Gateway One fire statement costs on a relevant building

7 min readBy PlanScope Editorial Team

A gateway one fire statement costs what the fire strategy behind it costs. Design maturity at appointment is the variable you actually control.

There is no planning fee for a fire statement. The gateway one fire statement cost is entirely professional fees, and the figure is driven by how complex the building is, how settled the design is when the fire engineer is appointed, and how many rounds of iteration the Building Safety Regulator's response triggers. The statement itself is a form. The engineering behind it is the expense.

Which is why the question to ask is not what a fire statement costs, but what the fire strategy work costs and when you were going to do it anyway.

When a fire statement is required

Article 9A of the Town and Country Planning (Development Management Procedure) (England) Order 2015 requires a fire statement to accompany applications for relevant development, and makes the Health and Safety Executive a statutory consultee.

Relevant development means development involving a relevant building, and a relevant building is one containing two or more dwellings or educational accommodation, with at least two storeys, that meets the height threshold of 18 metres or seven storeys. The regime has applied to applications since August 2021.

Three points about scope get missed. The requirement attaches to the planning application, so it applies at the point you apply rather than at construction. It applies to applications for development involving such a building, which can include works to an existing one. And the threshold is measured as the legislation and guidance define it, not as the design team casually describes the storey count, so check the measurement convention before concluding you are below it.

A Fire Statement is one of the report types where a professional with the necessary fire engineering competence is required rather than recommended, because the statement makes assertions about the building's fire safety design that only a competent author can responsibly make.

Who is competent to prepare it

The guidance expects the statement to be prepared by a competent person, and in practice that means a fire engineer. There is no single statutory register, so the filter is professional membership, relevant experience of residential buildings above the threshold, and professional indemnity insurance at a level that matches the risk.

Ask three things when appointing:

  • How many gateway one submissions have you prepared for buildings of this height and core arrangement, and what responses did the regulator give?
  • Will you also produce the fire strategy for gateway two, and is the planning stage work reusable in it?
  • What is included in the fee if the regulator's response requires design change, and what is charged additionally?

That third question is the one that determines the real cost. A fee quoted for one submission with no allowance for iteration is a fee that will be exceeded.

The same discipline applies to the rest of the professional team, and fire engineering is frequently outside the scope of a planning appointment, which is one of the exclusions worth checking in what a planning agent's fixed fee includes.

What drives the fee

Cost driver Why it moves the fee
Height and storey count More storeys means more onerous evacuation and firefighting provisions to justify
Number and arrangement of stair cores A single stair building requires a far more detailed justification than a two stair one
External wall construction and materials Balconies, cladding build-ups and insulation choices each need addressing
Site access and appliance routes Constrained urban sites need manoeuvring and hardstanding demonstrated on a drawing
Water supply for firefighting Hydrant provision and mains capacity have to be evidenced, sometimes with the undertaker
Design maturity at appointment An unsettled layout means the work is done twice
Existing building complexity Works to an occupied building bring phasing and existing condition into scope

Design maturity is the variable you control. A fire engineer appointed when the core positions, the stair arrangement and the elevation strategy are settled produces a statement in one pass. Appointed while the massing is still moving, the same engineer produces three versions and bills for all of them.

The regulator's consultation and its timescale

Once the application is submitted, the authority consults the Health and Safety Executive in its building safety role, and the response feeds into the determination.

Programme for longer than the standard consultation period. The regulator can seek further information or an extension of time, and a response that asks questions restarts a cycle of engineer, architect, agent and officer, which is measured in weeks rather than days. On a scheme with a tight funding deadline that cycle is the risk, not the fee.

What reduces the risk is a statement that answers the questions the regulator asks rather than the questions the design team finds easy. Appliance access drawn to scale with swept paths. Hydrant positions and flow evidence. The evacuation strategy stated plainly, with the basis for it. Firefighting shaft arrangement, lift provision and the strategy for people who cannot use stairs.

Design changes that follow the response

This is where the cost sits, and it is architectural rather than fire engineering cost.

The changes that commonly follow are an additional stair or an enlarged core, a revised firefighting shaft, changes to balcony construction and material, repositioned risers, additional appliance hardstanding that reduces developable area, and changes to the external wall build-up that affect the facade appearance and the floor area.

Any of those can move the unit count or the net to gross ratio. A scheme that loses two flats to a larger core has lost revenue permanently, and a scheme that needs a second stair late loses both area and programme.

Note the policy direction here too. The Government has introduced a requirement for a second staircase in new residential buildings above a stated height, with transitional arrangements, so check the current requirement and the transitional position for your scheme before designing a single stair building. A decision to test a single stair arrangement in the current climate needs to be a deliberate one with an informed client.

