Carbon offset funds and how the payment is calculated

7 min readBy PlanScope Editorial Team

An offset payment is the carbon shortfall in tonnes a year, multiplied by a price per tonne, multiplied by a period in years. Each of those three numbers can be argued.

A carbon offset fund payment is what a scheme pays when it cannot meet its carbon target on site. The calculation is simple arithmetic over a long period: the shortfall in regulated carbon dioxide emissions, measured in tonnes a year against the policy target, multiplied by a price per tonne, multiplied by the number of years the policy applies. The result is a single figure secured through a section 106 agreement before permission is issued, and it can run into six figures on a modest block of flats.

Knowing how each of those three numbers is set is how you reduce it.

Why an offset payment arises

Several authorities set a carbon reduction target that goes beyond building regulations, and the most developed version applies in London, where major development is expected to be net zero carbon with a minimum on-site reduction against the building regulations baseline and any remaining shortfall dealt with through a cash payment.

The payment exists because the policy target is often unachievable on site. A deep plan block with limited roof area cannot fit enough renewable generation to close the gap, so the policy allows the residual emissions to be offset financially rather than refusing the scheme.

That makes the offset a fallback rather than an option of first resort. Authorities expect the on-site minimum to be met first, and an energy statement that goes straight to an offset payment without demonstrating what was tried on site usually gets sent back.

How the shortfall is calculated

The shortfall is measured in annual tonnes of regulated carbon dioxide, meaning the emissions associated with fixed building services: heating, cooling, hot water, ventilation, fixed lighting and auxiliary energy. Unregulated emissions from appliances and cooking are normally excluded.

The sequence runs through the energy hierarchy. A baseline is modelled using the compliance methodology for the building type. Demand reduction measures are applied and the saving reported. Efficient supply, including heat network connection where available, is applied next. Renewable generation is applied last. The residual figure after all three stages is compared with the policy target, and the difference is the shortfall.

Two technical points decide the number more than the design does. Which version of the compliance methodology and which carbon factors were used, because grid carbon factors have fallen and the choice changes the arithmetic. And whether the baseline was set correctly, since an overstated baseline produces a flattering percentage saving and an understated one inflates the payment.

The price per tonne and the period applied

The payment is the shortfall multiplied by a price per tonne and then by a number of years. The period in the established London approach is 30 years, representing the assumed life over which the emissions would occur.

The price per tonne is set in policy or guidance. London-wide guidance has recommended a figure per tonne of carbon dioxide, and boroughs may adopt a higher local price supported by evidence, with some setting substantially higher figures. Those prices are reviewed, so take the current figure from the authority's own adopted document or published guidance rather than from an older scheme's section 106 agreement.

Element Where it comes from
Shortfall in tonnes a year The energy assessment, after all three hierarchy stages
Price per tonne Policy or published guidance, locally adopted
Period in years Policy, commonly 30 years
Payment trigger The section 106 agreement, usually before commencement

Run the calculation yourself early. A shortfall that looks like a rounding error in the modelling becomes a real capital cost once multiplied by a price and by three decades.

Securing the payment in an obligation

The payment is secured through a section 106 agreement rather than by condition, because it is a financial contribution. The drafting points that matter in practice:

  • the trigger, which is commonly commencement or a stage before first occupation
  • whether the figure is fixed at permission or recalculated from the as-designed assessment
  • indexation, and which index applies between permission and payment
  • whether any part is refundable if the delivered scheme performs better than modelled
  • what happens on a section 73 variation that changes the energy strategy

That recalculation point is worth pressing. Where the agreement fixes the sum at the planning stage, a design that improves afterwards pays the same. Where it provides for recalculation from a verified assessment at a later stage, improvements reduce the payment, which aligns the money with the outcome.

Keep the offset distinct from the levy. A carbon offset contribution is a site-specific obligation and is separate from the levy regime, and the distinction matters for the tests that apply, as set out in chargeable development under the Community Infrastructure Levy.

What authorities spend the fund on

The money goes into a ring-fenced fund used to deliver carbon reduction elsewhere in the area: retrofitting council housing and public buildings, energy efficiency schemes for households in fuel poverty, heat network extension, renewable installations on public land, and in some areas tree planting and behaviour change programmes.

Authorities publish what they have collected and spent, and those reports are worth reading before a negotiation. A fund with a large unspent balance is a weaker argument for a higher price per tonne than one that has been fully committed.

Monitoring and post-completion reporting

Reporting after completion is increasingly a condition rather than an aspiration. In London the expectation is that actual metered energy use is reported for a period after occupation, which closes the gap between modelled and real performance.

