Budgeting EIA screening and scoping before you apply
A screening opinion request costs consultant time rather than a fee. Being screened in after validation can push a determination from month four to month twelve.
There is no fee for a screening opinion request, so the eia screening cost that matters is the cost of the information you have to assemble to make the request worth submitting. On a Schedule 2 scheme that usually means a site description, a development description with quantums, a constraints appraisal and a short assessment against the selection criteria, which is a few thousand pounds of consultant time rather than a few hundred.
Budget it as the least costly insurance on the project. Being screened in after you have submitted, rather than before, is the expensive outcome.
When a screening opinion is worth requesting
Screening applies to development in Schedule 2 to the Town and Country Planning (Environmental Impact Assessment) Regulations 2017 that meets or exceeds the applicable threshold or is in a sensitive area. Schedule 1 development always requires assessment and does not need screening.
Request an opinion where any of the following is true.
- The scheme is close to a Schedule 2 threshold, above or below it
- The site is in or adjacent to a sensitive area as defined in the Regulations, which brings lower or no thresholds into play
- The scheme is part of a larger development that could be treated as a single project
- A previous phase on the same land was assessed, or was screened out on a basis that no longer holds
- An objector or consultee has already raised assessment in correspondence
The value of a negative screening opinion is certainty. It is a formal determination that the development is not EIA development, and while it can be revisited if the scheme changes materially, it removes the risk of a late challenge on that ground.
Where you are confident the scheme is well below any threshold and the site is unconstrained, a request is not worth the cost. Where you are within sight of a threshold, it is.
What the request has to contain
The Regulations set out what a screening request must include, and an incomplete request simply delays matters because the authority will ask for the rest.
- A plan sufficient to identify the land.
- A description of the development, including its physical characteristics and location.
- A description of the aspects of the environment likely to be affected.
- A description of the likely effects on the environment, so far as the applicant can assess them.
- Any information the applicant chooses to provide on how effects would be avoided or reduced.
The fourth item is where the work sits. "So far as the applicant can assess them" is an honest standard rather than a loophole, and an authority faced with a bare assertion of no likely effects will either ask for more or screen the scheme in to be safe.
What that means in budget terms: a constraints appraisal using the public datasets, a desk-based view of flood risk, heritage designations, protected sites and species records, air quality management areas and contaminated land history, and a short narrative assessment against the Schedule 3 selection criteria. The underlying constraint checks can be done from the public data tools, and the engineering judgement on top is the cost.
The authority has 21 days to adopt a screening opinion, extendable by agreement. In practice allow six weeks from instructing the work to holding the opinion.
Scoping opinions and what they fix
A scoping opinion under regulation 15 is requested after the development is identified as EIA development, and it records what the authority, having consulted the statutory consultees, considers the environmental statement should cover.
It is optional. It is also the single most useful document in the EIA process, because it fixes the chapter list and, if you ask properly, the methodologies.
Ask the authority to consult the full consultee list rather than a shortlist, because a consultee not consulted at scoping is a consultee who will raise something new later. Ask for methodologies as well as topics, since methodology disputes generate most further information requests. And where you propose to scope a topic out, set out the reason and the evidence rather than asserting it.
Budget for the scoping report itself, which is a substantive document, plus a round of consultee engagement. The authority has five weeks to provide the opinion, again extendable.
| Stage | Statutory period | Fee to the authority | Main cost |
|---|---|---|---|
| Screening request | 21 days | None | Constraints appraisal and selection criteria assessment |
| Screening direction from the Secretary of State | No fixed period | None | Submission and waiting time |
| Scoping request | 5 weeks | None | Scoping report and consultee engagement |
| Environmental statement | Part of a 16-week determination | Application fee only | The assessment work itself |
None of the EIA stages carries a fee to the authority, which surprises people. The money goes to consultants, and the application fee is charged on the ordinary basis for the development.
Screening directions from the Secretary of State
Where you disagree with an authority's positive screening opinion, you can ask the Secretary of State for a screening direction. The direction supersedes the authority's opinion.
Two practical points. There is no fixed period for a direction, so it is a programme risk rather than a fixed delay, and on a scheme with a funding deadline the uncertainty can be worse than preparing the statement. And a direction request needs the same material as the original screening request, prepared to a higher standard, because you are asking a different decision maker to reach the opposite conclusion.
The commercial calculation is usually straightforward. Compare the cost and time of an environmental statement against the cost and uncertainty of the direction route. On a mid-sized scheme where the statement would cost tens of thousands and take four to six months, a direction request is worth attempting. On a scheme where the statement is modest, it rarely is.
The cost of being screened in late
This is the number to put in front of whoever holds the budget.
If the authority screens the scheme in after validation, the application cannot be determined until an environmental statement has been submitted and publicised. That means the assessment work, which on an ecology-constrained site may wait for a survey season, then a 30-day publicity period, then consultee responses, then a 16-week determination period from the point the statement is in. A screening decision in month two can push a determination from month four to month twelve.
Add the sunk cost of a submission that has to be re-publicised, the extended professional appointments, and on an option or a funding facility, the cost of the delay itself. Against that, a screening opinion request costing a few thousand pounds and six weeks looks like the better purchase.
Budgeting the statement that follows
Where the scheme is screened in, the environmental statement is the largest single item in the planning budget, and it has to be prepared by competent experts under the 2017 Regulations.
Build the budget chapter by chapter from the scoping opinion rather than as a lump sum, because that is how the work is procured and it shows you where the cost sits. On most schemes the expensive chapters are transport, ecology, noise and, where relevant, heritage and townscape. Add a contingency for a regulation 25 further information request, because they are common enough to plan for.
The reports that sit alongside the statement also need budgeting. An environmental impact assessment is one of the report types where competent experts are legally required, so PlanScope's draft is a starting point for that team. Several of the supporting assessments, including the transport assessment and the preliminary ecological appraisal, are ones where councils expect a suitably qualified author and professional review is strongly advised.
For the pre-start conditions that follow a consent, and how those costs behave on a phased site, see pre-start condition discharge costs on a phased site.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.
Frequently asked questions
Is there a fee for an EIA screening opinion?
No. None of the EIA stages carries a fee to the local planning authority, and nor does a scoping request or a screening direction from the Secretary of State. The cost is the consultant work behind the submission, principally the constraints appraisal and the assessment against the Schedule 3 selection criteria.
What must a screening request contain?
A plan identifying the land, a description of the development including its physical characteristics and location, a description of the aspects of the environment likely to be affected, a description of the likely effects so far as the applicant can assess them, and optionally information on how effects would be avoided or reduced.
How long does a screening opinion take?
The authority has 21 days to adopt an opinion, extendable by agreement. In practice allow about six weeks from instructing the constraints and criteria work to holding the opinion. A screening direction from the Secretary of State has no fixed period, which makes it a programme risk rather than a fixed delay.
Is a scoping opinion worth requesting?
Usually yes, even though it is optional. It records what the authority and its consultees consider the environmental statement should cover, and if you ask for methodologies as well as topics it fixes the most contested ground. The authority has five weeks to provide it, extendable by agreement.
What does being screened in after submission cost?
A great deal more than a screening request. The application cannot be determined until a statement is submitted and publicised, which means the assessment work, possibly a wait for a survey season, a 30-day publicity period, consultee responses and then a 16-week determination period. A screening decision in month two can move determination from month four to month twelve.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.