The cost of a late fire strategy

Gateway one is a planning stage. Gateways two and three under the Building Safety Act 2022 sit with the Building Safety Regulator at building control stage, and a scheme whose fire strategy was assembled thinly for planning meets the consequences there.

The pattern to avoid is a fire statement produced to get past validation, followed by a Fire Safety Strategy at gateway two that contradicts the consented design. Changes needed at that point are expensive because the design is coordinated, the tender is priced and the programme is committed. A material departure from the consented scheme may also need a section 73 application or a fresh permission.

The honest comparison is this: fire engineering input at the planning stage is a cost you can plan. Fire engineering input after gateway two rejection is a cost that arrives with a delay attached.

Programming it with the planning submission

The sequence that works:

  1. Appoint the fire engineer at concept design stage, before the core and stair strategy is fixed, so the strategy shapes the plan rather than reacting to it.
  2. Settle the evacuation strategy, the stair arrangement and the appliance access before the planning drawings are finalised.
  3. Produce the fire statement on the published form, with the supporting drawings, as part of the application pack rather than as a late addition.
  4. Allow a realistic period in the programme for the regulator's response and one round of design response.
  5. Carry the planning stage strategy forward into the gateway two submission rather than starting again.

Budget the same way you would for an environmental screening exercise, where the cost of the process is modest and the cost of getting the answer late is not. The comparison with EIA screening and scoping request costs is close, because both are gateways that look procedural and both reshape schemes when they go the wrong way.

See PlanScope pricing if you want to draft the planning documents around the fire engineer's work rather than duplicating it.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required, and a fire statement requires an author with the necessary fire engineering competence.

Frequently asked questions

When is a fire statement required with a planning application?

Where the application is for relevant development under Article 9A of the Development Management Procedure Order 2015, meaning development involving a building containing two or more dwellings or educational accommodation, with at least two storeys, that meets the 18 metre or seven storey threshold. The Health and Safety Executive is a statutory consultee on those applications.

Is there a separate fee for the fire statement?

No. There is no planning fee attached to the statement itself, so the cost is entirely professional fees for the fire engineering work behind it. The figure depends on building height, core and stair arrangement, external wall construction, site access, water supply evidence and how settled the design is when the engineer is appointed.

Who can prepare a fire statement?

A person with the necessary fire engineering competence, in practice a fire engineer. There is no single statutory register, so check professional membership, experience of residential buildings above the threshold and professional indemnity cover. The statement makes assertions about fire safety design that only a competent author can responsibly make.

How long does the regulator's consultation take?

Programme for longer than the standard consultation period. The regulator can request further information or an extension of time, and a response raising questions starts a cycle involving the engineer, architect, agent and case officer that runs into weeks. On a funding deadline, that cycle is a bigger risk than the fee.

What happens if the fire strategy is left until gateway two?

Changes become far more expensive, because by then the design is coordinated, the works are priced and the programme is committed. A material departure from the consented scheme may also need a section 73 application or a fresh permission. Carry the planning stage strategy forward rather than starting again.

Sources and further reading

fire statementplanning gateway onebuilding safety actcostshigh-risefire engineering

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting7 min read

Serving notice on owners and the searches it needs

If anyone else owns part of the land in your red line, certificate B and a served notice are required before submission. The title searches that make that possible are quick and best done first.

Read article →
Costs, Fees and Budgeting7 min read

Press and site notices: the costs councils recover

Article 15 publicity is the authority's duty, paid for from the application fee. The advertisement costs that land on a developer come from highway orders, late Environmental Statements and performance agreements.

Read article →
Costs, Fees and Budgeting7 min read

Outline or full planning application: fees and risk

The reserved matters fee is calculated as if it were a full application, so the outline route rarely saves fees. What it saves is abortive design cost and risk.

Read article →
Costs, Fees and Budgeting7 min read

Bonds and sureties for landscaping and highway works

Security for landscaping and adopted highway works comes through section 106, section 278 or section 38, never a condition. How bonds are sized, priced and released.

Read article →
Costs, Fees and Budgeting6 min read

Screening and scoping opinions cost nothing, so use them

Neither a screening nor a scoping opinion attracts a planning fee, and both narrow what consultants can charge you for. Few tools in the system are better value.

Read article →
Costs, Fees and Budgeting7 min read

Demolition prior notification: cost and when it applies

Demolition is development. Part 11 of the GPDO turns most of it into a 28 day prior approval, but conservation areas, listed buildings and the Building Act notice all sit outside that route.

Read article →