Work out the section 106 parties leasehold land question from the land, not from the applicant. Section 106 of the Town and Country Planning Act 1990 lets a person interested in land bind that interest, and section 106(3) makes the obligation enforceable against the covenantor and against anyone deriving title from them. So an obligation given by a leaseholder binds the lease and nothing else. The freehold reversion walks away clean, and when the lease ends the authority is left holding a document that binds no one.

Why the obligation binds the land rather than the applicant

A planning obligation is a covenant that runs with the land. That is what makes it useful to an authority and what makes the identification of interests the first job rather than a tidying-up exercise at the end.

An applicant does not need to own the site to apply. Article 13 of the Development Management Procedure Order 2015 requires an ownership certificate, A to D, and notice to anyone with a freehold or a lease with at least seven years unexpired. That notice requirement is a useful prompt, because the people who had to be notified are usually the people who need to be parties.

The obligation can be a bilateral agreement with the authority or a unilateral undertaking. Either way it binds only the interest of the person giving it. A unilateral undertaking from a developer with an option over the site is worth very little if the landowner has not joined in.

Which interests an authority will want bound

Interest Why it matters Usual treatment
Freeholder Holds the reversion, so without them the obligation dies with the lease Party to the deed
Leaseholder carrying out the development The entity that will build and occupy Party to the deed
Mortgagee or chargee A sale under the power of sale may defeat a later obligation Party, or consent with a covenant to be bound
Option or conditional contract holder No present legal estate, but will acquire one Party, with the landowner also bound
Occupational tenants with security of tenure Their interest is unaffected by a landlord's covenant Party only where the obligation affects their occupation
Agricultural tenants Statutory protection may frustrate delivery Identify early, often a party

The chargee point is the one most often missed and the most expensive to get wrong. Where a charge was granted before the obligation was entered into, a lender enforcing its security is not deriving title from the covenantor in the sense section 106(3) contemplates, and may be able to sell free of the obligation. Authorities therefore ask the lender either to be a party or to give a consent and a covenant to be bound by any disposal. Lenders will usually give the consent and will usually resist being a party, and a short covenant on disposal is the compromise that normally closes the gap.

Where an option or a conditional contract is involved

A promoter with an option holds a contractual right, not a legal estate in the land. If the promoter alone gives the obligation, the authority has an obligation binding an interest that may never be exercised.

The standard answer is to make the landowner a party, with the promoter joining as the party carrying the positive obligations. Where the landowner is reluctant, the alternative is an obligation that only takes effect on implementation of the permission, with a restriction preventing development until the landowner has entered into a deed of adherence. Authorities accept that structure where the drafting is tight, because it means no development can lawfully start until every interest is bound.

Watch the timing of a sale. A site sold between the resolution to grant and the completion of the deed is a familiar way for an obligation to be executed by the wrong party, and the problem usually surfaces only when the buyer's solicitor raises an enquiry two years later.

What happens when a party is missing

Four consequences follow, in rough order of how often they bite.

  1. The obligation is unenforceable against the interest that was not bound, so the authority cannot compel delivery from the person who ends up owning the site.
  2. The permission may be challenged as having been granted on a flawed basis, if the obligation was the reason the development was found acceptable.
  3. A buyer's solicitor raises a requisition, and the deal stalls while a deed of adherence is negotiated with an authority whose negotiating position has improved.
  4. Affordable housing delivery fails, because a registered provider will not take units where the obligation structure is defective.

The fix is a supplemental deed, and it is harder than the original. The authority can reasonably ask for more than it asked for first time round, and the parties who were missing have no reason to be helpful. That is a different negotiation from renegotiating obligations on a stalled scheme, where the obligation at least exists and binds someone.

Registration, searches and what a title register shows

Planning obligations are local land charges. They appear in the local land charges register maintained under the Local Land Charges Act 1975, and so they show up in an LLC1 or the local authority search on a purchase.

They are not always noted on the registered title at HM Land Registry, and the absence of a note does not mean the land is free of the obligation. Binding effect comes from the statute and the deed, not from registration. Authorities sometimes also ask for a restriction on the title, which gives a practical control over disposals but is not what makes the obligation bite.

For the drafting team the practical consequence is that you cannot rely on a title register alone. Get official copies, get the filed plan, and get the local land charges search, because an obligation entered into in 2006 on a site that has since been split may still bind the plot your client is buying.

