispute, a section 106 needs negotiating and the council has instructed counsel, the money saved by going without an advocate is usually lost again in extra sitting days.

What is a statement of common ground worth?

It is the least expensive document at an inquiry. It records the agreed site description, planning history, development plan position, technical inputs and draft conditions. Every item agreed there is an item nobody gives evidence about, which removes proofs, rebuttals and part of a sitting day each time.

Can the council recover its costs if I lose?

Costs do not follow the event in planning appeals. An award requires unreasonable behaviour that caused the other party wasted expense, and the Planning Practice Guidance on appeals lists the categories. Withdrawing an appeal after the council has prepared its evidence is the clearest exposure for an appellant.

Sources and further reading

costs and feesplanning appealsinquirybudgetingproofs of evidenceplanning inspectorate

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting7 min read

Bonds and sureties for landscaping and highway works

Security for landscaping and adopted highway works comes through section 106, section 278 or section 38, never a condition. How bonds are sized, priced and released.

Read article →
Costs, Fees and Budgeting6 min read

Screening and scoping opinions cost nothing, so use them

Neither a screening nor a scoping opinion attracts a planning fee, and both narrow what consultants can charge you for. Few tools in the system are better value.

Read article →
Costs, Fees and Budgeting7 min read

Demolition prior notification: cost and when it applies

Demolition is development. Part 11 of the GPDO turns most of it into a 28 day prior approval, but conservation areas, listed buildings and the Building Act notice all sit outside that route.

Read article →
Costs, Fees and Budgeting7 min read

Free planning applications for disabled adaptations

The 2012 fee regulations remove the planning fee for works providing access or greater safety, health or comfort for a disabled person, in homes and in buildings open to the public. It must be claimed on the application.

Read article →
Costs, Fees and Budgeting6 min read

The costs that arrive after planning permission is granted

Permission is the start of the spending, not the end. Condition discharge, verification reporting, the levy, section 278 works, Building Regulations and utility connections all arrive after the build cost is fixed.

Read article →
Costs, Fees and Budgeting6 min read

What a biodiversity net gain shortfall costs in credits

Where a scheme cannot deliver its 10 per cent gain on site or off site, statutory credits fill the gap at a published tiered price set deliberately high. The hierarchy, the rounding and the 30 year obligation all affect the budget.

Read article →