For a design team that changes the risk profile. A scheme that modelled well and performs badly becomes visible, and a developer who agreed to reporting without planning for metering, data collection and submission has an obligation they cannot discharge. Specify the metering strategy at design stage and allocate the reporting duty in the building management arrangements.

Reducing the payment through design

Five moves that reduce a payment, in rough order of effect:

  1. Fabric first. Lower demand reduces the absolute shortfall at every later stage, and it is the only measure that cannot degrade through poor maintenance.
  2. Heat pump selection and system design, because the carbon factor applied to electricity now rewards electrified heating against the baseline.
  3. Maximising photovoltaic area, including on plant enclosures and south-facing facades, with a realistic shading analysis rather than a nominal figure.
  4. Connecting to an existing heat network where one is available and its carbon content is favourable, with the connection agreement evidenced.
  5. Checking the baseline and carbon factors used in the model, which is the least costly correction available and the one most often overlooked.

An illustrative example. A 48 flat scheme models a residual regulated shortfall after the full hierarchy. Applied against a published price per tonne over a 30 year period, the payment sits in the low hundreds of thousands. Adding roof-mounted generation on a plant enclosure and improving the fabric specification removes roughly a third of the residual, and because the obligation provides for recalculation at the as-designed stage, the saving is realised rather than lost. The figures here are illustrative and depend entirely on the price and period a given authority applies.

Where the authority also requires embodied carbon reporting, keep the two exercises consistent. The floor areas, fabric build-ups and services strategy in the whole life carbon assessment and in the energy work should match, and a sustainability statement that pulls the two together saves the officer reconciling them.

This is general guidance, not legal advice, and it does not state the price or period applying in any particular area. Check the authority's adopted policy and current guidance before relying on a figure. For specialist technical reports, qualified professional input may be required. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Browse all 66 report types to see how the energy and carbon documents fit together.

Frequently asked questions

What emissions does the offset payment cover?

Regulated emissions, meaning those from fixed building services: heating, cooling, hot water, ventilation, fixed lighting and auxiliary energy. Unregulated emissions from appliances and cooking are normally excluded. The shortfall is the residual annual tonnage after demand reduction, efficient supply and renewable generation have all been applied.

How is the payment figure built up?

The annual shortfall in tonnes of carbon dioxide is multiplied by a price per tonne set in adopted policy or published guidance, then by a period in years, commonly 30 in the established London approach. Prices are reviewed periodically and some authorities adopt higher local figures supported by evidence.

Is a carbon offset payment the same as the levy?

No. The levy is a charge on chargeable development under its own regulations, while a carbon offset payment is a site-specific obligation secured through a section 106 agreement. The tests and the drafting are different, and the two are accounted for separately by the authority.

Can the payment be recalculated if the design improves?

Only if the agreement says so. Where the sum is fixed at permission, later improvements pay the same amount. Where the obligation provides for recalculation from a verified assessment at a later design stage, improvements reduce the payment, which is worth pressing for during the negotiation.

What do councils spend the fund on?

Ring-fenced carbon reduction work elsewhere in the area: retrofitting council housing and public buildings, efficiency measures for households in fuel poverty, heat network extension and renewables on public land. Authorities publish collection and spend reports, which are worth reading before a negotiation over price.

Sources and further reading

carbon offsetenergy statementsection 106net zerolondon plansustainability

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Glossary

View all →
Glossary6 min read

First Homes: the discount, the caps and the 25% share

First Homes are discounted market sale units secured in perpetuity by a section 106 agreement and a title restriction. The discount, the price cap and the first-charge ordering all shape a scheme's affordable mix.

Read article →
Glossary7 min read

Ransom strip and the ha-ha of access rights

A retained sliver between a site and the highway blocks implementation rather than permission. How ransom strips arise, what the certificates require, and how they are resolved.

Read article →
Glossary6 min read

Section 184 vehicle crossings and the dropped kerb

Section 184 of the Highways Act 1980 governs vehicle crossings over a footway or verge, and it is decided separately from planning permission. When both are needed, the technical objections to expect, and how to sequence the applications.

Read article →
Glossary6 min read

Local Development Orders and when councils use them

Made under sections 61A to 61C of the Town and Country Planning Act 1990, a local development order removes the application stage for development it specifies. What it can grant, how to read its limitations, and what happens when it expires.

Read article →
Glossary6 min read

Lapsed permissions and what to do when time runs out

Once the three-year clock runs out without a lawful start, the permission is gone and section 73 cannot extend it. The options before expiry, the position afterwards, and the policy changes a fresh application now has to meet.

Read article →
Glossary7 min read

Prior approval: what the procedure actually involves

Prior approval under the General Permitted Development Order 2015 asks the council to sign off a short list of matters, not the principle of development. Here is how the procedure, the clocks and the deemed approval provisions work.

Read article →