Checking title before the draft is circulated

Do this before the heads of terms are agreed rather than after, because the obligation structure affects what can be promised.

Order official copies of every registered title that touches the red line and the blue line. Compare the filed plans against the application site plan, looking for slivers of land in different ownership, adopted highway, and access strips. Check for charges, options noted as agreements for sale, leases and easements. Then check the ownership certificate on the application form against what the titles show, because a certificate A signed by an applicant who does not own the access strip is a validation problem waiting to surface.

Where affordable units are involved, the structure has to work for the registered provider as well as the authority. Cascade and mortgagee protection wording interacts with who is bound, which is why the drafting is best done alongside the affordable housing cascade mechanism rather than after it. And where highway works are in the package, the parties to the section 278 agreement may differ from the parties to the obligation, a distinction set out in where a section 278 agreement ends and a section 106 starts.

The supporting statements are easier. An Affordable Housing Statement should name the interests and say who will be bound, so the committee report and the deed start from the same facts. Browse all 66 PlanScope report types and start a draft.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can a leaseholder enter into a section 106 agreement alone?

Yes, but the obligation then binds only the leasehold interest. Section 106(3) of the Town and Country Planning Act 1990 makes it enforceable against the covenantor and anyone deriving title from them, so the freehold reversion is unaffected and the obligation falls away when the lease ends. Authorities therefore ask the freeholder to join in.

Does a mortgagee have to be a party?

Not always, but a lender whose charge predates the obligation may be able to sell free of it when enforcing its security. Authorities close that gap either by making the lender a party or by taking a consent with a covenant that any disposal will be subject to the obligation. Lenders usually give the consent and resist full party status.

What if the developer only holds an option over the site?

An option is a contractual right rather than a legal estate, so an obligation from the option holder alone binds very little. The usual structure makes the landowner a party, with the promoter taking the positive obligations. Where the owner will not join, a restriction preventing development until a deed of adherence is completed can work if drafted tightly.

Will a section 106 show up on the title register?

Not necessarily. Planning obligations are local land charges and appear in the local land charges register maintained under the Local Land Charges Act 1975, so they show in the local authority search. They are not always noted at HM Land Registry, and the absence of a note does not mean the land is unencumbered, because binding effect comes from the statute and the deed.

How is a missing party fixed after completion?

By a supplemental deed of adherence, which is harder to negotiate than the original. The authority can ask for more than it did first time, and the previously unbound party has no incentive to cooperate. Buyers' solicitors usually find the problem during a later sale, when the negotiating position sits entirely with the authority.

Sources and further reading

section 106planning obligationsleaseholdtitleaffordable housingprocedure

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Viability, Obligations and Commercial

View all →
Viability, Obligations and Commercial7 min read

Transport contributions and the trip based calculation

Highway authorities build sustainable transport contributions from trip rates and mode share. Understanding how the figure is assembled is the only way to test whether it meets the statutory tests.

Read article →
Viability, Obligations and Commercial6 min read

Affordable housing on a site with a demolition credit

Twelve houses replacing four is twelve gross and eight net. Whether the threshold and percentage are read gross or net can be the whole margin, and the levy applies a separate floorspace test with its own timing trap.

Read article →
Viability, Obligations and Commercial6 min read

Nutrient neutrality mitigation cost in a viability appraisal

In an affected catchment, nutrient mitigation is a condition of consent rather than an enhancement. Price it per dwelling with a dated quotation, and model the securing obligation and the programme delay alongside it.

Read article →
Viability, Obligations and Commercial6 min read

Finance costs and the interest assumption in an appraisal

Finance moves more when you change the model than when you change the rate. Evidencing the debit rate, splitting the fees and showing finance is counted once.

Read article →
Viability, Obligations and Commercial7 min read

Open space and play contributions calculated per bedroom

A per-bedroom contribution is really an occupancy calculation. Which multipliers to check, how commuted maintenance sums work, and the six arithmetic errors to look for.

Read article →
Viability, Obligations and Commercial6 min read

Acquisition costs and stamp duty in a viability appraisal

Acquisition costs are a small line that causes large arguments. The conventional schedule, the stamp duty question, and what to do when the land is already owned.

Read article →